G.R.
No. 201112 - ARCHBISHOP FERNANDO R. CAPALLA, OMAR SOLITARIO ALI and MARY ANNE
L. SUSANO, Petitioners, versus
COMMISSION ON ELECTIONS, Respondent;
G.R.
No. 201121 - SOLIDARITY FOR SOVEREIGNTY (S4S) represented by Ma. Linda Olaguer;
RAMON PEDROSA, BENJAMIN PAULINO, SR., EYELYN CORONEL, MA. LINDA OLAGUER
MONTAYRE and NELSON T. MONTAYRE, Petitioners, versus COMMISSION
ON ELECTIONS, Respondent;
G.R.
No. 201127 - TEOFISTO T. GUINGONA, BISHOP BRODERICK S. PABILLO, SOLITA COLLAS
MONSOD, MARIA CORAZON MENDOZA ACOL, FR. JOSE DIZON, NELSON JAVA CELIS, PABLO R.
MANALASTAS, GEORGINA R. ENCANTO and ANNA LEAH E. COLINA, Petitioners,
versus COMMISSION
ON ELECTIONS and SMARTMATIC TIM CORPORATION, Respondents;
G.R.
No. 201413 - TANGGULANG DEMOKRASYA (TANDEM), INC., EVELYN L. KILAYKO, TERESITA D.
BALTAZAR, PILAR L. CALDERON and ELITA T. MONTILLA, Petitioners, versus
COMMISSION ON
ELECTIONS and SMARTMATIC TIM
CORPORATION, Respondents.
Promulgated:
June 13, 2012
x - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - x
S
E P A R A T E C O N C U R R I N G O P I N I O N
SERENO,
J.:
The
present Rule 65 Petitions challenge the proposed purchase of 80,916 Precinct
Count Optical Scan (PCOS) machines by the Commission on Elections (COMELEC) from
Smartmatic-TIM. They claim that the failure
of the latter to timely and completely exercise the option to purchase the said
units, prior to the expiration of the original given period, removed the legal
basis for the COMELEC to make the purchase without conducting a separate public
bidding. The proposed purchase is
embodied in a Deed of Sale executed by the parties on 30 March 2012 (Deed of
Sale). Under its original 2009 contract
with Smartmatic-TIM,[1]
COMELEC had until 31 December 2010 to exercise the option to purchase 82,200 PCOS
machines, which it was going to lease, and did lease, for use in the 2010 national
and local elections. On 23 September
2010, it partially exercised this option by purchasing 920 of the machines for
the 13 November 2010 Special Elections.[2] Four letters extending the option were sent by
Smartmatic-TIM to COMELEC, and an extension agreement over the option was
entered into by respondents. We will
discuss the legal effects of these letters and agreement subsequently. The issue in these Petitions thus ultimately
boil down to whether the COMELEC committed
grave abuse of discretion in purchasing 80,916[3] PCOS machines from
Smartmatic-TIM without subjecting the purchase to a separate public bidding, considering
that under the terms of the 2009 Contract, the original period within which the
purchase should have been made, already expired?
As will be clearly demonstrated, the
COMELEC has ample authority under the Constitution and the Civil Code to
execute the Deed of Sale, and this Deed of Sale does not violate any provision
of the Government Procurement Reform Act (GPRA), its implementing rules and
regulations (IRR), or any public policy on government contracts; and, thus, the
COMELEC did not commit any grave abuse of discretion to warrant the grant of
the Petitions.
Setting
Aside the Technical Issues
Petitioners
have raised five technical issues regarding the following:
(a) Absence of a
digital signature;
(b) Absence of a
voter verified paper trail;
(c) Existence of
an open port console;
(d) Deactivation
of the ultraviolet marks verification capability; and
(e) Last-minute
reconfiguration of the compact flash disks in 2010.
A
decision on whether the COMELEC can proceed to implement the Deed of Sale need
not hinge on the resolution of these issues for the following reasons:
One, a legal defect in the proposed
sale of the machines can only exist with respect to these technical issues, if
there is a showing that the machines are not fit for the purpose of their
intended use.[4] Absent a showing that the machines cannot
presently perform and cannot be made to perform in a way that satisfies the
requirements of an Automated Election System (AES) as defined by Republic Act
No. 8436, as amended
otherwise known as the Automated Election System Law (AES Law) then
the sale cannot be struck down on that legal point.
Petitioners
are not assailing the results of the 2010 elections. They are not parties to any electoral protest
involving the same. Allegations
regarding the failure of the machines to conform to the requirements of an
acceptable AES are intrinsically relevant only to the various electoral
protests currently lodged with the Presidential Electoral Tribunal[5]
and the House of Representatives Electoral Tribunal. The performance of the machines during the
2010 Elections will have an impact on this case only if petitioners can
demonstrate that these defects (1) fail the technical requirements of an AES;
and (2) were not and cannot be remedied.
We will avoid ruling on the first point so as not to prejudice the
outcome of the electoral protests. On
the second point, however, we can already rule, and hereby rule, that
petitioners have failed to prove it. We
will discuss this point in a later portion of this opinion.
Two, assuming that the burden of proof
to demonstrate the fitness of the machines has shifted to the COMELEC and
Smartmatic-TIM, this burden has been adequately met by respondents. We will discuss this in a later portion
together with our discussion on the first point. For now, let it suffice that the debate among
the Members of the Court focused on the legal issues surrounding the option to
purchase the PCOS machines; they did not consider the technical issues sufficiently
determinative of the disposition of the various Petitions for reasons that will
be evident in a later discussion.
Preliminary Discussion on the Context: The Interface Between Contract Law and Government Procurement
Regulations in This Case
A.
The
Treatment of Options, Extensions of Time for their Exercise, and their Revival Under Contract Law
Had the parties
been both private entities, then there would have been either no legal dispute
on the validity of the exercise of an option that was renewed after its expiry,
or, the legal dispute would have been quite easy to resolve. This is because our law on contracts is quite
straightforward on this matter. It is
our government procurement laws and regulations that have complicated the legal
issues we need to resolve.
First,
the Civil Code is quite emphatic about respecting the autonomy of the wills of
the parties:
Art. 1306. The contracting parties may establish such stipulations, clauses, terms and conditions as they may deem convenient, provided they are not contrary to law, morals, good customs, public order, or public policy.
Among the stipulations
that the parties can agree on is an option granted by one party in favor of
the other (Art. 1324, Civil Code). Samples
of such contractually created options can be found in some articles of the
Civil Code, such as: (a) an option to buy, which is embedded in a lease of personal
property (Art. 1485) and (b) sales on consignment in which the buyer has the
option to return the goods or pay the price thereof (Art. 1502).
Second.
A contract when validly executed has the legal effect of binding the party who
has undertaken to give something or to render some service (Art. 1305). By binding, we mean that a legally enforceable
right is created in favor of the person who is to receive the thing or the service. This right has the force of law between the
contracting parties (Art. 1159, Civil Code).
Conversely, if the person who possesses the right to
demand the performance of the undertaking to give or to render a service, can demand the performance thereof, he or
she can also waive the same. This
waiver has the effect of extinguishing the obligation. A waiver is the abandonment or voluntary forfeiture
of a right. It operates in the same
manner as a condonation or remission of a debt under Articles 1231(3), and 1270-1274
of the Civil Code.
Examples of
valid waivers can be found in the following articles of the Civil Code: (a) a waiver evidenced by the delivery of a
document evidencing a credit (Art. 1271); (b) the waiver of a right to assail a
voidable contract through an act ratifying the contract (Art. 1393); (c) the
waiver of a condition in a sales contract (Art. 1545).
Third,
if an option is conditioned on its exercise within a period, then this
condition that consists in a period or a deadline for its exercise can itself
be waived. In a contract of sale, for
example, where the obligation of either party . . . is subject to any
condition which is not performed, such party may refuse to proceed with the
contract or he may waive performance of
the condition. (Art. 1545, Civil
Code)
Fourth,
this waiver of a condition that consists in a deadline can be made by the party
in whose favor the deadline was constituted. Under Article 1196 of the Civil
Code, [w]henever in an obligation a period is designated, it is presumed to
have been established for the benefit of both the creditor and the debtor,
unless from the tenor of the same or other circumstances, it should appear that
the period has been established in favor of one or of the other. An option
that expires on a fixed date is an obligation with a resolutory period that
take[s] effect at once, but terminate[s] upon arrival of the day certain. An offeror can also always withdraw an option
under Article 1324 of the Civil Code, with the converse implication that he or
she can always extend the period for the acceptance of the offer.
Thus, an option
to purchase exercisable within a fixed period, embedded in a lease contract,
expires after that fixed period, because the lapse thereof is a resolutory
condition that extinguishes the option to purchase. Both
parties can agree to waive the resolutory condition, however, in the form of an
extension of the period for performance, under the very clear provisions of the
Civil Code. This accounts for the
commonness of renewed or revived options in private commercial agreements, such
as leases, sales, joint ventures, intellectual property rights contracts, etc.
The legal
disputes that will arise in these situations would be easy to resolve. Because both parties agreed to revive or
renew an expired option, their agreement binds both of them; and neither can
assail the agreement simply on the ground that the original option period has expired,
and this extension agreement has the force of law between them.
That the parties
have the ability to revive dead or terminated contracts is so basic a rule that
it has consistently and implicitly been understood to be so by this Court. In two
injunction cases, the Court restated its understanding that a dead or
terminated contract can always be revived or renewed by mutual agreement of the
parties.[6]
The termination
of a contract is not like the death of a natural being. It is
the will and the mutual understanding of the parties, rather than the form and solemnities,
that prevail in contract interpretation.
Thus, a contract that on its face expires can, by the mutual contracting
action of the parties, even be pronounced by the court to be continuing simply
because the parties consider it to be so continuing. As the eminent scholar on contracts put it:
In
the construction of an instrument, the intention of the parties is to be
pursued. The true agreement of the parties may be proved, as against the terms
and stipulations appearing in a written contract where a mistake or
imperfection of the writing, or its failure to express the true intent and
agreement of the parties, is put in issue by the pleadings, or there is an
intrinsic ambiguity in the writing. When the true intent and agreement of the
parties is established, it must be given effect and prevail over the bare words
of the written contract.[7]
B.
The
Treatment of Options, Extensions of Time for their Exercise, and their Revival Under
Government Procure-ment Laws
Having
laid down the premises for the intrinsic validity of the revival of expired
options upon mutual agreement of the parties, we shall now need to examine
whether such mutual agreement entered into by the government as vendee contravenes
law, morals, good customs, public order, or public policy.
It
has been alleged by petitioners that the Deed of Sale contravenes the law,
because it violates the mandatory public bidding provisions of the Government
Procurement Reform Act (GPRA).[8]
To
begin with, we will immediately dispose of an isolated claim made in one of the
Petitions that the option to purchase in the 2009 Contract is a void
arrangement in a contract for public procurement.
We
have already clarified that an option to purchase leased equipment is a
recognized stipulation by the Civil Code itself. This legal situation is no different when the
purchaser is a government entity.
Lease contracts with the government are covered by the GPRA.[9]
Although there is no express provision on options to purchase in a lease
contract in the GPRA, its implementing rules specifically point to other
permissible variations of leases, including lease-purchase, lease-to-own and
other similar arrangements. Section 46 of the GPRA/IRR holds thus:
The lease of construction and office
equipment, including computers, communication and information technology
equipment, are subject to the same public bidding and to the processes
prescribed under the Act and this IRR. Lease may also cover lease purchases or
lease-to-own and similar variations.[10]
(Emphasis supplied.)
Options to purchase in leases are implicitly recognized as valid
by the GPRA. In response to a query from
the Armed Forces of the Philippines, it has been opined by the Government
Procurement Policy Board an agency created under the GPRA that a
lease-to-own arrangement over military motor vehicles is valid and subject to
the rule on competitive bidding:
Whether Section 46
of the IRR-A of R.A. 9184 is applicable to the purchase of motor vehicles under
lease-to-own arrangement.
While lease-to-own of motor vehicles is not
contemplated under Section 46 of the IRR-A which specifically relates to
construction and office equipment, Section 5 (k) of the IRR-A expressly defines
goods as including related or analogous services, such as, lease or
purchase of office space, media advertisements, health maintenance services,
and other services essential to the operation of the procuring entity.
Undoubtedly, motor vehicles are essential in the operations of the procuring
entity. In addition, a lease-to-own arrangement is a variant of lease which
involves procurement as defined under Sections 4 and 5 (p) of the IRR-A.
Based on the foregoing, the procurement of motor vehicles under
lease-to-own arrangement is subject to the general rule of competitive bidding
under Section 5
(k) in relation to Section 4 of the IRR-A.[11]
In
the same manner, an option to purchase is a recognized alternative for any
government lease of goods in the international market under the World Trade
Organization Agreement on Government Procurement:
This Agreement applies to
procurement by any contractual means, including through such methods as
purchase or as lease, rental or hire purchase, with or without an option to buy, including any combination of
products and services.[12] (Emphasis supplied.)
An
option to purchase is even advised in one jurisdiction as a preferable condition for any lease of
equipment. In the United States, the Federal Acquisition Regulation System
provides that [i]f a lease is
justified, a lease with option to purchase is preferable.[13]
Next, as in any other ordinary
private contract, the procuring entity is permitted to allow an extension in
the performance of a government contract,
which includes the option to purchase.
The
GPRA IRR recognizes allowable delay, or extension of time, for the delivery of purchased
goods:
Subject to the conditions set
forth below, amendments to order may be issued at any time by the procuring
entity concerned. If any such order increases or decreases the cost of, or the time required for executing any part of the
work under the original contract, an equitable adjustment in contract price
and/or delivery schedule shall be mutually agreed upon between the parties
concerned, and the contract modified in writing.[14] (Emphasis supplied.)
Parties
to a government contract are also free to amend the government contract even
after the award and during the performance of the contract. In the procurement
of goods, supplies or materials, the government can issue amendments to its
order at any time, subject to the consent of the awarded supplier and to the
agreement being reduced into writing. Of course, as jurisprudence would
explain, such amendment must not be material as to affect or alter the terms of
the original competitive bidding.
The
same implementing rules of the GPRA also recognize instances, especially in
infrastructure projects, in which there is a justification for allowing the contracting
private party some extension of time to perform its contractual obligations:
Should the amount of additional
work of any kind or other special circumstances of any kind whatsoever occur
such as to fairly entitle the contractor to an extension of contract time, the
procuring entity shall determine the amount of such extension; xxx Upon receipt
of full and detailed particulars, the procuring entity shall examine the facts
and extent of the delay and shall extend the contract time completing the contract
work when, in the procuring entitys opinion, the findings of facts justify an
extension.[15]
It
is then left to the other contracting party whether to accept the explanations
for the delay and allow an extension or to refuse the explanation.[16]
In
Cities Service Helex, Inc., v. US,[17] the U.S. government was pronounced by the
Court as possessing the right to waive the expiry of contracts. Although
the government earlier terminated a contract for the supply of helium due to an
alleged material breach, it continued to accept and pay for the helium given by
the complaining corporations. The United States Court of Claims therein
ruled that a material breach of the contract only gave the injured party a
right to terminate the agreement, but would not prevent the latter, meaning the
government, from waiving the right to act on the breach and thus continue with the contract performance,
if accepted by the other party:
A
material breach does not automatically and ipso facto end a contract. It merely
gives the injured party the right to end the agreement; the injured party can
choose between canceling the contract and continuing it. If he decides to close
the contract and so conducts himself, both parties are relieved of their
further obligations and the injured party is entitled to damages to the end of
the contract term (to put him in the position he would have occupied if the
contract had been completed). If he elects instead to continue the contract,
the obligations of both parties
remain in force and the injured party may retain only a claim for damages for
partial breach.[18]
In
other words, pursuant to the dominance of the will of the parties in Philippine
contract law, and as illustrated in the U.S. procurement case above, the life
of a government procurement contract depends on the will of the parties, and
the terms on the face of the contract can be superseded by the contrary
exercise of that will.
In
a United States case that will be discussed subsequently, even unexercised options can be availed of after the lapse of the original
period, and a losing bidder cannot assail the belated exercise of that option.
FACTUAL
ANTECEDENTS
Respondent
COMELEC conducted a competitive bidding for the automated election system for
the 2010 national and local elections pursuant to its authority to implement an
automated election system under Republic Act No. 8436, as amended, otherwise
known as the Automated Election System Law (AES Law),[19]
which states:
SEC. 5. Authority to Use an Automated Election
System. - To carry out the above-stated policy, the Commission on Elections, herein referred to as the Commission, is
hereby authorized to use an automated election system or systems in the same
election in different provinces, whether paper-based or a direct recording electronic
election system as it may deem appropriate and practical for the process of
voting, counting of votes and canvassing/ consolidation and transmittal of
results of electoral exercises...In succeeding regular national or local
elections, the AES shall be implemented nationwide.
xxx xxx xxx
SEC. 12. Procurement of Equipment and Materials. -
To achieve the purpose of this Act, the Commission is authorized to procure,
in accordance with existing laws, by purchase, lease, rent or other forms of
acquisition, supplies, equipment, materials, software, facilities and other
services, from local or foreign sources free from taxes and import duties,
subject to accounting and auditing rules and regulations. With respect to the
May 10, 2010 elections and succeeding electoral exercises, the system procured
must have demonstrated capability and been successfully used in a prior
electoral exercise here or abroad. Participation in the 2007 pilot exercise
shall not be conclusive of the systems fitness...
On 18 March 2009, the COMELEC issued a Request for
Proposal (RFP)[20]
for the 2010 Poll Automation Project which consisted of the following:
Component 1: Paper-Based Automated Election System (AES)
1-A. Election Management System (EMS)
1-B. Precinct Count Optical Scan (PCOS) System
1-C. Consolidation/Canvassing System (CCS)
Component 2: Provision for Electronic Transmission of Election Results
using Public Telecommunications Network
Component 3: Overall Project Management
The prospective
bids were described in Part II of the RFP on Intent as bids for a lease with
option to purchase:
The Commission on Elections (COMELEC), through its Bids and Awards
Committee (BAC), is currently accepting bids for the lease, with an option to purchase, of an automated
election system (AES) xxx. (Emphasis supplied)
The terms of the
option to purchase (OTP) were specified in Part V of the RFP on Other
Specifications as follows:
28. The offer shall be for a one-time lease basis for Component 1-A, 1-B
and 1-C.
28.1 An offer for an option to purchase by component to be decided by
COMELEC before December 31, 2010 shall be included by the bidder in its
proposal.
28.2 The price of the
option-to-purchase shall not exceed 50% of the lease price of the equipment.
(Emphasis supplied.)
Only seven
bidders submitted bid proposals, of whom only two were able to satisfy the
eligibility requirements and thus qualified for further evaluation of their
technical and financial proposals. The technical proposals of the two remaining
complying bidders namely, Indra Sistemas/Strategic Alliance
Holdings/Hart InterCivic (Indra) and Smartmatic-TIM were declared qualified. However, upon opening of the financial proposals,
only Smartmatic-TIMs bid for the required 82,200 PCOS machines was qualified.
Indras bid was disqualified, because it was only for 57,231 PCOS machines.[21] A
comparison of the two bids is shown below:[22]
Item |
Budget Estimate |
Smartmatic-TIMs Bid (for 82,200 units) |
Indras bid (for 57,231 units) |
Component 1 |
₱10,923,618,400.00 |
₱6,891,484,742.96 |
₱10,923,307,793.00 |
1-A (EMS) and 1-B (PCOS) |
₱8,220,000,000.00 |
₱4,187,876,280.00 |
₱8,220,000,000.00 |
1-C (CCS) |
₱140,000,000.00 |
₱139,999,999.86 |
₱140,000,000.00 |
Services and Others |
₱1,563,618,400.00 |
₱1,563,618,399.00 |
₱1,563,618,400.00 |
Ballots |
₱1,000,000,000.00 |
₱999,999,064.10 |
₱999,689,393.00 |
Component 2 |
₱200,000,000.00 |
₱199,999,997.51 |
₱200,000,000.00 |
Component 3 |
₱100,000,000.00 |
₱99,999,999.00 |
₱100,000,000.00 |
Total Amount of Bid |
₱11,223,618,400.00 |
₱7,191,484,739.48 |
₱11,223,307,793.00 |
On May 26, 2009,
the COMELECs Special Bids and Awards Committee (SBAC) issued Omnibus SBAC
Resolution No. 09-007 declaring Smartmatic-TIM as the bidder that has
submitted the single complying calculated bid.
After Smartmatic-TIM
complied with post-qualification proceedings, COMELEC thereafter
entered into a lease agreement (the 2009 AES Contract)[23]
with the former. Under the 2009 Contract, Smarmatic-TIM would lease its PCOS
machines to public respondent and render services in connection with their
operation. One of the features of this agreement relevant to the instant
Petitions was the grant to respondent COMELEC of an OTP vis--vis the machines
leased by Smartmatic-TIM,[24] was
an option to be exercised on or before 31 December 2010:
ARTICLE 4
CONTRACT FEE AND PAYMENT
xxx xxx xxx
4.3 OPTION TO PURCHASE
In the event COMELEC exercises its option to purchase
the Goods as listed in Annex L, COMELEC shall pay the PROVIDER an additional
amount of Two Billion One Hundred Thirty Million Six Hundred Thirty Five
Thousand Forty Eight Pesos and Fifteen Centavos (Php2, 130,635,048.15) as
contained in the Financial Proposal of the joint venture partners- SMARTMATIC
and TIM.
xxx xxx xxx
ARTICLE 6
COMELECS RESPONSIBILITIES
xxx xxx xxx
6.6 COMELEC shall notify the PROVIDER on or before 31
December 20 10 of its option to purchase the Goods as listed in Annex L.
Aside from the
option to purchase, there are other major prestations in the 2009 Contract.
These include the purchase of ballots; the provision of allied support services;
the requirement that Smartmatic-TIM furnish a performance security as well as
the warranties of Smartmatic-TIM that all the goods covered would comply with
COMELECs specifications and that the former will provide all software/firmware
upgrades or replacements of any defective components or entire units. There is also
a provision reserving the right of the COMELEC to purchase goods on repeat
order basis whenever the need arises; and to issue variation orders to cover
any increase in quantities, including the introduction of new work items as a
result of a mutually agreed change of plans of the parties.
On 10 May 2010,
the synchronized national and local elections were held using the automated
election system of Smartmatic-TIM, including its 82,200 PCOS machines.
After the 2010
elections and prior to the expiration of the period, respondent COMELEC on 23
September 2010 partially exercised its option under the 2009 Contract and
purchased 920 PCOS machines for the 13 November 2010 special elections to be
conducted in Basilan, Lanao del Sur and Bulacan.[25]
In November
2010, COMELEC Chairperson Jose Melo tendered his resignation effective 31
January 2011, or four years ahead of his scheduled retirement. Not long after,
in February 2011, Commissioners Nicodemo Ferrer and Gregorio Larrazabal would also
retire.
On 18 December
2010, respondent Smartmatic-TIM reminded public respondent COMELEC of the
imminent expiration of the option period, but nevertheless granted the latter
its first three-month extension from 31 December 2010 to 31 March 2011.[26]
However, private respondent received no response from COMELEC regarding its
extension.
In the early
part of 2011, Atty. Sixto S. Brillantes, Jr., Atty. Christian Robert S. Lim and
Mr. Augusto Lagman were appointed as Chairperson and Members, respectively, of
the COMELEC, following the retirement of its previous members.
On 23 March
2011, Smartmatic-TIM again reminded the COMELEC of the option period and the
impending expiration of the extension. It also informed the COMELEC that there would
be a 10% price increase from the 2009 Contract price that was to be maintained
until 30 September 2011.[27]
On 23 September
2011, Smartmatic-TIM wrote a follow-up letter to inquire about the status of
the COMELECs decision on the OTP and reiterated the formers commitment to
extend the period to exercise the OTP until 31 December 2011, but with a 20%
price increase.[28]
On 28 December
2011, a few days before the end of 2011, Smartmatic-TIM again followed up
COMELECs decision on the OTP.[29]
Aside from extending the period for another three months or until 31 March
2012, Smartmatic-TIM dropped the price increase it had imposed in previous
extensions,[30] and outlined the
advantages and benefits to be obtained by COMELEC from exercising the OTP.
The extensions
made by Smartmatic-TIM are summarized as follows:
Extension |
Start of the Period |
Expiry of the Period |
Date of
Smartmatic-TIM Letter Extending the Period |
Price
Escalation |
(Original
Option Period) |
|
(31 December
2010) |
|
|
First
Extension Letter |
01
January 2011 |
31 March 2011 |
18 December
2010 |
No |
Second
Extension Letter |
01 April 2011 |
30 September
2011 |
23 March 2011 |
Yes (10% price
increase from the original 2009 price for 75,000 PCOS units. The price per
unit is therefore increased from ₱20,049.58 to ₱22,054.54) |
Third
Extension Letter |
01 October
2011 |
31 December
2011 |
23 September
2011 |
Yes (20% price
increase from the original 2009 price. The price per unit is therefore
increased from ₱ 20,049.58 to ₱ 24,059.50) |
Fourth
Extension Letter |
01 January
2012 |
31 March 2012 |
28 December
2011 |
No |
Meanwhile, the
General Appropriations Act of 2012 was signed into law.[31]
Although the COMELEC initially proposed a budget of ₱10,436,300,399for the procurement of the 2013 AES through a
lease, it received an approved budget of only ₱7 billion for this particular item. According to the COMELEC,
out of this approved budget for 2012, only ₱2.2
billion is available for purposes of securing an AES for the 2013 national
and local elections, because the balance would need to be allocated to fixed
expenses to run the 2013 elections.[32]
Citing the
budgetary constraints, the COMELEC En Banc promulgated assailed Resolution No.
9376 dated 21 March 2012 and exercised the OTP under its 2009 Contract with
Smartmatic-TIM, subject to three conditions:
NOW,
THEREFORE, the Commission on Elections, by virtue of the powers vested in it by
the Constitution, the Omnibus Election Code, Republic Act No. 9369 and other
election laws, and after finding the exercise of the Option to Purchase most
advantageous to the government, RESOLVED, as it hereby RESOLVES, to exercise its Option to Purchase the PCOS and CCS hardware
and software in accordance with Section 4.3, Article 4 of the AES contract
between the Commission and SMARTMATIC-TIM in connection with the May 10, 2010
National and Local Elections, subject to the conditions that:
1.
The warranties agreed upon under
Articles 4 and 8 of the 2010 AES Contract shall be in full force and effect;
2.
The original price for the hardware and
software covered by the Option to Purchase as specified under Annex L of the
2010 AES contract shall be maintained, excluding the cost of the nine hundred
twenty (920) units of PCOS and related peripherals previously purchased for use
in the 2010 special elections; and
3.
All other services related to the 2013
Automated Election System shall be subject to public bidding. (Emphasis
supplied.)
Commissioners Lim and Lagman dissented from the above-quoted Resolution. In his Additional Arguments for Dissent, Commissioner Lagman cited the failure of Smartmatic-TIM to complete the fixes and improvements required from it and alleged that the critical issues with the PCOS hardware and software had not yet been completely resolved, contrary to the claims of the majority of the Commissioners.[33] In response, Chairperson Brillantes argued that the alleged bugs in the software relied upon by Commissioner Lagman were easily identifiable and definitely correctible.[34]
On 30 March
2012, both respondents mutually agreed to extend the period for the exercise of
the OTP by the COMELEC to 31 March 2012.[35]
On even date, COMELEC duly exercised the extended option and entered into a
Deed of Sale for the purchase of the PCOS machines and CCS hardware and
software for a total amount of ₱1,833,274,457.09,
which was within the COMELECs approved budget of ₱2.2 billion.[36]
The extension of the period for the OTP[37]
and the exercise of the option[38]
were both duly approved by the COMELEC En Banc.
Several days
thereafter, petitioners questioned the validity of the exercise by the COMELEC
of its OTP under the 2009 Contract with respondent Smartmatic-TIM by filing the
instant consolidated Rule 65 Petitions[39]
with this Court.
In
essence, petitioners seek the nullification of the Deed of Sale executed by the
COMELEC and Smartmatic-TIM for the acquisition of the PCOS machines and CCS
hardware and software on the ground that the option period expired way back on
31 December 2010 without COMELEC timely exercising the OTP. Thus, the purchase
of the PCOS machines after the expired period should supposedly be deemed as a
new public procurement, which would require competitive bidding in compliance
with public procurement laws. According to petitioners, the absence of a
bidding process for the purchase of the PCOS machines from Smartmatic-TIM
constituted grave abuse of discretion on the part of COMELEC. Petitioners
likewise assailed the technical capabilities of the purchased PCOS machines,
since these purportedly failed to comply with the minimum requirements of an
automated election system under the AES Law.
DISCUSSION
OF THIS WRITER ON
THE
SUBSTANTIVE ISSUES
I
Do the Unassailed Public Bidding, Award of
Contract and 2009 Contract in Favor of Smartmatic-TIM also Provide Legal Cover for
the Deed of Sale as to Exempt It from the Requirement of a Separate Public
Bidding?
Several observations are in order. There are at least eight (8) distinct
prestations in the 2009 Contract: (1)
lease of goods, (2) purchase of ballots, (3) provision of allied support services,
(4) payment of contract fee, (5) option to purchase, (6) provision of
performance security, (7) observance of warranties, and (8) provisions on
repeat orders and variation orders.
It would be the height of absurdity to posit that the
conduct of eight public biddings is required for each of these eight prestations
to be valid under the GPRA. Instead, the
only sensible position is that the 2009 Contract is a unitary contract, and that
all of its provisions have the benefit of legal cover provided by the
successful and unassailed public bidding conducted on 04 May 2009 and the
consequent award of contract in favor of Smartmatic-TIM.
It has been posited, however, that the OTP, which is the fifth
prestation identified above, expired; thus, there is absolutely no option that
can be exercised anymore. In other
words, once an option to purchase expires in any government contract, it allegedly
cannot be revived anymore without violating the GPRA. To understand the legal impact of this
proposition, we need to analyze the prestations involved in the 2009
Contract. Below is a table showing the
major prestations and their respective expiry dates or conditions:
Table of Expiry of
Prestations of the 2009 Contract
A. By
Express Contract Prestation Provisions |
Expiration |
|
1. Lease of Goods |
1-A:
Election Management System |
|
|
1-B:
Precinct Count Optical Scan |
Delivery, Testing and Acceptance of
the PCOS machines |
|
1-C:
Consolidation/Canvassing System |
Delivery, Testing and Acceptance of
the PCOS machines |
|
2:
Electronic Transmission |
|
|
3:
Over-all Project Management |
Delivery of Over-All Project
Management Report |
2.
Purchase of Ballots |
Print and delivery of ballots |
|
3.
Allied Support Services |
Expiration of the Contract |
|
4.
Contract Fee (Schedule and Mode of Payment) |
Within 30 days from receipt of Final
Report |
|
5.
Option to Purchase |
On or before 31 December 2010 |
|
6.
Performance Security |
To be released within 7 days from
delivery of the Over-All Project Management Report after successful conduct
of the 2010 Elections |
|
7.
Warranties |
If PCOS machines are purchased, 10
years; if CCS hardware and software are purchased, 3 years. |
|
8.
Repeat Order and Variation Orders |
Expiration of the Contract |
|
B. By
the Provisions of the Civil Code on Sales |
|
|
|
Intended lifespan of machines |
|
|
10 years from delivery (Art. 1144,
Civil Code) |
|
C.
By the Provisions of the GPRA IRR
(2009) |
|
|
1.
Performance security (Secs. 39.4 & 39.5) |
Issuance of final Certificate of
Acceptance |
|
2.
Warranty for non-expandable supplies
(Sec. 62.1) (GPRA IRR (2009)) |
Minimum of 1 year |
It
would appear that the prestation on the contract fee has yet to be performed,
as Smartmatic-TIM still has an outstanding claim.[40]
Moreover, the performance security has not been released.[41]
In other words, the 2009 Contract, as a totality, is still very much alive.
An
American case, C.M.P., Inc. d/b/a/ C.M.P.
Corporation v. The United States,[42] illustrates
why options should be considered as an
intrinsic part of the mother contract, and why an original procurement contract
with an option should be considered as unitary:
On February 8, 1985, the procurement division of the Department of
Commerce issued an Invitation for Bids (IFB) No. 50SOL61665 to procure
maintenance services for the Bureau of the Census for Government-owned IBM data
processing equipment located in Suitland, Maryland. The IFB was prepared from
the automated document preparation system of the Department of Commerce, and
embodied the standard clauses utilized for the various procurements of that
Department.
Prices for maintenance services for 14 listed items of equipment
were solicited, to be provided during an initial period, with options to the
Government to extend for additional periods. The IFB specified that the initial
term of contract for services of a continuing nature such as maintenance would
extend to September 30 of the award year, and that additional term periods were
to be at the Government's option. Special contract provision H.1 provided, in
part:
As used in this contract, the phrase Term of the Contract refers
to that period of time for which this contract is valid for the purpose of the
Government exercising certain unilateral rights, such as exercising options for
increased quantity. If this contract results in services of a continuing
nature, as opposed to one time services, such as but not limited to
transportation or installation, then the term of contract shall be from the
date of contract award through September 30 of the Government's fiscal year in
which award is made, subject to the Government's unilateral option to extend
the term of contract. Services of a continuing nature may include, but are not
necessarily limited to lease/rent of equipment, license or lease of software,
maintenance, or on-going system support.
The combination of initial and extended terms was limited to 42
months. Special contract provision H.2 provided:
a. This contract is renewable at the prices stated elsewhere in
the contract, at the option of the Government, by the Contracting Officer
giving written notice of renewal to the Contractor by the first day of each
fiscal year, or funded portion thereof, of the Government, or within 30
days after funds for that fiscal year become available, whichever date is the
later; provided that the Contracting Officer shall have given preliminary
notice of the Government's intention to renewal at least 30 days before
this contract is to expire. Such a preliminary notice of intent to renew shall
not be deemed to commit the Government to renewals. If the Government exercises
this option for renewal, the contract as renewed shall be deemed to include
this option provision. However, the total duration of this contract, including
the exercise of any options under this clause shall not exceed 42 months from
the first day of service(s) covered hereunder.
Provisions in the IFB relative to evaluation of bids explained the
policy reasons for use of the option method of contracting and gave notice that
award would be based on the price for all option periods. Section M(a) stated,
in part:
This solicitation is being conducted on the basis that the known
requirements extend beyond the initial contract period to be awarded, but, due
to the unavailability of funds including statutory limitations on obligation of
funds, the option(s) cannot be exercised at the time of award of the initial
contract. There is a reasonable certainty that funds will be available
thereafter to permit exercise of the options. Because realistic competition for
the option periods is impracticable once the initial contract is awarded, it is
in the best interest of the Government to evaluate options in order to
eliminate the possibility of a buy-in.
Section M(c)(2) provided, in part:
Evaluation of Prices. Offers will be evaluated for purpose of
award by adding the total price of all optional periods to the total price for
the initial contract period covering the initial systems or items. These prices
will be adjusted by the appropriate discount factors shown in this Section M.
Evaluation of option prices will not obligate the Government to exercise the
options.
Section M(f) contained the following notice:
failure to exercise an option(s) shall not obligate the Government
to any charges other than the contract price including exercised options.
The IFB required price information to be supplied by means of
completed unit price tables and by completion of a pricing questionnaire. There
were two tables: (1) pricing tables for equipment to be maintained and (2) a
table for optional extended maintenance service and per-call monthly rates for
service outside the designated principal period of maintenance (PPM). PPM was a
defined term:
Any nine consecutive hours per day, including an official meal
period not to exceed one hour per day, between the hours of 7:00 AM and 6:00
PM, Monday through Friday, excluding holidays observed at the installation.
The unit pricing tables listed and described each item of
equipment, designated the number of units and contained space for insertion of
a price for each item in columns. One column was headed: Monthly Unit Price
PPM and the other column was headed: Monthly Unit Prices Extended PPM.
A synopsis of the solicitation was published in Commerce Business
Daily on December 21, 1984, and 14 companies requested copies of the IFB; eight
companies, including plaintiff, submitted bids. At bid opening, on March 11,
1985, preliminary comparison of the pricing tables indicated that Sorbus, Inc.,
with a bid of $3,076.23 per month, was the low bidder. Sorbus, Inc. was
announced as the low bidder at that time. Plaintiff's representatives at the
bid opening complained that its bid had been erroneously interpreted and that
its bid was $2,975 per month, which made it the actual low bidder. Plaintiff
was told to make a written complaint.
On March 22, 1985, plaintiff's president, by letter, explained the
computations on plaintiff's unit pricing tables and confirmed its contention
that its bid when properly analyzed was for $2,975 per month for the equipment
listed. Thereafter there were discussions between representatives of plaintiff
and defendant, and plaintiff's contentions were considered in the Commerce
Department's general counsel's office.
Plaintiff had completed the pricing tables in a manner that was
not clear on the face of the tables as submitted, and in a manner which was
unexpected by defendant. None of the other bidders had submitted price
information that was calculated on the same basis that plaintiff had used.
During July 1985, the contracting officer reviewed the IFB and the
bids that had been submitted by plaintiff and Sorbus, Inc. The contracting
officer concluded that it would be inappropriate and unfair to accept
plaintiff's explanation of the manner in which its bid had been calculated or
to permit plaintiff to correct the bid it had submitted.
At argument, defendant conceded that the agency had recomputed
column 2 (Monthly Unit Prices Extended PPM) for all bids, for the reason that
the IFB possibly was ambiguous as to that column. Plaintiff does not challenge
defendant's authority to make such recomputations. In this recalculation, the
contracting officer found that, on the basis of the information in column 1 of
plaintiff's table, the total monthly on-call maintenance cost submitted by
plaintiff was $6,425 per month. The recalculation of the bid of Sorbus, Inc.
confirmed the $3,076.23 per month that company had submitted, and that Sorbus,
Inc. had submitted the low bid.
On July 31, 1985, contract No. 50YABC566031 was awarded to
Sorbus, Inc.
DISPOSITION
Plaintiff does not challenge the award to Sorbus, Inc. of a
contract under the IFB for the initial period, April 1September 30, 1985.
Plaintiff seeks to invoke the equitable jurisdiction of this court to enjoin
the exercise of the option to procure maintenance services from Sorbus, Inc.,
during the forthcoming fiscal year, October 1, 1985, through September 30,
1986. Plaintiff's premise is that, as to the period commencing October 1, 1985,
until the option is exercised, no contract is in being between defendant and
Sorbus, Inc., and, accordingly, that a contract had not been awarded on
September 6, 1985, when plaintiff filed its complaint.
Plaintiff argues that an option is a contract in which one of the
contracting parties holds an inchoate power to bring into being a second
contract through acceptance of an offer that contractually has been rendered
irrevocable under certain conditions.
The option that the Government may exercise for the period
commencing October 1, 1985, according to plaintiff, would give rise to a new
contractual relationship between the parties during the later performance
period. Plaintiff argues that, since no contractual relationship presently
exists between Sorbus, Inc. and the Government for that later period,
plaintiff's claim qualifies as a contract claim brought before the
contract is awarded within the meaning of 28 U.S.C. 1491(a)(3).
Plaintiff misconceives the nature of the contractual relationship
that was created between defendant and Sorbus, Inc. on July 31, 1985. That
contract includes an initial term of computer maintenance that is to expire on
September 30, 1985, and it includes provision for renewals of 1 year, with a
maximum of 42 months from July 31, 1985. The options are essential parts of the
total contractual relationship and are in no sense severable from the initial
term as far as the obligations of the parties are concerned. Sorbus, Inc. is
subject to an obligation to provide maintenance services at the contract rates
for a maximum of 42 months. Concurrently, the defendant has a vehicle which
assures it of those services at those prices if it is in its best interest.
The contract that was awarded was
the contract that was intended to result from the IFB on which plaintiff
submitted its bid. The exercise of an option in an existing contract is not
equivalent to the award of a new and different contract; it is an element in
the continuation of a unitary contract package. The decision to exercise an
option is a matter of contract administration, when done in compliance with the
requirements of the federal acquisition regulation. 48 C.F.R. 17.207.
(Emphasis
supplied)
xxx x x x xxx
In this case, the contract that controls the exercise of this
court's equitable jurisdiction was awarded on July 31, 1985, well before
the complaint was filed on September 6, 1985. For purposes of section
1491(a)(3), the exercise of an option in an existing contract is not the equivalent of the award of a new contract.
The use of option
clauses in IFBs and contracts accords with Government policies and procedures.
The use of options is authorized in recognition of the Governments need in certain service
contracts for continuity of operation where there is an anticipated need for
similar services beyond a first contract period. 48 C.F.R. 17.202(d). The use
of options is particularly apt and is frequently used in Government contracts
to obtain maintenance services. x x x
If such contracts
as the above U.S. government contract is
unitary with all its various parts, and the exercise of an option therein is
not to be considered as a new contract ─ especially to benefit
government during periods when it may not have a budget to immediately procure
the intended service ─ then there
is absolutely no reason why the OTP herein should be denied the legal cover
provided by the successful public competitive bidding conducted in 2009. It is false, artificial and too shrill an
argument to say that an expired clause in the 2009 Contract will immediately
deny government a procurement advantage it might otherwise have.
There are two
other related arguments that seek to contradict our position that the OTP is
part of a unitary contract that need not be subjected to a new public bidding, neither
of which is correct.
One,
according to petitioners, the Deed of Sale is a new contract requiring a new
public bidding.
Petitioners
argue that the Deed of Sale between COMELEC and Smartmatic-TIM is a new
contract with a new object and must therefore undergo another bidding in
compliance with the GPRA.[43] But
the Deed of Sale does not contain a new object, as it is in fact pursuant to
the option under the 2009 Contract clearly contemplated by the parties and
included as an integral part thereof, precisely in accordance with the doctrine
in the C.M.P. case.
In claiming that
a new contract is being entered into ─ as opposed to
considering the transaction as merely giving effect to a mere subpart of the
old contract or as a matter of contract administration ─
petitioners are in effect saying that the aforesaid 2009 Contract has been
novated, and that a new contract has replaced it. This argument is plainly wrong.
There
are two kinds of novation. There is express novation when it is so declared in
unequivocal terms[44]
while there is implied novation when there is complete or substantial
incompatibility between two agreements.
In
the present case, there is no express
novation, since the Deed of Sale does not state in clear terms that the
obligations under the 2009 Contract are extinguished and in lieu thereof the
Deed of Sale will be substituted. On the contrary, the Deed of Sale expressly
states that it is being entered into pursuant to the OTP under the 2009
Contract:
WHEREAS,
after public bidding, the BUYER and the SELLER had executed on 10 July 2009 a
Contract for the Provision of an Automated Election System for the May 10, 2010
Synchronized National and Local Elections (AES Contract), a copy of which is
hereto attached by way of reference as Annex A hereof;
WHEREAS,
Article 4.3, among others, of the AES Contract granted the BUYER the option to
purchase the hardware and software listed in Annex L of the AES Contract,
including one (1) lot of EMS Machine, for the total option price of Two Billion
One Hundred Thirty Million Six Hundred Thirty Five Thousand Forty Eight Pesos
and Fifteen Centavos (Php 2,130,635,048.15);
In
fact, the Deed of Sale even incorporates, by way of reference, Articles 4 and 8
of the 2009 Contract; and the warranties thereunder continue to remain in full
force and effect:
The warranties agreed upon by the parties
under Articles 4 and 8 of the AES Contract, including the limitations on
warranties under Article 8.5, shall continue to remain in full force and
effect. Articles 4 and 8 of the AES Contract are incorporated by way of
reference. [45]
Neither
is there an implied novation, since
the Deed of Sale is not incompatible with the 2009 Contract. Changes that breed incompatibility must be
essential in nature and not merely accidental. The incompatibility must take
place in any of the essential elements of the obligation, such as its object,
cause or principal conditions.[46]
Neither is there
substantial change in the principal conditions resulting in a novation.
Jurisprudence has consistently held that a mere extension or renewal of a
period does not novate a contract.[47] What is sought to be performed is still the
old contract or, more specifically, a part of it. In other words, the option herein
is merely being allowed
to be given effect vis--vis
the mother contract or
the 2009 AES Contract, which has not been novated and
still subsists. Therefore, there is no new contract. Consequently, there is no
need for a new bidding.
In some cases,
the Court deemed changes that were considerably more substantial than a mere
extension of time as insufficient to create incompatibility that would result
in an implied novation. For instance, additional interest was not deemed
sufficiently substantial to create incompatibility.[48]
Two,
petitioners allege that the Deed of Sale is a substantial amendment of the 2009
Contract that requires a new public bidding.
Amendments of government contracts, per se, are not prohibited. It is when an amendment is so substantial as
to effectively alter the terms of the bid that the amendment can be struck down
if it is not covered by a separate public competitive bidding. Public biddings would not be competitive if a
bidder, after winning the contract, can abruptly and substantially change the
original parameters of its obligations under the government contract, to the
prejudice of the losing bidders. Otherwise, nothing would prevent unscrupulous
bidders from lowballing their bids and promising the world, only to attempt to change
the terms of the contract midstream after the government has awarded them the
contract.
The logic of this principle was
well-discussed in the seminal case Agan,
Jr., v. PIATCO.[49] The
Court struck down the 1997 Concession Agreement between the government and the
Philippine International Airport Terminals, Co. (PIATCO), because the
amendments made to the government contract for the construction of the Ninoy
Aquino International Airport International Passenger Terminal III were
substantial. These changes included new terms and conditions that provided
financial benefit to PIATCO, which could have altered the technical and
financial offer of the other bidders had they known that such terms were
available. The amendments to the originally bidded contract proposal included
modification of the public and non-public utility revenues that may be
collected by PIATCO and the inclusion of a direct guarantee by the Republic of the
liabilities of PIATCO in case the latter defaulted on them. The Court, through
then Justice Reynato S. Puno, succinctly ruled that any substantial amendment
to a government contract would contravene the very rationale for open and
competitive bidding and would result in turning the exercise into a farce:
An
essential element of a publicly bidded contract is that all bidders must be on
equal footing. Not simply in terms of application of the procedural rules and
regulations imposed by the relevant government agency, but more importantly, on the contract bidded upon. Each bidder must be able to bid on the same
thing. The rationale is obvious. If
the winning bidder is allowed to later include or modify certain provisions in
the contract awarded such that the contract is altered in any material respect,
then the essence of fair competition in the public bidding is destroyed. A
public bidding would indeed be a farce if after the contract is awarded, the
winning bidder may modify the contract and include provisions which are
favorable to it that were not previously made available to the other bidders.[50]
(Emphasis supplied.)
In Information
Technology Foundation of the Philippines v. COMELEC,[51]
the Court was confronted with a petition to cancel a billion-peso contract
entered into by COMELEC with Mega-Pacific for, oddly enough, the automation of
the counting and canvassing of the ballots in the 2004 elections. The Court
found that COMELEC awarded the contract to Mega-Pacific with inexplicable haste
despite the latters non-participation in the public bidding process, and that
it had even failed to adequately qualify under COMELECs own financial,
technical and legal requirements. In striking down the contract with
Mega-Pacific, the Court ruled that COMELEC violated the policy on public
biddings, especially when the latter allowed the winning bidder to alter the
contract:
At
the very outset, the Court has explained that Comelec flagrantly violated the
public policy on public biddings (1) by allowing MPC/MPEI to participate in the
bidding even though it was not qualified to do so; and (2) by eventually
awarding the Contract to MPC/MPEI. Now, with the latest explanation given by
Comelec, it is clear that the Commission further desecrated the law on public
bidding by permitting the winning bidder to change and alter the subject of the
Contract (the software), in effect allowing a substantive amendment without
public bidding.
This
stance is contrary to settled jurisprudence requiring the strict application of
pertinent rules, regulations and guidelines for public bidding for the purpose
of placing each bidder, actual or
potential, on the same footing. The essence of public bidding is, after
all, an opportunity for fair competition, and a fair basis for the precise
comparison of bids. In common parlance, public bidding aims to level the
playing field. That means each bidder must bid under the same conditions; and
be subject to the same guidelines, requirements and limitations, so that the
best offer or lowest bid may be determined, all
other things being equal.
Thus,
it is contrary to the very concept of public bidding to permit a variance
between the conditions under which bids are invited and those under which
proposals are submitted and approved; or, as in this case, the conditions under
which the bid is won and those under which the awarded Contract will be
complied with. The substantive amendment of the contract bidded out, without
any public bidding after the
bidding process had been concluded is violative of the public policy on
public biddings, as well as the spirit and intent of RA 8436. The whole point in going through the public
bidding exercise was completely lost. The very rationale of public bidding was
totally subverted by the Commission.[52]
In sharp contrast, the extension of time
for the exercise of the purchase option under the 2009 Contract is not a
substantial amendment that would render the other qualifying bidders
disadvantaged. The issue of substantial
amendment of the awarded contract for the AES can be framed in this wise: would
stretching the period for the COMELEC to exercise the OTP from 31 December 2010
to 31 March 2012 have given an unfair advantage in favor of Smarmatic-TIM and
unduly prejudiced the other qualifying bidders? The answer is no.
In this particular case, the period for
exercising the purchase option in the lease arrangement is insignificant, as it
does not materially promote the position of the winning bidder vis--vis that of the other
bidders. In fact,
petitioners conceded that, had the alteration of the period been mutually
agreed upon before the original deadline set in the 2009 AES Contract, no legal
issue would have arisen:
JUSTICE ABAD
Since
that option to purchase is part of the lease agreement awarded as a result of
competitive bidding, why should the exercise of that option still require
competitive bidding?
ATTY. ESPEJO
Because
the option has expired, Your Honor.
JUSTICE ABAD
But
supposing it was extended, the option is validly extended, it would be alright?
ATTY. ESPEJO
The
extension must be in accordance with the procurement law. In other words, it
must refer to the same subject matter.
JUSTICE ABAD
Well yes, assuming that it is done
properly, would the agreement to lease with option to purchase be valid?
ATTY. ESPEJO
It
will be valid, Your Honor.[53]
(Emphasis supplied)
The above exchange only emphasizes the nature of
the extension of the period as one that is not an intrinsically prohibited
amendment as would amount to a substantially modified contract. Despite the lapse of the original OTP period
and the delay in the exercise of the purchase option by the COMELEC,
Smartmatic-TIM not only allowed the extensions but maintained the same purchase
price the latter had originally bid out. Hence, Indra, the other qualifying
bidder, cannot claim unfair treatment, since it could not have offered superior
price terms based on its submitted bid in 2009. Smartmatic-TIM did not insist on a higher
purchase price from what was originally set in the 2009 Contract, which was
pegged at ₱2,130,635,048.15.[54]
Under the Deed of Sale,[55]
COMELEC would only be paying for ₱1,833,274,457.09
for the remaining units (minus the 920 units earlier purchased and those that have
been lost or have become unserviceable), subject to a hardware acceptance test.[56]
If any disadvantage resulted from the
extension of the OTP period, it was against the interest of the winning bidder,
Smartmatic-TIM. Allowing the COMELEC to vacillate in its decision on whether to
exercise the OTP was not without financial cost to Smartmatic-TIM. From 01
January 2011 to 30 March 2012, the latter shouldered the costs of storing and
maintaining the PCOS machine units. It
did not pass on these costs during the period of COMELECs indecision.
We have demonstrated that the OTP is
an intrinsic part of the 2009 Contract and should thus be covered by the legal
protection of the public bidding conducted in 2009.
The next question that should be asked
is whether that legal protection can extend to the purchase under an option
that has previously expired. To answer
this question would require examining the exchanges of communication between the
parties on the extension of the option period.
The
exchange of letters between the COMELEC and Smartmatic-TIM outlined below
strongly evinces the indubitable mutual intention of the parties to continually
negotiate the formers exercise of the OTP granted to it, including their
intention to continually extend the option period to allow the negotiation. Thus, the option period never expired.
Significantly, in none of the letters did COMELEC show any intention to
repudiate the extensions granted to it by Smarmatic-TIM; much less, to
repudiate the formers right to exercise the option itself.
The
first of four extension letters was
sent to COMELEC by Smartmatic-TIM on 18 December 2010. In the letter, the
company reminded the COMELEC of the impending expiration of the option period
on 31 December 2010 and assured the latter that it understood that COMELEC is
still finalizing its evaluation of the automated election system, in order [for
the Commission] to make a decision on the Option to Purchase. Smartmatic-TIM then
informed COMELEC that it was granting the latter its first three-month
extension from 31 December 2010 to 31
March 2011 in order to allow the Commission to meet [sic] its decision
regarding the option to purchase on the PCOS machines.[57] As
an added concession, the company said that it was waiving the storage cost, as
well as the maintenance cost related to keeping the machines in the Philippines.
On 23 March
2011, Smartmatic-TIM sent a second
letter of extension to the COMELEC informing the latter of the impending
expiration of the first extended option period on 31 March 2011. It also
informed COMELEC of a 10 percent increase in the price of the PCOS machines to
be maintained until 30 September 2011.[58] Alternatively,
it was offering COMELEC a right of first refusal effective until 31 December
2011, for which there would be no price escalation for the PCOS machines.
However, COMELEC was to pay for the warehouse and security costs for the
machines until 31 December 2011. The COMELEC was reminded that if it did not
purchase the PCOS machines, it would be sacrificing significant financial savings.
On 30 March
2011, within a week of receiving the second extension letter from
Smartmatic-TIM, the COMELEC, through Commissioner Rene Sarmiento, wrote a
formal clarification letter on the aforesaid options outlined in the second
letter. The latter sought a clarification
of whether the company would still absorb the warehousing costs if the
Commission exercised the option by 30 September 2011, among other things. It
then requested Smartmatic-TIM to set a date to continue our discussions and
negotiations on or before 31 March 2011 xxx.
In response to
the clarifications sought by COMELEC, Smartmatic-TIM wrote a letter dated 1
April 2011 explaining the offers it made to COMELEC in the companys second
letter of extension dated 23 March 2011. Smartmatic-TIM reiterated that,
beginning 1 April 2011, there would be a price increase of 10 percent to be
maintained until 30 September 2011. It also said that the warehousing costs would
be paid separately by COMELEC. It assured the COMELEC that the former was
still very interested in COMELEC exercising the option to purchase... and
would be willing to maintain the original 2009 prices until December 2011 in a
right of first refusal arrangement. It also outlined the benefits of exercising
the OTP.
On 23 September
2011, Smartmatic-TIM sent COMELEC the third
letter extending the option period to 31 December 2011. However, there
would be a 20 percent price increase. It also said that after the new extended
period, it would update COMELEC if we are willing to further extend the
option, and if any price increases were to be decided on by our corporate
headquarters. It then outlined again the benefits of exercising the option.[59]
On 28 December
2011, Smartmatic-TIM sent its fourth
letter of extension to COMELEC.[60] Aside
from again granting an extension on the option to purchase for another three
(3) months or until 31 March 2012, the
company also dropped the price increase it had imposed in previous extensions.[61] Furthermore,
Smartmatic-TIM also outlined the advantages and benefits to be obtained by
COMELEC from exercising the OTP. Additionally, it offered to provide the
additional PCOS machines that it heard COMELEC would need if the latter would increase
the number of poll precincts.
The exchange of
letters above clearly shows the intention of the parties to extend the option
period to allow them to continue their negotiations for COMELECs exercise of
the OTP. Thus, the option period never expired.
In fact, the
intention of the parties to extend the period for the exercise of the OTP by
the COMELEC to 31 March 2012 was finally formalized and embodied in an extension agreement signed on 30 March 2012.
In the said agreement, the parties noted that while such extension normally
leads to an increase in the price of the hardware and the software, subject of
the option to purchase, due to warehousing and maintenance costs, the PROVIDED
[Smartmatic-TIM] offered to sell them at the same price [2009 AES Contract]
without such increase.[62]
If we were to use the analysis in Helex, and go by the principles
continually stated in Philippine cases, a government procuring entity need not
treat the expiry of the period, or even a material breach of the contract, as a
bar to waiving the right to continue the contract, provided that the other
party agrees. In Helex, the continued supply of helium by the private corporation
and the continued ordering of supplies by the government, despite the notice of
termination earlier sent by the latter, was considered as evidence that the
contract continued to be alive.
So also, the exchange of communication
by the parties indicates (1) that Smartmatic-TIM did not want the option to expire
and was in fact unilaterally extending it several times; and (2) that COMELEC
was contemplating making use of the option but, for different reasons, was not
in a position to immediately and definitively arrive at a decision on the
manner. In other words, neither of the parties wanted to demand the
termination of the option, and both of them eventually waived the expiry of the
original option period.
In the face of this evidence, the Court
cannot conclude that the option period, given the contrary intervention of the
parties, has already expired.
Even assuming arguendo that the option period has expired, this Court, under the
circumstances, cannot deny the revived option the benefit of the successful
bidding conducted in 2009. This matter will
be discussed in the immediately succeeding portion.
II
Did
the COMELEC Commit Grave Abuse of Discretion in Executing the Deed of Sale?
We have already ruled that the period to exercise the
option to purchase, under the principles of contract law, was extended by the
mutual agreement of the parties.
We have also posited that, even assuming that the period to
exercise the option has expired, the parties have agreed to revive the option,
and this revived option is valid. While
this principle finds ready application to private parties, it is also
applicable to a government contract, provided that other relevant laws are not
violated, and government is not placed at a disadvantage. We hold this to be so, and because of the
circumstances surrounding the revival of the option in this case, the revival
herein is valid.
We now also rule that the COMELEC did not commit grave
abuse of discretion in executing the Deed of Sale, and that the successful
bidding in 2009 satisfies the requirement of the GPRA; again, only because of
the unique circumstances of this case.
COMELEC Could Not Have Been Legally Required to Commit
to Availing or Not Availing Themselves of the Option Before the Original Expiry
Thereof on 31 December 2010.
A test of grave abuse of discretion
here could be propounded thus: Were then COMELEC Chairperson Jose A. Melo and
Commissioners Rene V. Sarmiento, Nicodemo T. Ferrer, Lucenito N. Tagle,
Gregorio Y. Larrazabal, Armand C. Velasco and Elias R. Yusoph remiss in their
lawful duties if they failed to exercise the option to purchase before it
expired on 31 December 2010? Another way of putting it is: could they be
justified in failing to immediately act on the option if as these COMELEC
members claim, the exercise of the option is after all advantageous to the
Republic?
While procurement laws seek
to prevent abusive exercise of discretion, they do not unreasonably require
government agencies to abandon their duty to exercise care and good judgment.[63]
In this case, the decision to purchase the PCOS machines under the OTP was
actually an exercise of sound discretion afforded to the COMELEC to implement
our electoral laws, given the limited circumstances and the viable options open
to it at that time.
For petitioners to
singularly target the fact that the OTP had already lapsed without COMELEC
exercising the option or accepting the offer to extend the period is to ignore
the factual context in which it was at that time. It is an overly strict
construction of a government contract that would only prejudice the voting
public. At the time that the initial OTP period was to expire on 31 December
2010, the COMELEC had just finished conducting the first nationwide automated
national elections and was facing the myriad consequences of such electoral
exercise. Aside from deciding and ruling on various local electoral protests,
it had to reschedule and conduct special elections in affected areas. Prior to
the Courts Decision in Kida v. Senate,[64]
the Commission was also faced with preparations for the elections in the
Autonomous Region of Muslim Mindanao previously scheduled on 08 August 2011, but
since been reset and synchronized with the 2013 national and local elections.
Of course, it did not help that the COMELEC at the beginning of 2011 was also
undergoing changes in its composition with the retirement of COMELEC Chairperson
Melo and Commissioners Ferrer and Larrazabal, as well as the consequent
appointment of present COMELEC Chairperson Sixto Brillantes and Commissioners
Christian Robert S. Lim and Augusto C. Lagman.
More compelling than these
daily operational constraints is the budgetary limitation imposed by Congress
itself on the financial capabilities of COMELEC. It must be remembered that
from the latters initial request for a ₱10,436,300,399
budget for the procurement of an AES for the 2013 elections, the budget was
significantly reduced to only ₱7 billion. Out of that amount, it could
only use ₱2.2 billion for sourcing the AES, whether through purchase or
lease. If we were to reckon the lowest calculated responsive bid from its experience
in 2009, the COMELEC will have to spend a minimum of ₱9 billion in order
to secure a viable AES through public bidding. This fact only highlights the
limitations imposed by its reduced budget grant of ₱7 billion. The Court
cannot summarily ignore these financial constraints imposed upon the COMELEC.
It has been posited, in
response to these financial considerations, that COMELEC could still request an
additional budget for the lease or purchase of an AES in time for the 2013 elections
and still undergo a new public bidding process. This proposition asks the Court
to make several leaps of faith which is simply untenable and too fraught with
peril to warrant any proper consideration, especially since we are dealing here
with something that directly impacts elections, which are at the heart of our
representative democracy.
First, the proposed alternative route of
going to Congress for additional budget presupposes that there are available
funds for re-allocation to answer the needs of COMELEC. In addition, the
alternative likewise assumes that the process of approving additional funding
requirements would immediately and swiftly pass through Congress and the Senate
and achieve Presidential approval, all in time for COMELEC to receive the
needed appropriation, request proposals, and conduct another public bidding. The
alternative route already assumes that no opposition to an increase in funding would
be raised and thus prolong discussion and delay eventual approval. Of course,
all of this should be achieved in sufficient time before the conduct of the
2013 elections which is less than a year from now.[65]
Second, the proposition heavily relies on the
existence of other qualified bidders who would willing to submit offers within
the limited budget provided under the 2012 General Appropriations Act. Lest it
be forgotten, during the public bidding for the 2009 AES, the next best bid
after Smartmatic-TIMs offer of ₱4,327,876,279.86
for 82,200 PCOS machine units was Indras bid of ₱8,360,000,000 for only 57,231 units. The Court has been
given no assurance that the market for these machines has improved since 2009 such
that greater interest and participation from qualified suppliers would be
generated.
The final leap
of faith required by the Court under this alternative route would be to assume
that a new bidding would result in the procurement of an AES that is perfect
and free from technical glitches of the kind complained of here. In fact, even
Commission Lagman admits that there is no guarantee that the new machines to be
procured by the COMELEC would be problem-free.[66]
Rather than make
these three giant leaps of faith, the more defensible and reasonable position
is to dismiss the convoluted argument of petitioners that the exercise of the
OTP cannot be mutually extended and affirm that the purchase option was validly
extended and consensually agreed upon by the contracting parties.
The GPRA
recognizes exceptional circumstances that would dispense with the requirement
of public bidding, considering the overarching need to promote economy and operational
efficiency. These alternative methods of procurement, which would allow for
dispensing with the requirement of open, public and competitive bidding,
include limited source bidding, direct contracting, repeat order, shopping and
negotiated procurement.[67]
The limitation is that in resorting to these modes of procurement, the Procuring
Entity shall ensure that the most advantageous price for the government is
obtained. The underlying consideration in these alternative modes is that requiring
strict compliance with the statutory processes of bidding under the GPRA would
burden the procuring entity with needless technicalities, even if there are
adequate safeguards to prevent corruption and ensure transparency in the
procurement of goods and services.
Of particular significance to the
present case is the repeat order method under the GPRA, whereby the procuring
entity obtains goods from a winning bidder previously awarded through
competitive bidding, whenever there is a need to replenish those goods.[68] Specific
conditions are outlined
under
the GPRA[69] and its implementing
rules and regulations[70]
before repeat orders can be resorted to by a government agency:[71]
a.
Previous
Award - Existence of a supply contract
awarded through full competitive or public bidding;
b.
Unforeseen
Need - Need of procuring entity for
additional quantity of goods supplied under the contract due to unforeseen
cause;
c.
Non-splitting
of Contracts - The procurement must no result in
the splitting of contracts, requisitions, or purchase orders under Section 54.1
of the IRR-A;
d.
Time
Requirement - Must be availed within six (6)
months from the date of the Notice to Proceed arising from the original
contract except in cases approved by the Government Procurement Policy Board;
e.
Same
or Lower Price - Unit prices must be the same
as, or lower than those in the original contract, and still the most
advantageous to the procuring entity based on price verification;
f.
Quantity
Limitations - The procurement shall not exceed
twenty-five percent (25%) of the quantity of each item in the original
contract.
Similar to direct contracting,[72]
repeat orders are made by the procuring entity directly to a specific and
winning bidder for the purchase of specific goods. The policy rationale for this
alternative mode is that these goods have already been prescreened under a
previously conducted competitive bidding. It would be redundant for the
procuring entity to go through another round of bidding in this instance,
because the goods have been qualified under the GPRA.
To some
reasonable extent, there is enough room for this Court to apply the rationale
for repeat orders to the questioned OTP, in order to justify the exemption from
the requirement of public bidding, even if we cannot strictly categorize the
purchase as a repeat order.
First, the PCOS
machines sought to be purchased have previously gone through competitive
bidding and qualified under the technical requirements of the COMELEC as a
procuring entity. The goods to be purchased by it under the OTP are the same
machines that were used under the 2009 AES Contract for the 2010 national and
local elections. Subject only to the Hardware Acceptance Test under the Deed of
Sale, these PCOS machines have presumably passed the technical requirements for
the AES in 2009. None of the petitioners have put into question the regularity
in the conduct of the public bidding that gave rise to the 2009 AES Contract. To
conduct another round of public bidding for the PCOS machines, when they have been
previously proven to have satisfied the COMELEC requirements, would be superfluous.
Second, the
purchase price for these PCOS machines has not increased and continues to be
the superior bid as opposed to the proposal of the other bidder, Indra. None of
the petitioners claims that the 2009 AES Contract should have been awarded to any
other supplier. In fact,
the bid of Smartmatic-TIM was found to be the single complying calculated bid after an evaluation of its technical and financial proposal.[73]
These strongly indicate that both its product and the purchase price are superior
to those of the others and more advantageous to the government.
In the final
analysis, not only is the extension of the OTP and the exercise thereof
compliant with the objectives of competitiveness and transparency under the
GPRA, but these are also the most advantageous options available to the COMELEC
considering the present factual circumstances, the urgency of the upcoming
mid-term elections, and limited financial resources.
There
is no overwhelming necessity for the Court in the instant Petition to make
definitive findings on the alleged technical defects of the PCOS machines at
this time.
Petitioners
have highlighted the technical defects of the PCOS machines to demonstrate
their failure to comply with the requirements under the AES Law. On the other
hand, respondents COMELEC and Smartmatic-TIM argue that the claimed
deficiencies of the PCOS machines are either attributable to human intervention
and not to the machines themselves or alternatively, are not critical to render
the units unacceptable for purposes of conducting the 2013 elections.
We
understand the concerns of petitioners. Any doubt as to the functionality of
the PCOS machines would put the integrity of the electoral process under serious
suspicion and hence, cast disconcerting shadows on the legitimacy of their
results. Elections are indispensable in a true democracy,[74]
so that, without it, democracy would not flourish and would be a sham.[75]
Nevertheless,
petitioners have not sufficiently demonstrated to this Court that the PCOS
machines have technical insufficiencies of such magnitude as would support our exercise
of judicial review over the exclusive mandate of the COMELEC to administer the
election process.
The
Constitution empowered the COMELEC to [e]nforce and administer all laws and
regulations relative to the conduct of an election, plebiscite, initiative,
referendum, and recall.[76]
No other body is granted such plenary powers with regard to elections under the
Constitution. In recognition of this Constitutional mandate, the Court has, in
a long line of cases,[77]
given the COMELEC wide latitude in devising means and
methods that will insure the accomplishment of the great objective for which it
was created free, orderly, honest, peaceful, and credible elections.[78]
The COMELEC deserves to be accorded by the Court the greatest measure
of presumption of regularity in its course of action and choice of means in
performing its duties, to the end that it may achieve its designed place in
the democratic fabric of our government.[79]
Sumulong v. COMELEC,[80] underlined
the distinct role of the COMELEC and highlighted the Courts policy of non-interference,
even if the Court may not fully agree with the Commissions choice of means:
The Commission on Elections is a constitutional body. It is intended to play a distinct and important part in our scheme of government. In the discharge of its functions, it should not be hampered with restrictions that would be fully warranted in the case of a less responsible organization. The Commission may err, so may this court also. It should be allowed considerable latitude in devising means and methods that will insure the accomplishment of the great objective for which it was created - free, orderly and honest elections. We may not agree fully with its choice of means, but unless these are clearly illegal or constitute gross abuse of discretion, this court should not interfere. Politics is a practical matter, and political questions must be dealt with realistically not from the standpoint of pure theory. The Commission on Elections, because of its fact-finding facilities, its contacts with political strategists, and its knowledge derived from actual experience in dealing with political controversies, is in a peculiarly advantageous position to decide complex political questions.
xxx xxx xxx
There are no ready-made formulas for solving public problems. Time and experience are necessary to evolve patterns that will serve the ends of good government. In the matter of the administration of the laws relative to the conduct of elections xxx we must not by any excessive zeal take away from the Commission on Elections the initiative which by constitutional and legal mandates properly belongs to it. Due regard to the independent character of the Commission, as ordained in the Constitution, requires that the power of this court to review the acts of that body should, as a general proposition, be used sparingly, but firmly in appropriate cases. We are not satisfied that the present suit is one of such cases. (Emphasis supplied.)
In Roque v. COMELEC,[81]
this Court upheld the very same 2009 Contract between the COMELEC and
Smartmatic-TIM containing the OTP exercised by the Commission. Reiterating its
pronouncement in Sumulong, the Court
explained:
The COMELEC is an independent constitutional body with a distinct and pivotal role in our scheme of government. In the discharge of its awesome functions as overseer of fair elections, administrator and lead implementor of laws relative to the conduct of elections, it should not be stymied with restrictions that would perhaps be justified in the case of an organization of lesser responsibility. It should be afforded ample elbow room and enough wherewithal in devising means and initiatives that would enable it to accomplish the great objective for which it was created to promote free, orderly, honest and peaceful elections. This is as it should be for, too often, COMELEC has to make decisions under difficult conditions to address unforeseen events to preserve the integrity of the election and in the process the voice of the people. Thus, in the past, the Court has steered away from interfering with the COMELECs exercise of its power which, by law and by the nature of its office properly pertain to it. Absent, therefore, a clear showing of grave abuse of discretion on COMELECs part, as here, the Court should refrain from utilizing the corrective hand of certiorari to review, let alone nullify, the acts of that body. xxx. (Emphasis supplied.)
Rather than employ
excessive judicial zeal, this Court has generally deferred to the discretion of
the COMELEC in the performance of the latters constitutional mandate. Oftentimes,
we have steered away from unduly interfering with the administration of electoral
exercises by COMELEC and refrained from substituting our own wisdom. This
judicial policy of guarded review holds especially true in administrative matters,
such as the determination of which voting machines to use for purposes of the
automated elections.
Hence,
restraint in ruling on the discretion regularly exercised by the COMELEC is the
better part of prudence, especially in administrative matters; otherwise, excessive
meddling may create adverse critical consequences. In questioning the decision
of the constitutional body, petitioners bear a heavy burden of proving that it
acted with grave abuse of discretion.
The defects of the PCOS machines have
not been sufficiently demonstrated to support a judicial finding that they failed
to comply with the technical requirements under the AES Law.
The issue raised by petitioners is whether
the modern voting machines used and purchased by the COMELEC will accurately
reflect the will of the people in a manner that also complies with the AES Law.
In praying for
the nullification of the Deed of Sale of the PCOS machines, petitioners cite
five areas of special concern in which the integrity, security and auditability
of the AES, as required by the AES Law, may be particularly vulnerable: (a)
absence of a digital signature; (b) lack of verified paper trail; (c) lack of
ultraviolet marks on the ballots; and (d) last-minute configuration of the
compact flash disks in 2010.
Although
petitioners cited the presence of the open console port as another technical
defect of the PCOS machines which, according to them, allowed unauthorized
access to the operating system thereof,[82] this
purported defect is not expressly required under the AES Law and need not be
discussed at length. Suffice it to say that Smartmatic-TIM easily remedied the
defect by physically closing the port with tamper-proof mechanical seals[83]
and installing new firmware to prevent unauthorized access to the system.[84] That
this defect was remediable was even candidly admitted by Commissioner Lagman during
the oral arguments.[85]
On the other
hand, respondents have presented arguments to refute these claims of alleged
defects. They argue that the cited technical insufficiencies of the purchased
PCOS machines will not pose substantial and critical threats to the integrity
of these machines. Respondents likewise insist that most of the errors are not
attributable to the PCOS machines themselves, but more to human intervention.
A summary of the
opposing arguments of both sides are presented below:
A. Digital
Signature
The AES Law, as amended, provides for
the manner in which the electronically transmitted election results are
authenticated:
The
manner of determining the authenticity and due execution of the certificates
shall conform with the provisions of Republic Act No. 7166 as may be
supplemented or modified by the provisions of this Act, where applicable, by
appropriate authentication and certification procedures for electronic data,
electronic documents and electronic signatures as provided in Republic Act No.
8792 as well as the rules promulgated by the Supreme Court pursuant thereto.[86]
Hence, the digital signature is the
primary means of ensuring the authenticity of electronically transmitted
election returns. In fact, only a digitally signed election return is
considered as containing official election results.[87]
Petitioners point to the failure of the
PCOS machine to ensure the security of the election results because of the lack
of a digital signature. According to them, the machines are incapable of
embedding digital signatures as required by the AES Law.[88]
In response, Smartmatic-TIM explained
that the PCOS machines can be programmed to have several types of digital signature including
self-generated ones or even those generated by a third-party certifying
authority.[89]
However, COMELEC allegedly disabled the feature that would have enabled
the Board of Election Inspectors (BEI) to put additional personal digital
signatures generated by a third-party certifying authority, because a
certifying authority had not been established by law, among other reasons.[90] Despite these instructions by the
COMELEC to disable the said feature, Smartmatic-TIM argues that the separate
i-Button gadget could be considered as sufficient compliance with the digital
signature provision of the AES Law.[91]
B.
Voter
Verified Paper Audit Trail
One of the other minimum capabilities
required by the AES Law was that the voting machine should have a provision for
voter verified paper audit trail[92]
and allow the voter a system of verification to find out whether or not the
machine has registered his or her choice.[93]
The objective of this requirement is to allow voters to confirm that their choices as marked
in their ballots have been properly read and counted.
Petitioners
claim that no such voter verified paper audit trail was provided to the voters
during the 2010 elections.[94] They allege that even COMELEC admitted to
disabling this feature for logistical reasons, specifically the lack of ink for
printing the paper audit trail.[95]
Again, Smartmatic-TIM
argues that this capability was actually present in the PCOS machines except
that it was also disabled by the COMELEC.[96] No
adequate explanation has been offered by the COMELEC why this feature was
rendered inoperative, even if the PCOS machines were capable of performing
them.
C. Deactivation of the UV Mark Detectors
Another of the cited problems is the
disabling of the UV marks detection capability of the PCOS machines, which
compromises the security of the ballots.[97]
Respondent
COMELEC admits that it intentionally disabled the detectors because of printing
problems and the belated decision to change the UV marks design from that of
the COMELEC to that of the National Printing Office.[98]
According to Smartmatic-TIM, the delay in its printing schedule necessitated
fast-tracking of the UV-mark printing using less UV-ink concentration. The
reduced concentration resulted in unreliable UV detection. Thus, COMELEC
deactivated the UV detectors and decided to use handheld UV lamp detectors instead.
[99] The
PCOS machines, however, have the capability to read UV marks.
D. Reconfiguration of the
Compact Flash Cards
Finally, petitioners cite the much
publicized recall and reconfiguration of the compact flash cards a week before
the conduct of the 2010 elections.[100]
This controversy fuelled speculations of attempts to abandon the AES, resort to
the vulnerable manual voting, perpetrate massive fraud, and reduce voter
confidence in the process.[101]
COMELEC admits
that during the Final Testing and Sealing (FTS) a week before the 2010
elections, it was discovered that the PCOS machines did not properly read the
local side of the ballot.[102] It
explains that this was because the CF cards were configured to read a ballot
design that used single-spacing for the local side of the ballot, while COMELEC
belatedly decided to use double-spacing, because the local side was relatively
empty in comparison with the national side which was full due to the lengthy
list of party-list candidates. The decision to use double-spacing was not
timely communicated to Smartmatic-TIM. This omission led to the nationwide
recall of the CF cards to correct their configuration, so that the PCOS
machines would read the local side of the ballot as double-spaced, instead of
single-spaced.[103] The
recall of the CF cards did not impact the technical fitness of the PCOS
machines.
The purported technical defects of the PCOS machines are
factual issues that are not proper and ripe for the present Rule 65 Petitions.
After evaluating the above factual
allegations of both petitioners and respondents, we find that we are unable to
make a conclusion of grave abuse of discretion based on these allegations. To every
allegation of material defect, respondents are able to give an answer. The
Court would need to conduct a hearing on the facts to make a conclusion on
which claim is correct.
Had there been adequate time and
resources, a third-party review by a proven and competent authority would have
been valuable in helping the Court to resolve the supposed technical deficiencies
of the PCOS machines. It would be legally improper for the Court to entertain
these highly technical disputes in the instant Rule 65 Petition, when the basic
legal issue sought to be resolved is limited only to whether the OTP was
properly exercised by the COMELEC, and whether the consequent Deed of Sale
covering the PCOS machines is legally valid.
In any event,
the PCOS machines have been subject to review by SLI Global Solutions (SLI).[104] SLI twice evaluated Smartmatic-TIMs AES to examine
compliance with COMELECs technical requirements under the AES Law as well as
the request for proposal. SLI likewise used
the 2005 Voluntary Voting System Guidelines of the United States Election Assistance Commission to gauge
the proposed electoral system. Prior to the May 2010 elections, SLI issued its
Final Certification Test Report,[105] in
which it concluded as follows:
xxx. While the system conforms to key requirements and
is operationally suitable for use, findings
remain in areas such as documentation, process and setup. All issues
are considered however to be minor in nature or reconcilable using
appropriate manual processes and/ or compensating controls. Assuming the above mentioned
controls are put into practice and that the AES is properly configured,
operated and supported, SysTest Labs finds Smartmatic Automated Election System
to be capable of operating properly, securely and accurately and therefore recommends the system
for certification and use in the May 10, 2010 election. (Emphasis supplied)
SLI performed another review after the elections to
determine the viability of the AES for future elections. On 07 November 2011,
SLI issued a Final Certification Test Report, which affirmed its earlier
findings and recommended the certification of the system as conformant with the
operations requirements:
xxx. Assuming that the AES environment setup is
successfully completed, and the, system is properly configured, operated and
supported, and that the compensating controls are implemented, SLI Global Solutions finds that the Automated Election
System is functionally capable of operating properly, securely and accurately,
although there will continue to be dependence on the vendor for assistance. SLI
recommends the system for certification, as it is conformant with the
operational requirements and is suitable for use in applicable future elections.
(Emphasis supplied.)
The
above certification of the SLI, as to the functional viability and suitability
of Smartmatic-TIMs AES for both the 2010 and 2013 elections, deserves sufficient
weight. There has been absolutely no claim that the methods used by SLI are
doubtful, or that its qualifications are questionable. Petitioners, as well as
the Court, cannot simply disregard the approval given by an independent and objective
evaluator of the AES.
Fuelling the trepidation
to rule on the technical sufficiency of the PCOS machines is the general sense
obtained during the course of the oral arguments that these defects do not
appear to be critical or intrinsic to the machines. Strangely, many of the
complaints focus on the wisdom of the administrative decisions made by COMELEC
in the performance of its discretionary authority, i.e., disabling some of the
features of the PCOS machines. Although it is not discounted that the PCOS
machines may leave room for improvement, it seems that another aspect of the
problem may have something to do with the conduct of COMELEC personnel using the
PCOS machines, which is already beyond the scope of the issue with respect to
the technical compliance of the units with the minimum functional capabilities
set by law for an AES.
Without making
set judgment as to the gravity of the defects, it is to be noted that these
defects are remediable, as admitted by former COMELEC Commissioner Lagman in
his testimony during the oral arguments:
JUSTICE
SERENO:
xxx. So, you are basically saying here that these
technical proposals are not inherently irremediable. That is the conclusion
that we are coming to. There are access devices or accessories that you can
attach to machines and it will do what you want it to do. The software can be
configured. In other words, in the world of technologies the possibilities are
there. Okay?
FORMER COMMISSIONER LAGMAN:
That is correct, Your Honor. I just dont know whether
they can do it in time.[106]
Based on the
foregoing exchange, Commissioner Lagmans concern was whether the defects could
be remedied in time. This illustrates the speculative character of some of the
concerns raised in these Petitions.
Considering the wide latitude given to the COMELEC in the exercise of its constitutional mandate, the lack of competence of the Court to decide on technical matters, and the apparently adequate explanations given by respondents for the non-intrinsic defects, the Court finds it extremely difficult to declare that grave abuse of discretion attended the decision of the COMELEC to purchase the PCOS machines based on supposed technical insufficiencies.
This
Case Is Unique: The Interests of the Government Are Adequately Safeguarded in
This Particular Circumstance.
This Courts Decision is not intended to be a new,
wide-open valve that would violate the requirements of the GPRA. The conditions herein compel us to rule in
favor of COMELEC or, rather, to avoid stymieing its exercise of discretion of
COMELEC in its planned conduct of future elections. Government
procurement officials are still required to give adequate written notice of
their intention to make use of options to purchase in validly executed
contracts and to put in writing mutual agreements to extend option periods which
must ultimately be justified in the context of the original contract in which the
option inheres.
For the guidance of government
procurement officials, we enumerate conditions that, at a minimum, must exist
in order that expired OTPs can still be availed of. More conditions may be required if provided
for by law, regulation or contract, as follows:
One, there can be
no revival of an expired option if the revival is not made within a reasonable
time after its expiry.
Two, the delay in
the exercise of the option or the failure to exercise it within the original
period must be fully justified under the circumstances.
Three, the exercise
of the option must be advantageous to government.
We clarify,
however, that the option period in this case has not, under the circumstances,
truly expired as to deny the parties the ability to make use of them.
Accordingly, I
vote to DISMISS the instant
Petitions. Consequently, the Commission on Elections Resolution Nos. 9373 and
9376 dated 06 March 2012 and 21 March 2012, respectively on the Agreement on the Extension of the Option to
Purchase under the Contract for the Provision of the Automated Election System
for the May 10, 2010 Synchronized National and Local Elections dated 30 March
2012 and the Deed of Sale dated 30 March 2012 by and between COMELEC and
Smartmatic-TIM Corporation are declared VALID.
The Temporary
Restraining Order issued by this Court on 24 April 2012 enjoining respondents
COMELEC and Smartmatic-TIM Corporation from implementing COMELEC Resolution No.
9376 should likewise be LIFTED.
MARIA LOURDES P.
A. SERENO
Associate Justice
[1] Contract for the Provision of an Automated Election System for the 10 May 2010 Synchronized National and Local Elections, Annex 3 of Smartmatic-TIMs Comment dated 30 April 201, hereafter the 2009 Contract.
[2] In Basilan, First District of Bulacan and some areas of Lanao del Sur.
[3] The original quantity of PCOS machines subject of the option to purchase was 82,200 units. After COMELEC partially exercised the option for 920 units for the special elections, the remaining number of units available for purchase should have been 81,280 units. However, the assailed proposed purchase covers only 80,916 units instead of 81,280, because it appears that some of the remaining PCOS machines have been lost, missing or unserviceable. (Annexes E and E-1 of the Deed of Sale dated 30 March 2012, Annex 16 of Smartmatic-TIMs Comment dated 30 April 2012.)
[4] ARTICLE 1562. In
a sale of goods, there is an implied warranty or condition as to the quality or
fitness of the goods, as follows:
(1)Where
the buyer, expressly or by implication, makes known to the seller the
particular purpose for which the goods are acquired, and it appears that the
buyer relies on the seller's skill or judgment (whether he be the grower or
manufacturer or not), there is an implied warranty that the goods shall be
reasonably fit for such purpose;
(2)Where
the goods are brought by description from a seller who deals in goods of that
description (whether he be the grower or manufacturer or not), there is an
implied warranty that the goods shall be of merchantable quality. (n) (Civil
Code)
[5] Roxas v. Binay, docketed as PET Case No. 004, is a Protest filed under Rule 15 of the 2010 Rules of the Presidential Electoral Tribunal. Protestant Manuel A. Roxas seeks the annulment of the proclamation of protestee Jejomar C. Binay as the duly elected Vice-President of the Republic of the Philippines after the 10 May 2010 synchronized elections due to fraud, anomalies, irregularities and statistical improbabilities in certain clustered precincts, among other grounds. The fraud, anomalies and irregularities were alleged to be due to the complete and utter disregard by COMELEC and Smartmatic-TIM of the mandated minimum system capabilities for an automated election system under the AES Law. It is alleged that the two were complicit in disabling or entirely removing crucial safeguards that should have prevented the occurrence of system-wide electoral fraud in the Vice-Presidential Contest.Among the mandatory requirements and security safeguards allegedly disregarded or deactivated were the voter verified paper trail, the digital signatures, the ultraviolet (UV) verification capability, the source code review and the configuration of the compact flash (CF) cards in a way that made them unable to read votes for the protestant.
[6] A contract can be renewed, revived or
extended only by mutual consent of the parties. (Light Rail Transit
Authority v. CA, 486 Phil. 315,329 (2004); Thunder Security and
Investigation Agency v. NFA (Region I), G.R. No. 182042, 27 July 2011, 654
SCRA 714, 725).
[7] Arturo M. Tolentino, Commentaries and jurisprudence on the Civil Code of
the Philippines, Volume Four, 559-560 (1987).
[8]ARTICLE IV, Sec. 10. Competitive Bidding. All Procurement shall be done through Competitive Bidding, except as provided for in Article XVI of this Act.
[9] Lease of construction and office equipment, including computers, communication and information technology equipment are subject to the same public bidding and to the processes prescribed under this Act. (GPRA, Sec. 46)
[10] Part A, Rule XIV, Sec. 46.
[11] GPPB NFM No. 065-2007 dated 03 December 2007 available at http://www.gppb.gov.ph/opinions/view_opinion.asp?o_id=447 (last visited on 05 June 2012).
[12] WTO Agreement on Government Procurement, Art. 1 (2).
[13] 48 C.F.R. 7.402 (b)
(2).
[14] IRR-A of the GPRA, Annex D, Sec. 1.1.
[15]IRR-A of the GPRA, Annex E, Contract Implementation Guidelines for the Procurement of Infrastructure Projects, Sec. 10.
[16]If the government agrees to extend the
period, however, the winning bidder of the infrastructure project is obliged to
increase or extend its performance security to cover the approved contract time
extension:
For the procurement of infrastructure projects, the winning bidder
shall post an additional performance security following the schedule above to
cover any cumulative increase of more than ten percent (10%) over the original
value of the contract as a result of amendments to order or change orders,
extra work orders and supplemental agreements, as the case may be. The winning
bidder shall cause the extension of the validity of the Performance Security to
cover approved contract time extensions. (IRR-A of the GPRA, Sec. 39.5.)
[17] 21 Ct.Cl. 222, 543 F.2d 1306, 20 UCC Rep. Serv. 923 (20 October 1976).
[18] Id. at 1313.
[19] AES Law, Sec. 5, as amended by Republic Act No. 9369.
[20] Annex 1, Consolidated Comment of COMELEC dated 30 April 2012.
[21] COMELECs Consolidated Memorandum dated 18 May 2012, p. 7.
[22] Consolidated Comment of COMELEC dated 30 April 2012, pp. 60-61.
[23] Contract for the Provision of an
Automated Election System for the May 10, 2010 Synchronized National and Local
Elections dated 09 July 2009.
[24] 2009 AES Contract, Art. 4.3, p. 8.
[25] Contract of Sale dated 23
September 2010.
[26] 6. Partial Temporary Extension - In order to allow the Commission to meet its decision regarding the option to purchase on the PCOS machines, Smartmatic-TIM is amenable to extend the option to purchase, solely on the remaining 81,280 PCOS machines, until March 31st 2011, waiving the storage costs, and covering the maintenance costs. Would COMELEC exercise the option to purchase before March 31st, the additional 1 years [sic] warrant would begin to count again. (Smartmatic-TIC Letter dated 18 December 2010, p. 3)
[27] Smartmatic-TIM letter
dated 23 March 2011.
[28] Smartmatic-TIM letter dated 23 September 2011.
[29] Smartmatic-TIM letter dated 28 December 2011.
[30] Considering it is now end of December 2011, and the Commission is
still finalizing its evaluation of the AES in order to make a decision on the
purchase of the equipment, we are again granting an extension of the option to
purchase for another three (3) months. (Id.)
[31] Republic Act No.
10155.
[32]Based on COMELECs computation, ₱4.8 billion out of the
₱7 billion budget will be used for essential services (₱2.8 billion)
and to defray the costs of deployment (₱2 billion). (COMELEC Memorandum
dated 18 May 2012, p. 22)
[33] Thus, the phrase has determined that the critical and major
issues on, the Voluntary Voting System Guidelines (VVSG) of the 2010 AES have
already been resolved (though wrongly phrased as there are no issues on the
VVSG-standard used for the review of the software source code) is wrong. SMTT,
in fact, is still in the process of presenting the fixes to the Comelec. While
fixes on some issues have already been presented, none of [the] said fixes have
actually and officially been accepted. (Additional Arguments for Dissent dated
21 March 2012)
[34] Comment dated 21 March 2012, p. 2.
[35] The period in which
the COMELEC can exercise its option to purchase is extended to 31 March 2012.
(Agreement on the Extension of the Option to Purchase under the Contract for
the Provision of an Automated Election System for the May 10, 2010 Synchronized
National and Local Elections dated 30 March 2012)
[36]2. For and in consideration of the amount of One Billion Eight
Hundred Thirty Three Million Two Hundred Seventy Four Thousand Four Hundred
Fifty Seven Pesos and Nine Centavos (Php1,833,274,457.09) (Purchase Price),
the BUYER [COMELEC] hereby purchases the hardware and software listed in Annex
E and Annex E-1 from the SELLER [Smartmatic-TIM] subject to the terms and
conditions set forth in Annex D. The Purchase Price shall be paid by the
BUYER in accordance with the payment schedule attached as Annex F. The BUYER
shall pay the Purchase Price to the SELLER via irrevocable letter of credit
issued by the Land Bank of the Philippines. (Deed of Sale dated 30 March 2012)
[37] To formally ACCEPT the offer of SMARTMATIC-TIM to extend the
period to exercise the Option to Purchase until March 31, 2012. (COMELEC Resolution No. 9377 dated 29 March
2012)
[38] To APPROVE the Deed of Sale between the COMELEC and the
SMARTMATIC-TIM attached as Annex A hereof to purchase the latters PCOS
Machines (hardware and software) to be used in the upcoming May 13, 2013
National and Local Elections; xxx. (COMELEC Resolution No. 9378 dated 30 March
2012)
[39]Petition
for Review on Certiorari, Prohibition and Mandamus dated 10 April 2012 (G.R. No
201112); Certiorari and Prohibition dated 03 April 2012 ( G.R. No. 201121);
Petition for Certiorari, Prohibition and Mandamus dated 10 April 2012 ( G.R.
No. 201127); and Petition dated 26 April 2012 (G.R. No. 201413).
[40] Smartmatic-TIM claims that in addition to the substantial part of the Performance Security, which the COMELEC still retains, the company also has a remaining outstanding claim of ₱23,000,000 for the Command Center that it built at the Philippine International Convention Center upon the instruction of the COMELEC. (Smartmatic-TIMs Consolidated Memorandum dated 18 May 2012, p. 39)
[41] The performance security was furnished through an
irrevocable domestic standby letter of credit, which Smartmatic-TIM
opened on 15 June 2009 in favor of the COMELEC. The standby letter of credit
remained in effect until its expiration on 10 July 2010. However, in COMELEC
Resolution No. 9293 dated 6 October 2011, the COMELEC retained an amount
approximately equal to ₱50,000,000
to cover the remaining unfulfilled obligations of Smartmatic-TIM under the 2009 AES Contract. (COMELECs Consolidated Memorandum
dated 18 May 2012, pp. 54-55.)
[42]8 Cl.Ct. 743, 33 Cont.Cas.Fed., 26 Sept. 1985.
[43] TSN, 02 May 2012, p.12.
[44]Article
1292, Civil Code. See also Evadel Realty and Development Corporation v. Spouses Antero, 409 Phil. 450 (2001) and Transpacific Battery
Corporation v. Security Bank
& Trust Co., G.R. No. 173565, 08 May 2009, 587 SCRA 536.
[45] Deed of Sale dated 30 March 2012, Art. 9, p. 4.
[46]Cresencio C. Milla v. People of the Philippines, G.R. No. 188726, 25 January 2012 citing Quinto
v. People, 365 Phil. 259 (1999).
[47]Inchausti
& Co. v. Yulo, 34 Phil. 978 (1914); Pascual v. Lacsamana, 100
Phil. 381 (1956); Tible v. Aquino,
160 Phil. 214 (1975); California Bus
Lines v. State Investment House, 463 Phil. 689 (2003).
[48]BPI v. Gooch, 45 Phil 514 (1923).
[49] 450 Phil. 744 (2003).
[50] Id. at 814-815.
[51] 464 Phil. 173 (2004).
[52] Id. at 248.
[53] TSN, 02 May 2012, p. 91.
[54] 2009 AES
Contract, Art. 4.3, p. 8.
[55] Deed of Sale dated 30
March 2012, Art. 2, p. 2.
[56]4. The SELLER [Smartmatic-TIM] shall retain administrative control
and ownership of the hardware and software prior to the conduct of the Hardware
Acceptance Test (HAT). The control and ownership of the hardware and software
shall be transferred to the BUYER [COMELEC] upon acceptance per batch of 20,000
units during the HAT process. For said purpose, the SELLER shall issue a
Delivery Receipt of accepted hardware upon acceptance of every 20,000 units.
The SELLER shall submit the Inventory List (including the serial numbers) of
the hardware and software listed in Annex E and Annex E-1 to the BUYER
within three (3) business days after the execution of this Deed of Sale. (Deed of Sale dated 30 March 2012, Art. 4, p. 2)
[57] 6. Partial Temporary Extension - In order to allow the Commission to meet its decision regarding the option to purchase on the PCOS machines, Smartmatic-TIM is amenable to extend the option to purchase, solely on the remaining 81,280 PCOS machines, until March 31st 2011, waiving the storage costs, and covering the maintenance costs. Would COMELEC exercise the option to purchase before March 31st, the additional 1 years [sic] warrant would begin to count again. (Smartmatic-TIM letter dated 18 December 2010, p. 3)
[58] Smartmatic-TIM letter
dated 23 March 2011.
[59] Smartmatic-TIM letter dated 23 September 2011.
[60] Smartmatic-TIM letter dated 28 December 2011.
[61] Considering it is now end of December 2011, and the Commission is
still finalizing its evaluation of the AES in order to make a decision on the
purchase of the equipment, we are again granting an extension of the option to
purchase for another three (3) months. (Id.)
[62] The period in which
the COMELEC can exercise its option to purchase is extended to 31 March 2012.
(Agreement on the Extension of the Option to Purchase under the Contract for
the Provision of an Automated Election System for the May 10, 2010 Synchronized
National and Local Elections dated 30 March 2012)
[63] Data Recognition Corporation v. State of Minnesota, 2003 WL 23335317 (Minn.Dist.Ct.).
[64] G.R. Nos. 196271, 196305, 197221, 197280, 197282, 197392 & 197454, 18 October 2011.
[65] TSN, 02 May 2012, pp. 66-67, 296-297.
[66] Id. at 192.
[67] GPRA, Sec. 48.
[68] GPRA, Sec. 48 (c).
[69] GPRA, Sec. 51.
[70] IRR-A of the GPRA,
Sec. 51.
[71] Florante b. nacor, The Philippine Government Procurement Reform Act
(R.A. No. 9184) and the Revised IRR, Annotated: A Handbook on Public Bidding, Central Book Supply, 541 (2011).
[72] Direct contracting is a method of procurement that does not require
elaborate bidding documents because the supplier is simply asked to submit a
price quotation or a proforma invoice, together with the conditions of sale,
which is an offer that may be accepted immediately or after some negotiations.
(GPRA, Sec. 48 [b]; Sec. 50)
[73] Roque v. COMELEC, G.R. No. 188456, 10 September 2009, 599 SCRA 69.
[74]Bato Ali v. Court of First Instance of Lanao, 80 Phil. 506 (1948).
[75] COMELEC v. Tagle, 445 Phil. 667 (2003).
[76] Constitution, Art.
IX, Sec. 2.
[77] Tolentino v. COMELEC, G.R. Nos. 187958, 187961, 187962, 187966,
187967, 187968, 07 April 2010, 617 SCRA 575; Province of Agusan del Norte v. COMELEC, G.R. No. 165080, 24 April
2007, 522 SCRA 94; Pamatong v. COMELEC,
G.R. No. 161872, 13 April 2004, 427 SCRA 96; Laban ng Demokratikong Pilipino v. COMELEC, 468 Phil. 70 (2004); Buac v. COMELEC, 465 Phil. 800 (2004); Akbayan Youth v. COMELEC, 407 Phil. 618 (2001); Pelayo v. COMELEC, 132 Phil. 822 (1968).
[78] 1987 Constitution, Art. IX, Section 4.
[79] Id., citing Aratuc v. COMELEC, 177 Phil. 205 (1979).
[80] 73 Phil. 288, 294-296 (1941).
[81] Supra note 73, at 152-153.
[82] Annex A, S4S Memorandum dated 18 May 2012; TSN, 02 May 2012, pp. 139, 164-168.
[83] Smartmatic-TIMs Consolidated Memorandum dated 18 May 2012, p. 82; COMELEC Consolidated Memorandum dated 18 May 2012, p.103.
[84] JUSTICE SERENO: These machines are configurable by the
necessary software commands, correct Commissioner?
COMMISSIONER
LAGMAN: Yes, Your Honor.
JUSTICE SERENO: Except for the accessible port but even the accessible port cannot be actually
disabled.
COMMISSIONER LAGMAN: It can be disabled, Your Honor. (TSN dated 02 May 2012, p. 178; emphasis supplied)
[85] TSN, 02 May 2012, p. 178.
[86] AES Law, as amended by
Republic Act No. 9369, Sec. 30.
[87] The election returns transmitted electronically and digitally signed shall be considered as official election results and shall be used as the basis for the canvassing of votes and the proclamation of a candidate. (AES Law, as amended, Sec. 22; emphasis supplied)
[88] Petitioners Capalla et al.s Memorandum dated 18 May 2012, p. 22; Petitioners Guingona et al.s Memorandum dated 18 May 2012, pp. 19-26; Petitioners Solidarity for Sovereignty (S4S) et al.s Memorandum dated 18 May 2012, pp. 35-36; Tanggulang Demokrasya (Tan Dem) et al.s Memorandum dated 18 May 2012, pp.11-13.
[89] The PCOS machine itself has provisions for, and can be programmed to have, several types of digital signatures. SMARTMATIC-TIM will only program the PCOS machines in accordance with the instructions of COMELEC. (Consolidated Comment of Smartmatic-TIM dated 30 April 2012, p.53). See also TSN dated 08 May 2010, pp. 159-170.
[90] 3.87
For the 2010 elections, COMELEC evaluated different options to implement
additional signatures to the PCOS machines, but there were basically three
constraints. First, during the
preparations for the 2010 elections, a Certification Authority for the use of Public Key
Infrastructure had not been established. xxx.
3.88 Second, the members of the Board of Advisers are
selected a couple of months before the elections, while the final data
configuration of voting machines and canvassing
servers need to be finished by January 2010, making it therefore impossible to
add the specific individual certificates and keys in the
PCOS machines.
3.89. Third,
there was concern that providing each BEI member with his or her own
digital signature would leave success of transmission reliant on the attendance
of all tile BEI members. The drop-out rate of BEIs is
typically too high to justify essentially giving any one person the
"key" to the PCOS. Also, the use of personal digital
signatures exposes BEIs to higher probabilities of
coercion, violence, and bribery.
3.90. To reiterate, the PCOS machine has security features as it allows for the addition of multiple keys, on top of the one supplied to the BEI chairman. However, COMELEC discarded this option for the reasons described above. xxx. (Consolidated Comment of Smartmatic-TIM dated 30 April 2012, pp. 54-55; See also TSN, dated 08 May 2010, p. 161)
[91] xxx [I]t is not correct to state that
the COMELEC did not require or use a digital signature in the 2010 elections. COMELEC Resolution No. 8786 defines the processes for the generation of the PCOS machine's digital signature
through the use
of a proprietary token known as the i-Button, which contains a unique PIN or
password (private key) assigned to the specific voting precinct, and which is
under the control and custody of the BEl Chairman assigned to that voting
precinct. Inside every PCOS machines a
digital certificate is implanted, from the moment the machines are configured
in COMELEC central. Together with the i-Button provided to the chairman of the
BEI and a password, the results are digitally signed and encrypted, thus giving
the ER its integrity, confidentiality and non-repudiation properties, and
enabling the encryption of the ER data as needed for secure transmission. (Consolidated Comment of Smartmatic-TIM dated 30 April 2012, pp. 53-54; see also COMELEC Resolution No. 8739, otherwise known as the General Instructions
for the Board of Election Inspectors; and TSN, 08 May
2010, pp. 159-170)
[92] AES Law, as amended,
Sec. 6 (e).
[93] AES Law, as amended,
Sec. 6 (n).
[94] Petitioners Guingona et al.s Memorandum dated 18 May 2012, pp.15-19; Petitioners Capalla et al.s Memorandum dated 18 May 2012 , pp. 24-25.
[95] Petitioners Capalla et al.s Memorandum dated 18 May 2012, p. 25.
[96] xxx. Sec 6(3) of RA 9369 requires that the AES must at least have the functional capability to provide for voter verified paper audit trail. The law asks that the system has the capability, which it has. It is up to COMELEC to activate it, and not SMARTMATIC-TIM. Thus, it cannot be said that the system lacks the capability. (Consolidated Comment of Smartmatic-TIM dated 30 April 2012, pp. 55-56)
[97] Petitioners Guingona et al.s Petition dated 10 April 2012, p. 13.
[98] 177. Third. The PCOS machines are perfectly capable of detecting UV marks. It just so happened that the COMELEC intentionally disabled the UV mark verification feature for reasons extraneous to the PCOS machines- printing problems and the belated decision to use the change the UV mark's design from the COMELEC's to the National Printing Office's ("NPO's"). (COMELECs Consolidated Comment dated 30 April 2012, pp. 107; see also COMELECs Memorandum dated 18 May 2012, pp. 103-104)
[99] 3.94. The PCOS machines have UV-reading functionality so that the PCOS machine itself would automatically confirm the authenticity of a ballot. However, in the 2010 elections, tight deadlines brought about by legal impediments necessitated fast-tracking of the UV-mark printing with less UV-ink concentration resulting in unreliable UV detection. Since the printing had to proceed given the time constraints, COMELEC decided to disable the UV verification feature on the PCOS. Instead COMELEC procured handheld UV lamps for each polling precinct's BEI to use on election day to verify each ballot's authenticity before handing it to a voter. (Smartmatic-TIMs Consolidated Comment dated 30 April 2012, p. 57.)
[100] Petitioners Guingona et al.s Petition dated 10 April 2012 p. 13; Petitioners Guingona et al.s Memorandum dated 18 May 2012, p. 12; Petitioners S4S et al.s Memorandum dated 18 May 2012, p. 34.
[101] Was malicious software placed in recalled CF cards?,
http://www.abs-cbnnews.com/nation/05/27/10/was-malicious-software-placed-recalled-cf-cards;
Defective data cards for poll machines recalled, http://newsinfo.inquirer.net/topstories/topstories/view/20100504-268027/Defective-data-cards-for-poll-machines-recalled
(last visited on 08 June 2012); Erap
camp gathering proof of electronic fraud, http://www.philstar.com/Article.aspx?articleId=575062&publicationSubCategoryId=63
(last visited on 08 June 2012).
[102] 146.1. During the Final Testing and
Sealing (FTS), it was discovered that the PCOS machines did not properly read the local side of
the ballot. This was because the CF cards were configured to read a ballot
design that used single-spacing for the local side of the ballot.
146.2.
The COMELEC made the belated
decision to use double-spacing for the
local side of the ballot
because the local side was relatively empty in comparison to the national side
which was full due to the lengthy list of party-list
candidates.
146.3.
The decision to use double-spacing was not timely communicated leading to the
recall of the CF cards to correct their configuration so the PCOS machines
would read the local side of the ballot as double-spaced, instead of single-spaced. (COMELECs
Consolidated Comment dated 30 April 2012, pp. 76-7.)
[103] Id. at 77.
[104] Formerly known as SysTest Labs Incorporated.
[105] Annex 16, Consolidated Comment of COMELEC dated 30 April 2012.
[106] TSN, 02 May 2012, pp. 186-191.