Republic of the
Supreme Court
THIRD DIVISION
PHILIPPINE
CHARTER INSURANCE CORPORATION, Petitioner, - versus - PETROLEUM
DISTRIBUTORS & SERVICE CORPORATION Respondent. |
|
G.R. No.
180898 Present: VELASCO, JR., J., Chairperson, PERALTA, ABAD, PERLAS-BERNABE,
JJ. Promulgated: April 18, 2012 |
X
--------------------------------------------------------------------------------------
X
D E C I S I O N
MENDOZA, J.:
Before the Court is a petition for review under Rule
45 of the Rules of Court seeking the reversal of the July 31, 2007 Decision[1] and the
December 28, 2007 Resolution[2] of the
Court of Appeals (CA) in CA-G.R. CV No. 82417, which affirmed with
modification the January 12, 2004 Decision of the Regional Trial Court, Branch 111,
Pasay City (RTC).
The
Facts:
On January 27, 1999, respondent Petroleum
Distributors and Services Corporation (PDSC), through its president,
Conrado P. Limcaco, entered into a building contract[3] with
N.C. Francia Construction Corporation (FCC), represented by its president
and chief executive officer, Emmanuel T. Francia, for the construction of a
four-story commercial and parking complex located at MIA Road corner Domestic
Road, Pasay City, known as Park N Fly Building (Park N Fly). Under the
contract, FCC agreed to undertake the construction of Park N Fly for the price
of ₱45,522,197.72.
The parties agreed that the construction work would
begin on
To ensure compliance with its obligation, FCCs
individual officers, namely, Natividad Francia, Emmanuel C. Francia, Jr., Anna
Sheila C. Francia, San Diego Felipe G. Bermudez, Emmanuel T. Francia,
Charlemagne C. Francia, and Ruben G. Caperia, signed the Undertaking of Surety[8]
holding themselves personally liable for the accountabilities of FCC.
Also, FCC procured Performance Bond No. 31915 amounting
to ₱6,828,329.00 from petitioner Philippine Charter Insurance Corporation
(PCIC) to secure full and faithful performance of its obligation under
the Building Contract.[9]
The construction of the Park N Fly started on
Pursuant to the Building Contract, PDSC sourced out
construction materials and subcontracted various phases of the work to help
obtain the lowest cost of the construction and speed up the work of the project.
These resulted in the reduction of the contract price.[10]
During the Phase 1 of the project, PDSC noticed that
FCC was sixteen (16) days behind schedule. In a Letter[11] dated
Consequently, on
On even date, PDSC and FCC likewise executed a
memorandum of agreement (MOA),[16]
wherein the parties agreed to revise the work schedule of the project. As a
consequence, Performance Bond No. 31915 was extended up to
For failure of FCC to accomplish the project within
the agreed completion period, PDSC, in a letter[18] dated
Despite notice, PDSC did not receive any reply from either
FCC or PCIC, constraining it to file a complaint[21] for
damages, recovery of possession of personal property and/or foreclosure of
mortgage with prayer for the issuance of a writ of replevin and writ of
attachment, against FCC and its officers before the RTC. PDSC later filed a
supplemental complaint[22] impleading
PCIC, claiming coverage under Performance Bond No. 31915 in the amount of ₱6,828,329.66.
In its Amended Answer with affirmative defense and
counterclaim,[23]
FCC admitted that it entered into a contract with PDSC for the construction of
the Park N Fly building. It, however, asserted that due to outsourcing of
different materials and subcontracting of various phases of works made by PDSC,
the contract price was invariably reduced to ₱19,809,822.12.
FCC denied
any liability to PDSC claiming that any such claim by the latter had been
waived, abandoned or otherwise extinguished by the execution of the
For its part, PCIC averred that as a surety, it was
not liable as a principal obligor; that its liability under the bond was
conditional and subsidiary and that it could be made liable only upon FCCs
default of its obligation in the Building Contract up to the extent of the
terms and conditions of the bond. PCIC also alleged that its obligation under the
performance bond was terminated when it expired on
PCIC added that PDSCs claim against it had been
waived, abandoned or extinguished by the
Nonetheless, in the event that PCIC would be made
liable, its liability should be in proportion to the liabilities of the other
sureties.
On
FCC and PCIC filed their respective notice of appeal[26] with
the RTC. On
On
WHEREFORE, the Decision dated 12
January 2004 of the Regional Trial Court of Pasay City, Branch 111 is AFFIRMED
with MODIFICATION in that appellants N.C. Francia Construction Corporation,
Natividad Francia, Emmanuel Francia, Jr., Anna Sheila Francia San Diego, Felipe
Bermudez, Emmanuel Francia, Charlemagne Francia, Ruben Caperia, and Philippine
Charter Insurance Corporation are hereby held solidarily liable to pay appellee
Petroleum Distributors & Services Corporation (1) liquidated damages in the
sum of ₱3,882,725.13, which
shall earn legal interest at the rate of 6% per annum from 10 January 2000
until finality of this judgment; (2) attorneys fees amounting to ₱50,000.00; and (3)
cost of suit. Pursuant to Performance Bond No. 31915, the liability of
appellant Philippine Charter Insurance Corporation should not exceed ₱6,828,329.66.
Appellants N.C Francia
Construction Corporation, Emmanuel Francia and Natividad Francia are adjudged
liable to pay appellant Philippine Charter Insurance Corporation for the amount
the latter may have paid under Performance Bond No. 31915.
SO ORDERED.[29]
FCC and PCIC filed their separate motions for
reconsideration[30]
but the CA denied them in its
Hence, this petition.
It is well to note that only PCIC appealed the CAs
decision. It became final and executory with regard to FCC and the other
parties in the case. Hence, the Court shall limit its discussion to the
liability of PCIC.
In its Memorandum,[32] PCIC
anchored its petition on the following issues:
1. Whether or
not the Court of Appeals, in adjudging Petitioner liable for liquidated damages,
expanded liability under Performance Bond No. 31915 which on its face answers
only for actual and compensatory damages, not liquidated damages.
Assuming arguendo
liability for liquidated damages under the performance bond, whether or not the
Court of Appeals erred in not declaring that the award of liquidated damages is
iniquitous and unconscionable and in not applying the provisions of Article
2227, Civil Code, and Palmares v. Court of Appeals, 288 SCRA 422.
2. Whether or
not the Memorandum of Agreement dated Sept. 10, 1999 entered into by respondent
and Francia Construction, confirmed in a letter dated Sept. 20, 1999, ---
without Petitioners knowledge or consent---, the effect that all costs,
expenses, payments and obligations shall be deemed paid, performed and fully
settled as of Sept. 10, 1999, discharged Petitioner from liability under the
performance bond under Article 2079, Civil Code.
3. Whether or
not the Court of Appeals, having made the finding of fact that the sums of
Php2,793,000.00 and Php662,836.50 should be deducted from Php3,882,725.13,
erred in not deducting the amounts in the dispositive portion of the decision.[33]
In sum, the issues before the Court are (1) whether
or not PCIC is liable for liquidated damages under the performance bond; (2)
whether or not the September 10, 1999 MOA executed by PDSC and FCC extinguished
PCICs liability under the performance bond; and (3) whether or not the amounts
of ₱2,793,000.00 and ₱662,836.50 are deductible from the liquidated
damages awarded by the CA.
PCIC argues that in case of a breach of contract,
the performance bond is answerable only for actual or compensatory, not for
liquidated damages. The terms of the bond are clear that the liability of the
surety is determined by the contract of suretyship and cannot be extended by
implication beyond the terms of the contract. Nonetheless, even assuming that it
is liable under the performance bond, the liability should be based on equity.
It claims that it is unlawful and iniquitous to hold FCC responsible for the
delay of the subcontractor commissioned by PDSC.
PCIC adds that the act of PDSC of subcontracting the
various stages of the project resulted in a revision of work schedule and
extension of the completion date that ultimately released both FCC and PCIC of whatever
claims PDSC may have against them. PCIC is of the impression that since the
subcontracting made by PDSC was made without its consent and knowledge, its
liability under the performance bond should be extinguished.
PCIC also pointed out that the receivable in the
amount of ₱2,793,000.00 acquired by PDSC from Caltex and the proceeds
from the auction sale in the sum of ₱662,836.50 should be deducted from
the award of ₱3,882,725.13.
The Court finds no merit in the petition.
The Building Contract entered into by PDSC and FCC provides
that:
Art. 2 ESSENCE
OF THE CONTRACT
2.1 It is understood that time, quality of work in accordance with the
OWNERs requirements, and reduced construction costs are the essence of this
Contract.
2.2 The CONTRACTOR shall commence the construction for the first two (2)
levels not later than five (5) days immediately after the date of execution of
this Contract and shall regularly proceed and complete the construction within
Two Hundred Fifty-Nine (259) calendar days reckoned from the date of signing of
this Contract or not later than October 15, 1999, whichever is earlier. To
ensure completion of the work within the time given herein, construction work
shall be conducted at least twenty hours each day with at least two (2) work
shift for every day actually worked.
2.3 In the event that the construction is not
completed within the aforesaid period of time, the OWNER is entitled and shall
have the right to deduct from any amount that may be due to the CONTRACTOR the
sum of one-tenth (1/10) of one percent (1%) of the contract price for every day
of delay in whatever stage of the project as liquidated damages, and not by way
of penalty, and without prejudice to such other remedies as the OWNER may, in
its discretion, employ including the termination of this Contract, or
replacement of the CONTRACTOR.
2.4 Furthermore, the CONTRACTOR agrees not to request any extension of
time due to any delay in the procurement of materials needed in the
construction other than due to circumstances of Force Majeure. Force Majeure
is hereby defined as any war, civil commotion and disturbance, acts of God or
any other cause beyond the CONTRACTORs control and without any contributing
fault on the part of the CONTRACTOR.
2.5 Contractor shall
arrange, schedule and carry on the work so as not to interfere with the
delivery and erection of the work of others. To facilitate the erection of such
other work, the CONTRACTOR shall cease or resume work at any point or stage of
the Project, when so directed by the OWNER or his duly authorized
representative. [Emphasis supplied]
Paragraph 2.3 of the Building Contract clearly provides
a stipulation for the payment of liquidated damages in case of delay in the
construction of the project. Such is in the nature of a penalty clause fixed by
the contracting parties as a compensation or substitute for damages in case of
breach of the obligation.[34] The
contractor is bound to pay the stipulated amount without need for proof of the
existence and the measures of damages caused by the breach.[35]
Article 2226 of the Civil Code allows the parties to
a contract to stipulate on liquidated damages to be paid in case of
breach. It is attached
to an obligation in order to insure performance and has
a double function: (1) to provide for liquidated damages, and (2) to strengthen
the coercive force of the obligation by the threat of greater responsibility in
the event of breach.[36]
As a general rule, contracts constitute
the law between the parties, and they are bound by its stipulations.[37] For as long as they are not contrary to law,
morals, good customs, public order, or public policy, the contracting parties
may establish such stipulations, clauses, terms and conditions as they may deem
convenient.[38]
In the case at bench, the performance bond issued by
PCIC specifically provides that:
KNOW ALL MEN BY THESE PRESENTS:
That we, N.C. FRANCIA CONSTRUCTION
CORPORATION of Merryland Corporate Offices,
THE
CONDITION OF THIS OBLIGATION ARE AS FOLLOWS:
WHEREAS, the
above bounden principal, on the ____ day of ________ 19___ entered into an
________________ with ___________, to fully and faithfully guarantee that the
above-named Principal shall furnish, deliver, place and complete any and all
necessary materials, labor, plant, tools appliances and equipment, supplies,
utilities transportation, superintendence, supervision and all other facilities
in connection with the construction of a 4-storey commercial/parking complex
situated at MIA Road cor. Domestic Road, Pasay City as per attached Building
Contract dated January 27, 1999.
Provided, however, that the
liability of the Surety Company under this bond shall in no case exceed the
face value hereof.
WHEREAS, said oblige requires said
principal to give a good and sufficient bond in the above stated sum to secure
the full and faithful performance on its part of said undertaking.
NOW THEREFORE, if the principal
shall well and truly perform and fulfill all the undertakings, covenants, terms
conditions and agreements stipulated in said undertakings then this obligation
shall be null and void; otherwise it shall remain in full force and effect.
[Emphasis Supplied]
By the language of the performance bond issued by PCIC,
it guaranteed the full and faithful compliance by FCC of its obligations in the
construction of the Park N Fly. In fact, the primary purpose for the
acquisition of the performance bond was to guarantee to PDSC that the project
would proceed in accordance with the terms and conditions of the contract and
to ensure the payment of a sum of money in case the contractor would fail in
the full performance of the contract.[39] This
guaranty made by PCIC gave PDSC the right to proceed against it (PCIC)
following FCCs non-compliance with its obligation.
A contract of suretyship is an agreement whereby a
party, called the surety, guarantees the performance by another party, called
the principal or obligor, of an obligation or undertaking in favor of another
party, called the obligee.[40] Although the contract of a surety is secondary
only to a valid principal obligation, the surety becomes liable for the debt or
duty of another although it possesses no direct or personal interest over the
obligations nor does it receive any benefit therefrom.[41] This was explained in the
case of Stronghold Insurance Company, Inc. v. Republic-Asahi Glass
Corporation,[42]
where it was written:
The suretys obligation is not an original and
direct one for the performance of his own act, but merely accessory or
collateral to the obligation contracted by the principal. Nevertheless,
although the contract of a surety is in essence secondary only to a valid
principal obligation, his liability to the creditor or promisee of the
principal is said to be direct, primary and absolute; in other words, he is
directly and equally bound with the principal.
Corollary, when PDSC communicated to FCC that it was
terminating the contract, PCICs liability, as surety, arose. The claim of PDSC
against PCIC occurred from the failure of FCC to perform its obligation under
the building contract. As mandated by Article 2047 of the Civil Code, to wit:
Article 2047. By guaranty, a
person, called the guarantor, binds himself to the creditor to fulfill the
obligation of the principal debtor in case the latter should fail to do so.
If a person binds himself
solidarily with the principal debtor, the provisions of Section 4, Chapter 3,
Title I of this Book shall be observed. In such case, the contract is called a
suretyship.
Thus, suretyship arises upon the solidary
binding of a person deemed the
surety with the principal debtor for the purpose of fulfilling an obligation.[43] A
surety is considered in law as being the same party as the debtor in relation
to whatever is adjudged touching the obligation of the latter, and their
liabilities are interwoven as to be inseparable.[44]
Therefore, as surety, PCIC becomes
liable for the debt or duty of FCC although it possesses no direct or personal
interest over the obligations of the latter, nor does it receive any benefit
therefrom.[45]
The Court also found untenable the contention of PCIC
that the principal contract was novated when PDSC and FCC executed the
A surety agreement has two types of relationship:
(1) the principal relationship between the obligee and the obligor; and (2) the
accessory surety relationship between the principal and the surety. The obligee
accepts the suretys solidary undertaking to pay if the obligor does not pay.
Such acceptance, however, does not change in any material way the obligees
relationship with the principal obligor. Neither does it make the surety an
active party in the principal obligor-obligee relationship. It follows,
therefore, that the acceptance does not give the surety the right to intervene
in the principal contract. The suretys role arises only upon the obligors
default, at which time, it can be directly held liable by the obligee for
payment as a solidary obligor.[46]
Furthermore, in order that an obligation may be
extinguished by another which substitutes the same, it is imperative that it be
so declared in unequivocal terms, or that the old and new obligation be in
every point incompatible with each other.[47] Novation
of a contract is never presumed. In the absence of an express agreement,
novation takes place only when the old and the new obligations are incompatible
on every point.[48]
Undoubtedly, a surety is released from its
obligation when there is a material alteration of the principal contract in
connection with which the bond is given, such as a change which imposes a new
obligation on the promising party, or which takes away some obligation already
imposed, or one which changes the legal effect of the original contract and not
merely its form.[49]
In this case, however, no new contract was concluded and perfected between PDSC
and FCC. A reading of the
At first blush, it would seem that
the parties agreed on a revised timetable for the construction of Park N Fly.
But then, nowhere in the voluminous records of this case could We find the
Annex A mentioned in the above-quoted agreement which could have shed light
to the question of whether a new period was indeed fixed by the parties. The
testimony of appellant Emmanuel Francia, Sr., President and Chief Executive
Officer of appellant N.C, Francia, candidly disclosed what truly happened to
Annex A, as he admitted that no new PERT/CPM was actually attached to the
Memorandum of Agreement.
Accordingly, We find no compelling
reason to declare that novation ensued under the prevailing circumstances. The
execution of the Building Contract dated
It must likewise be emphasized that pursuant to the
September 10, 1999 MOA, PCIC extended the coverage of the performance bond
until
Finally, as pointed out by PCIC, the receivable in
the amount of ₱2,793,000.00 acquired by PDSC from Caltex and the proceeds
from the auction sale in the sum of ₱662,836.50 should be deducted from
the award of ₱3,882,725.13. There is no quibble on this point. The ruling
of the CA on the matter is very clear. It reads:
With these points firmly in mind,
We proceed to the next question raised by appellants whether the value of the
securities given as well as the proceeds of the sale of chattels should be
deducted from the claim of liquidated damages.
We answer in the affirmative.
There is no quibble that appellant
N.C Francia assigned a portion of its receivables from Caltex Philippines, Inc.
in the amount of ₱2,793,000.00 pursuant to the Deed of Assignment dated
So too, vehicles and equipment
owned by appellant N.C. Francia were sold at public auction at ₱1,070,000.00. After
deducting storage fees, the amount of ₱662,836.50 was deposited before the court a quo.
The latter amount accrues in favor of appellee Petroleum Distributors as
partial payment of its claim for liquidated damages.
WHEREFORE, the petition is DENIED. The July 31, 2007 Decision and
SO ORDERED.
JOSE CATRAL
Associate
Justice
WE CONCUR:
PRESBITERO J. VELASCO, JR.
Associate
Justice
Chairperson
DIOSDADO M.
PERALTA ROBERTO A.
ABAD
Associate Justice Associate Justice
ESTELA M. PERLAS-BERNABE
Associate
Justice
A T T E S T A T
I O N
I attest that
the conclusions in the above Decision had been reached in consultation before
the case was assigned to the writer of the opinion of the Courts Division.
PRESBITERO J. VELASCO, JR.
Associate
Justice
Chairperson,
Third Division
C E R T I F I C
A T I O N
Pursuant to
Section 13, Article VIII of the Constitution and the Division Chairpersons
Attestation, I certify that the conclusions in the above Decision had been
reached in consultation before the case was assigned to the writer of the
opinion of the Courts Division.
RENATO
C. CORONA
Chief Justice
[1] Rollo,
pp. 28-48. Penned by Associate Justice Japar B. Dimaampao and concurred in by
Associate Justice Mario L. Guaria III and Associate Justice Sixto C. Marella,
Jr.
[2]
[3] Annex A of the Complaint, Records,
Volume I, pp. 26-43.
[4] Annex B
of the Complaint, CPM & Bar Chart, Records, Volume I, p. 46.
[5]
[6]
[7] Article 2.3 of the Building
Contract, Annex A of the Complaint, Records, Volume I, p. 28.
[8] Annex C of the Complaint, Records,
Volume I, p. 60.
[9] Annex B
of the Complaint, Records, Volume III, pp. 1173-1174.
[10] Letter dated
[11] Records,
Volume III, p. 1177.
[12] Exhibit
Q, Records, Volume III, p. 1178.
[13] Exhibit
R, Records, Volume III, p. 1181.
[14] Exhibit
U, Records, Volume III, pp. 1186-1187..
[15] Annex E
of the Complaint, Records, Volume I, pp. 63-66.
[16] Annex D
of the Complaint, Records, Volume I, pp. 61-62.
[17] Exhibit
N-1, Records, Volume III, p. 1175.
[18] Annex F,
Records, Volume I, pp. 70-71.
[19] Annexes
G to M, Records, Volume I, pp. 72-85.
[20] Annex D,
Records, Volume II, p. 682.
[21] Records,
Volume I, pp. 2-25.
[22] Records,
Volume II, pp. 654-659.
[23] Records,
Volume I, pp. 290-315.
[24] Answer to Supplemental
Complaint, Records, Volume II, pp. 761-765.
[25] Records,
Volume IV, pp. 1547-1558.
[26]
[27]
[28] CA Rollo, pp. 275-293.
[29] Rollo, p. 48
[30] CA Rollo, pp. 297-303 & 314-319.
[31]
[32] Records, pp. 172-191.
[33]
[34] Comments and Jurisprudence on
Obligations and Contracts, Desiderio P. Jurado, Twelfth Revised Edition 2010,
p. 219.
[35] Titan Construction
Corporation v. Uni-Field Enterprises, Inc.,
[36] Filinvest Land, Inc. v. Court
of Appeals, 507 Phil. 259, 267 (2005).
[37] R & M General Merchandise,
Inc. v. Court of Appeals, 419 Phil.
131, 142 (2001).
[38] Art. 1306. The contracting parties may establish such stipulations,
clauses, terms and conditions as they may deem convenient, provided they are
not contrary to law, morals, good customs, public order, or public policy.
(1255a)
[39] http://www.
Businessdictionary.com/definition/performance-bond.html;
[40] Stronghold
Insurance Company, Incorporated v. Tokyu Construction Company, Ltd.,
G.R. Nos. 158820-21,
[41] Asset
Builders Corporation v. Stronghold Insurance Company, Incorporated,
G.R. No. 187116,
[42] G.R. No.
147561, 492 SCRA 179, 190,
[43] Prudential Guarantee and
Assurance, Inc. v. Equinox Land Corporation, G.R. Nos. 152505-06, September 13, 2007, 533 SCRA 257, 268.
[44] Security Pacific Assurance
Corporation v. Hon. Tria-Infante, 505 Phil. 609, 620, (2005).
[45]
[46] Asset Builders Corporation v. Stronghold Insurance
Company, Incorporated, supra note 41 at 380.
[47] Article 1292 Civil Code.
[48] Security Bank and Trust
Company, Inc, v.
[49] Stronghold Insurance Company,
Incorporated v. Tokyu Construction Company, Ltd., G. R. No. 158820-21,
[50] Paragraph 5 of the Memorandum
of Agreement dated
[51] Rollo, pp. 38-39
[52] Exhibit
N-1, Records, Volume III, p. 1175.