Republic of the
Supreme Court
THIRD
DIVISION
PHILIPPINE CHARTER INSURANCE CORPORATION,
Petitioner, -
versus - CENTRAL COLLEGES OF
THE
Respondents. |
|
G.R. Nos. 180631-33 Present: VELASCO, JR., J.,
Chairperson, PERALTA, ABAD, PERLAS-BERNABE, JJ. Promulgated:
February 22, 2012 |
X
--------------------------------------------------------------------------------------X
D E C I S I O N
MENDOZA, J.:
This is a petition for review on certiorari
under Rule 45 of the 1997 Rules of Civil Procedure challenging the June 29,
2007 Decision[1] and November
19, 2007 Resolution[2] of the Court
of Appeals (CA) in the consolidated cases CA-G.R. SP Nos. 90361, 90383
and 90384.
THE FACTS
On May 16, 2000, Central Colleges of
the Philippines (CCP), an educational institution, contracted the
services of Dynamic Planners and
Construction Corporation (DPCC) to be its general contractor for the
construction of its five (5)-storey school building at No. 39 Aurora Boulevard,
Quezon City, with a total contract price of P248,000,000.00. As embodied in a Contract Agreement,[3] the
construction of the entire building would be done in two phases with each phase
valued at P124,000,000.00.
To
guarantee the fulfillment of the obligation, DPCC posted three (3) bonds, all
issued by the Philippine Charter Insurance Corporation (PCIC), namely:
(1) Surety Bond No. PCIC-45542, dated P7,031,460.74;[4]
(2) Performance Bond No. PCIC-45541[5] in
the amount of P2,929,775.31 which was subsequently increased to P6,199,999.99
through Bond Endorsement No. E-2003/12527;[6]
and (3) Performance Bond No. PCIC-46172
for P692,890.74.[7] All the bonds were callable on demand and set
to expire on
The
Phase 1 of the project was completed without issue. Thereafter, CCP paid DPCC P14,880,000.00
or 12% of the agreed price of P124,000,000.00 with a check dated
The Phase 2 of the project, however,
encountered numerous delays. When CCP audited DPCC on
Thus,
in a letter dated
You are both hereby NOTIFIED that the
Bonds referred to above for the faithful performance of a Contract, dated
On
On
In
a letter dated
We acknowledge the receipt of your letter
dated
Furthermore, we would like to reiterate
that your principal, the Dynamic Planners & Construction Corporation has
breached the Contract of Agreement dated May 16, 2000 by having completed only
an estimated 51% of the construction of the 5-storey CCP Extension Building,
Phase 2 and has therefore failed to perform the work within the agreed
schedule.
In view thereof, as stated in our earlier
letter of
The Central Colleges of the
Meanwhile,
on
Eventually, negotiations to continue
on with the construction between CCP and DPCC reached a dead end. CCP hired another contractor to work on the
school site.
On
P13,924,351.47
as indicated in the bonds.[13]
On
Thus,
on
1. Under Surety Bond No. 45542, the
amount of Php7,031,460.74 plus legal interest from the date of demand until
full payment thereof;
2.
Under Performance Bond Nos. PCIC-45541 [Bond Endorsement Nos. E-2003/12527] and
PCIC-46172, the amount of Php6,892,890.73 plus legal interest from the date of
demand until full payment thereof; and
3.
Php100,000.00 as and for attorneys fees.[16]
In
their Answer,[17] DPCC
and PCIC denied any liability and proffered that CCP unlawfully withheld the
materials, equipment, formworks and scaffoldings left at the premises amounting
to P4,232,264.12.
On
1. Claimant was legally justified in
terminating the Contract;
2. On the issue of whether claimant
faithfully complied with its contractual obligation in respect of (a) the
release of the downpayment, (b) the delivery of the drawings for construction,
and (c) the payment of progress billings, there is no record that Dynamic
protested the delay in the delivery of the site, the delay in the submission of
technical plans and demanded as a result thereof the corresponding adjustment
of the Contract Period or the Contract Price.
The issue of delay in the reduction of the down payment is moot since
Dynamic acquiesced in the reduction of the down payment from 15% to 12% and the
issue of payment of the 12th progress billing arose as a consequence
of a legitimate issue as to the percentage of completion of the work by Dynamic
as of August 2003.
3. Dynamics percentage of accomplishment
as of the date of the termination of the Contract was 57.33% at P71,089,200.
4. The original Contract Price was P124,000,000. To this amount shall be added the price of
Variation Order No. 2 of P13,857,814.87 or an adjusted Contract Price of
P137,857,814.87. Deducting P110,000,792.87,
the overpayment to Dynamic is P27,779,022.00. However, Claimant is entitled to an award not
exceeding the amount of its claims in its Complaint and in the Terms of
Reference.
5. Dynamic failed to produce evidence to
show that it was not paid the balance of the Contract Price for Phase 1 of the
Project.
6. Surety is liable to Claimant under the
Performance and Surety Bonds it issued in favor of Claimant. The liability of Surety is to indemnify
Claimant for the un-recouped down payment [which] shall not exceed P7,031,460.74
under the Surety Bond and for not more than P6,892,890.73 under the
Performance Bonds.
7. If Surety is obliged to pay these
amounts to Claimant, it is entitled, on its cross-claim, to indemnity from
Dynamic.
8. Claimants claims under the Surety and
Performance Bonds are not time-barred.
9. Surety is not barred by estoppel from
denying liability under the Surety and Performance Bonds.
10. Claimants request to Dynamic to
extend the term of these bonds, Dynamics request to Surety to extend their
terms and Suretys grant of the extension requested have no adverse legal
effect upon the rights and obligations of the parties.
11.
The contractual time-bar embodied in the bonds is valid and binding.
12.
Dynamic is entitled to its claims for the payment of P1,732,264.14 for
materials and of P2,500,000.00 for the equipment, formworks and scaffolding
left at the site.
13.
The claims for payment of moral, exemplary and temperate damages and for
attorneys fees are denied.
14.
The parties shall bear their own cost of arbitration.[18]
Thus,
CIAC disposed of the case finding DPCC liable to pay CCP P7,031,460.74
from the Surety Bond representing the unrecouped downpayment and P6,892,890.73
from its Performance Bond for a total of P13,924,351.47. The CIAC likewise ordered CCP to pay DPCC P1,732,264.12
corresponding to the construction materials left at the site and P2,500,000.00
for the cost of equipment, formworks and scaffoldings appropriated by CCP or a
total of P4,232,264.12. The fallo
reads:
WHEREFORE, award is hereby made against
Respondent Dynamic Planners and Construction Corporation and Respondent
Philippine Charter Insurance Corporation, ordering them, jointly and severally,
to pay Claimant, Central Colleges of the Philippines the amount of P7,031,460.74
under the Surety Bond as un-recouped down payment, and the amount of P6,892,890.73
under the Performance Bond or the total amount of P13,924,351.47.
Award
is likewise made against Claimant, Central Colleges of the Philippines,
ordering the latter to pay Respondent Dynamic Planners and Construction
Corporation, the amount of P1,732,264.12 for the latters materials left
at the Project Site and the amount of P2,500,000.00 as the cost of its
equipment, formworks and scaffoldings which were appropriated by the former or
the total amount of P4,232,264.12.
Offsetting
the amount due claimant Central Colleges of the Philippines from Respondent
Dynamic Planners and Construction Corporation and that due the latter from the
former, there is a net amount of P9,692,087.37 which Respondent Dynamic
Planners and Construction Corporation is hereby ordered to pay Claimant Central
Colleges of the Philippines with interest at the rate of 6% per annum from the
date of this Final Award and 12% per annum from the time this Final Award
becomes final and executory and until it is fully paid in accordance with
Eastern Shipping Lines, Inc. vs. Court of Appeals (1994) 234 SCRA 78.
The
joint and several liability of Respondent Philippine Charter Insurance
Corporation with Respondent Dynamic Planners and Construction Corporation is
accordingly reduced to P9,692,087.37.
In the event of payment by Respondent Philippine Charter Insurance
Corporation, the latter is entitled to indemnity from its co-Respondent Dynamic
Planners and Construction Corporation up to the full amount of such
payment. In the event of delay in making
payment to indemnify Respondent Philippine Charter Insurance Corporation,
Respondent Dynamic Planners Charter Insurance Corporation shall pay interest at
the rate of 21% per annum in accordance with the Indemnity Agreement between
them.
All
other claims, counterclaims and cross-claims not otherwise determined in this
Final Award are deemed denied for lack of merit.
SO
ORDERED.[19]
All the parties appealed the CIAC decision
to the CA. PCICs appeal was docketed as
CA-G.R. SP No. 90361;[20] CCPs appeal was docketed as CA-G.R. SP No.
90383;[21]
and DPCCs appeal was docketed as CA-G.R. SP No. 90384.[22] Eventually, the cases were consolidated.[23]
On
WHEREFORE, the Final Award, dated P4,232,264.12
is DELETED.
Philippine Charter Insurance Corporation
and Dynamic Planners and Construction Corporation are ORDERED jointly and
severally to pay Central Colleges of the P13,924,351.47
under Surety Bond No. PCIC-45542, Performance Bond No. PCIC-45541 (as modified
by Bond Endorsement No. E-2003/12527), and Performance Bond No.
PCIC-46172. Said amount shall bear
interest at the rate of 6% per annum from the date of demand made on
SO ORDERED.[28]
PCIC moved
for the reconsideration of the said decision, but the CA disposed of it with a
denial in its
Hence, this
petition.[29]
In its
Memorandum,[30]
PCIC submits the following issues for resolution:
1st
Issue: Whether or not the CA grossly erred in sustaining the CIAC award finding
petitioner liable to respondent CCP under the performance bonds and the surety
bond?
2nd
Issue: Whether or not the CA grossly erred in upholding the CIAC award
pronouncing respondent CCP as rightfully and justifiably entitled to terminate
the contract agreement?
3rd
Issue: Whether or not the CA grossly erred in deleting the counterclaim of
respondent DPCC covering the costs of materials, equipment, formworks and
scaffoldings left at site and in denying petitioner to benefit from the
counterclaim?[31]
PCIC argues
that the CA erred in sustaining the award of P692,890.74 representing
Performance Bond PCIC-46172 because the obligation guaranteed by said
performance bond was already completed, therefore, no liability should attach against
the said bond.[32]
In this
regard, the petitioner has a point.
Although this
particular issue was not expressly raised in the parties Terms of Reference,[33]
nevertheless, the issue on Performance Bond PCIC- 46172 was extensively
discussed during the arbitral tribunals hearing of
ATTY. G. Q.
ENRIQUEZ:[34]
I am calling your attention to Bond
PCIC-45542.
MR. CRISPINO P.
REYES:[35]
You are calling my attention where?
ATTY. G. Q.
ENRIQUEZ:
In the terms of Reference, can we
please get the copy of that so that we can be reminded?
ATTY. B.G.
FAJARDO:
There are only two, Counsel-the
Performance and the Surety Bond.
ATTY. G. Q.
ENRIQUEZ:
Performance
Bond in the amount of-
MR. CRISPINO P.
REYES:
Were interested in 45542 and were interested in 45541. What were no longer interested in, we have
to be candid to this Honorable Tribunal, we are no longer interested, [we] no
longer want to collect on Performance Bond 46172.
ATTY. A.V. CAMARA:[36]
At this point in time, we would like
to be of record that although that Bond 46172 covering the amount of P692,890.74
per their declaration had already been satisfied that is why only two bonds now
are being
ATTY. J.N. RABOCA:
May I make a qualification with
that, your Honor? Its not that it was satisfied. Its that the Claimant is not claiming
anymore because all the works under this bond were already accomplished.
ATTY. G. Q.
ENRIQUEZ:
Yes, because you have already a
Certificate of Acceptance.
ATTY. J.N. RABOCA:
Correct.
ATTY. G. Q.
ENRIQUEZ:
So, were just narrowing down into
two bonds.
ATTY. A.V. CAMARA:
The two bonds.
ATTY. G. Q.
ENRIQUEZ:
Okay.
ATTY. A.V. CAMARA:
Then therefore the liability on 46172
should be released. They are only
covered by the pleadings especially the Complaint.
MR. CRISPINO P.
REYES:
We do not dispute this.[37] [Emphases supplied]
It is clear from the testimony of Crispino P.
Reyes, CCPs President, that the school no longer wants to collect on Performance
Bond PCIC 46172 (with a value of P692,890.74). This statement before the arbitral tribunal is
a judicial admission effectively settling the issue with respect to PCIC 46172. Section 4, Rule 129 of the Rules of Court
provides:
Sec. 4. Judicial admissions. An admission, verbal or written, made by a party in the course of
the proceedings in the same case, does not require proof. The admission may be
contradicted only by showing that it was made through palpable mistake or that
no such admission was made.
A party may make judicial admissions
in (a) the pleadings; (b) during the trial, either by verbal or written
manifestations or stipulations; or (c) in other stages of the judicial
proceeding.[38]
It is an established principle that judicial admissions cannot be contradicted
by the admitter who is the party himself[39] and binds the person who makes the same, and absent
any showing that this was made thru palpable mistake, no amount of
rationalization can offset it.[40]
Since CCP, through its President,
judicially admitted that it is no longer interested in pursuing PCIC-46172, the
scope of its claim will just be confined to Surety Bond No. PCIC-45542 and Performance Bond No.
PCIC-45541.
PCIC claims
that DPCC was already in default as early as
The Court finds
itself unable to agree. Article 1169 of
the New Civil Code provides:
Art. 1169.
Those obliged to deliver or to do something incur in delay from the time
the obligee judicially or extrajudicially demands from them the fulfillment of
their obligation.
The civil law concept of delay or
default commences from the time the obligor demands, judicially or
extrajudicially, the fulfillment of the obligation from the obligee. In
legal parlance, demand is the assertion of a legal or procedural right.[43] Hence, DPCC incurred delay from the time CCP called
its attention that it had breached the contract and extrajudicially demanded the
fulfillment of its commitment against the bonds.
It is the obligors culpable delay,
not merely the time element, which gives the obligee the right to seek the performance
of the obligation. As such, CCPs cause of action accrued from
the time that DPCC became in culpable delay as contemplated in the surety and
performance bonds. In fact, Surety Bond PCIC-45542,[44]
Performance Bond PCIC-45541[45] and
PCIC-46172 each specified how claims should be made against it:
Surety Bond
PCIC-45542[46]
The
liability of PHILIPPINE CHARTER INSURANCE CORPORATION, under this bond will
expire on October 30, 2003; Furthermore,
it is hereby agreed and understood that PHILIPPINE CHARTER INSURANCE
CORPORATION will not be liable for any claim not presented to it in writing
within FIFTEEN (15) DAYS from the expiration of this bond, and that the Obligee
hereby waives its right to claim or file any court action against the surety
after the termination of FIFTEEN (15) DAYS from the time its cause of action
accrues.
Performance Bond PCIC-45541[47] and
PCIC-46172:[48]
The liability of PHILIPPINE
CHARTER INSURANCE CORPORATION, under this bond will expire on October 30,
2003; Furthermore, it is hereby agreed
and understood that PHILIPPINE CHARTER INSURANCE CORPORATION will not be liable
for any claim not presented to it in writing within TEN (10) DAYS from the expiration
of this bond or from the occurrence of the default or failure of the Principal,
whichever is the earliest, and the Obligee hereby waives its right to file any
claims against the Surety after termination of the period of ten (10) DAYS
above mentioned after which time this bond shall definitely terminate and be
deemed absolutely cancelled.
Thus, DPCC became in default on
Upon notice
of default of obligor DPCC, PCICs liability, as surety, was already attached. A surety under Article 2047 of the New Civil Code solidarily binds itself with the
principal debtor to assure the fulfillment of the obligation:
Art. 2047. By guaranty a person, called
the guarantor, binds himself to the creditor to fulfill the obligation of the
principal debtor in case the latter should fail to do so.
If a person binds himself solidarily with
the principal debtor, the provisions of Section 4, Chapter 3, Title I of this
Book shall be observed. In such case the contract is called a
suretyship. [Emphasis supplied]
The case of Asset Builders Corporation v.
Stronghold Insurance Company, Inc.[49]
explains how a surety agreement works:
As provided in Article 2047, the surety
undertakes to be bound solidarily with the principal obligor. That
undertaking makes a surety agreement an ancillary contract as it presupposes
the existence of a principal contract.
Although the contract of a surety is in
essence secondary only to a valid principal obligation, the surety becomes
liable for the debt or duty of another although it possesses no direct or
personal interest over the obligations nor does it receive any benefit
therefrom.[50]
Let it be stressed that notwithstanding the fact that the surety contract is
secondary to the principal obligation, the surety assumes liability as a
regular party to the undertaking.[51]
Stronghold Insurance
Company, Inc. v. Republic-Asahi Glass Corporation,[52] reiterating the ruling in Garcia v. Court of Appeals,[53]
expounds on the nature of the suretys liability:
X x x. The suretys obligation is not an
original and direct one for the performance of his own act, but merely
accessory or collateral to the obligation contracted by the principal. Nevertheless, although the contract of a
surety is in essence secondary only to a valid principal obligation, his
liability to the creditor or promisee of the principal is said to be direct,
primary and absolute; in other
words, he is directly and equally bound
with the principal.
Suretyship, in essence, contains two
types of relationship the principal relationship between the obligee and the
obligor, and the accessory surety
relationship between the principal and
the surety. In this arrangement, the obligee accepts the
suretys solidary undertaking to pay if the obligor does not pay. Such acceptance, however, does not change in
any material way the obligees relationship with the principal obligor. Neither
does it make the surety an active party to the principal obligee-obligor
relationship. Thus, the acceptance does
not give the surety the right to intervene in the principal contract. The suretys role arises only upon the
obligors default, at which time, it can be directly held liable by the obligee
for payment as a solidary obligor.[54]
[Emphases supplied]
Having
acted as a surety, PCIC is duty bound to perform what it has guaranteed on its
surety and performance bonds, all of which are callable on demand, occasioned
by its principals default.
PCIC also proffers that CCP did not
file any claim against the bonds after its extension.[55]
The Court is not persuaded. CCP need not file another claim as to the supposed
extended bonds because the
As to whether CCP was legally warranted
in terminating the contract with DPCC for its failure to comply with its
obligation, the Court affirms the CAs disquisition. The option to terminate the contract is
clearly apparent in the parties agreement.
Specifically, Article 16 of the Contract Agreement provides:
ARTICLE 16
Termination
16.1 The OWNER
shall have the right to terminate this CONTRACT after giving fifteen (15) days
notice in writing for any of the following causes:
16.1.1.
Substantial failure on the part of the CONTRACTOR in fulfilling its obligation;
16.1.2.
Assignment or sub-contracting of any of the works herein by the CONTRACTOR
without approval by the OWNER;
16.1.3
The CONTRACTOR is willfully violating any of the material conditions,
stipulations and covenants of this CONTRACT and/or the attachments hereto. In the event of termination of this CONTRACT
pursuant to the above, any amount owing to the CONTRACTOR at the time of such
termination for services already rendered and/or materials delivered and taken
over by the OWNER shall be withheld by the OWNER pending the determination of
value of damages sustained by the OWNER by reason of such termination and
payment of such damages by the CONTRACTOR.
The
Court also finds nothing improper in the deletion by the CA of the award of
actual damages in favor of DPCC. Actual or compensatory damages means the adequate
compensation for pecuniary loss suffered and for profits the obligee failed to
obtain. To be entitled to actual or
compensatory damages, it is basic that there must be pleading and proof of
actual damages suffered.[56] Equally vital to the fact that the amount of loss must be
capable of proof, such loss must also be actually proven with a reasonable
degree of certainty, premised upon competent proof or the best evidence
obtainable.[57] The
burden of proof of the damage suffered is, consequently, imposed on the party
claiming it[58] who, in turn, should
present the best evidence available in support of his claim. It could include
sales and delivery receipts, cash and check vouchers and other pieces of
documentary evidence of the same nature pertaining to the items he is seeking
to recover. In the absence of corroborative evidence, it has been held that self-serving
statements of account are not sufficient basis for an award of actual damages.[59] Moreover, a claim for actual damages cannot
be predicated on flimsy, remote, speculative, and insubstantial proof.[60] Thus, courts are required to state the
factual bases of the award.[61]
In this
case, DPCC was not able to establish that it is entitled to the actual damages that
it prayed for in its counterclaim. As
the CA put it, while Dynamic (DPCC) presented receipts issued by its suppliers
of materials, equipment, formworks and scaffoldings, it failed to prove that
the items in the receipts correspond to the items allegedly left at the work
site.[62] Besides,
the Court cannot grant a relief in its favor because DPCC did not appeal the
decision of the CA.
WHEREFORE, the
petition is PARTLY GRANTED. The
June 29, 2007 Decision of the Court of Appeals in CA-G.R. SP Nos. 90361, 90383
and 90384 is MODIFIED to read as follows:
Philippine Charter Insurance Corporation and Dynamic
Planners and Construction Corporation are ordered to, jointly and severally,
pay Central Colleges of the P13,231,460.73 under Surety Bond No. PCIC-45542 and
Performance Bond No. PCIC-45541 (as modified by Bond Endorsement No.
E-2003/12527). Said amount shall bear interest at the rate of 6% per annum from
the date of demand made on
SO
ORDERED.
JOSE CATRAL
WE CONCUR:
PRESBITERO
J. VELASCO, JR.
Associate Justice
Chairperson
DIOSDADO M.
PERALTA ROBERTO A.
ABAD
Associate
Justice Associate Justice
ESTELA M.
PERLAS-BERNABE
Associate Justice
A T T E S T A T I O N
I attest that the conclusions in the above Decision
had been reached in consultation before the case was assigned to the writer of
the opinion of the Courts Division.
PRESBITERO
J. VELASCO, JR.
Associate Justice
Chairperson,
Third Division
C E R T I F I C A T I O N
Pursuant to Section 13, Article VIII of the
Constitution and the Division Chairpersons Attestation, I certify that the
conclusions in the above Decision had been reached in consultation before the
case was assigned to the writer of the opinion of the Courts Division.
RENATO
C. CORONA
Chief Justice
[1] Rollo, pp. 8-12. Penned by Associate Justice Ricardo R. Rosario, with Associate Justice Rebecca De Guia-Salvador and Associate Justice Magdangal de Leon, concurring.
[2]
[3]
[4]
[5]
[6]
[7]
[8]
[9]
[10]
[11]
[12]
[13]
[14]
[15]
[16]
[17]
[18]
[19]
[20]
[21]
[22]
[23]
[24]
[25]
[26]
[27]
[28]
[29]
[30]
[31]
[32]
[33]
[34] Counsel for Dynamic Planners and Construction Corporation (DPCC).
[35]
President of Central Colleges of the
[36] Counsel for Philippine Charter Insurance Corporation (PCIC).
[37] Records
I, pp. 418-420, TSN,
[38] Binarao v. Plus Builders, Inc., 524
Phil. 361, 365 (2006).
[39] Regalado,
Remedial Law Compendium, Volume II, 7th Revised Edition, 1995, p.
651, citing Granada v. PNB, 124 Phil. 561 (1966).
[40]
Yuliongsiu v. PNB, 130
Phil. 575, 580 (1968).
[41] Rollo, p. 933.
[42]
[43] Blacks
Law Dictionary, Abridged 8th ed., 2005, p. 364.
[44] Rollo,
p. 195.
[45]
[46]
[47]
[48]
[49] G.R.
No. 187116,
[50] Security Pacific Assurance Corporation v. Hon. Tria-Infante, 505 Phil. 609, 620 (2005).
[51] Philippine Bank of Communications v. Lim,
495 Phil. 645, 651 (2005).
[52] 525
Phil. 270, 280 (2006).
[53] G.R.
No. 80201,
[54] Intra-Strata Assurance Corporation v. Republic,
G.R. No. 156571, July 9, 2008, 557 SCRA 363, 375-376.
[55] Rollo, p. 946.
[56]
[57] Manila Electric Corporation v. T.E.A.M.
Electronics Corporation, G.R. No. 131723, December 13, 2007, 540 SCRA 62,
79.
[58] Luxuria Homes, Inc. vs. Court of Appeals, 361 Phil. 989, 1001-1002 (1999).
[59] MCC Industrial Sales Corporation v.
Ssangayong Corporation, G.R. No. 170633, October 17, 2007, 536 SCRA 408,
467-468.
[60] Hanjin Heavy Industries and Construction
Co., Ltd. v. Dynamic Planners and Construction Corp., G.R. Nos. 169408
& 170144, April 30, 2008, 553 SCRA 541, 567 .
[61]
[62] Rollo, p. 37.