SECOND DIVISION
NATIONAL HOUSING AUTHORITY,
Petitioner, - versus - FIRST UNITED CONSTRUCTORS CORPORATION,
Respondent. |
|
G.R. No. 176535 Present: CARPIO, J., Chairperson, BRION, PERALTA,* BERSAMIN,** and PEREZ, JJ. Promulgated: September
7, 2011 |
x - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -x
D E C I S I O N
PEREZ, J.:
Before this Court is a petition for review
on certiorari under Rule 45 of the Revised Rules of Court filed by
petitioner National Housing Authority (NHA), seeking to reverse and set aside
the 1 August 2006 Decision[1] of
the Court of Appeals (CA) and its Resolution dated 31 January
2007[2] in CA-G.R. SP No. 81635.
In the questioned Decision, the
appellate court affirmed with modification the Decision promulgated on 7 January
2004[3] by
the Construction Industry Arbitration Commission (CIAC), thru a three member
Arbitral Tribunal[4] in CIAC
Case No. 14-2003 entitled First United
Constructors Corporation v. National Housing Authority, that granted an
arbitral award in favor of respondent First United Constructors Corporation
(FUCC); and in its assailed Resolution, refused to reconsider its Decision.
The Facts
From the Petition,[5]
the Comment[6] thereon
of respondent, petitioners Reply,[7]
and their respective Annexes,[8]
particularly the Complaint[9] of
respondent, petitioners Answer[10]
and the Joint Stipulations[11]
of the parties incorporated as Admitted Facts in the Supplemental Terms of
Reference,[12] all
filed with the CIAC, and from the CA Decision and the CIAC Decision, the Court
gathers the following relevant facts and antecedents:
Respondent FUCC was the contractor of
Phase I of the Freedom Valley Resettlement Project (the FVR Project or the
Project) of petitioner NHA.[13]
The FVR Project was a proposed
resettlement site for informal settlers of Metro Manila. Conceived in May 1996, it was the subject of
a Memorandum of Agreement entered into by and among the Housing & Urban
Development Coordinating Council (HUDCC), the Department of Environment &
Natural Resources (DENR), the Metro Manila Development Authority (MMDA) and the
Marilaque Commission.[14]
The FVR Project sits on a 750-hectare
property reserved as a resettlement site for the landless and homeless
residents of Metro Manila under Presidential Proclamation No. 799 dated 3 June
1996, situated in Sitio Boso-Boso, Brgy.
Phase I of the FVR Project called for
the development of an area of roughly 300 hectares of the resettlement site
into 7,500 home lots of 60 to 80 square meters per lot in three (3) residential
Clusters, namely: Cluster 1, Cluster 2 and Cluster 3.[16]
FUCC won the public bidding for the works
contract of the FVR Project conducted by NHA on 26 February 1998 with a bid
price of P568,595,780.00.[17]
The work consisted principally of
bulk earthworks and the construction of roads, drainage, water supply and
sewerage systems, slope protection and bridge structures, as well as survey
works, titling of the lots and other off-site works.[18]
On 2 March 1998, NHA issued a Notice
of Award[19] for
Phase I of the FVR Project to FUCC.
On 10 March 1998, NHA and FUCC
entered into a Contract for Land Development of
The
work duration stipulated in the Contract was three hundred sixty five (365)
days. The contract amount was the bid
price of FUCC, or P568,595,780.00.[21]
FUCC
commenced actual contract works on 16 March 1998. Counting 365 days, the original contract
expiration date was 15 March 1999.[22]
Unfortunately,
the FVR Project suffered various work suspensions and delays, so much so that
the project was not completed on 15 March 1999.[23]
There were also changes in the scope of work that necessitated the issuance of
variation orders, specifically Variation
Order No. 1,[24]
and Variation Order No. 2,[25]
which delayed the completion of the project further.
Variation Order No. 1
reduced the number of
home lots to be generated, from 7,500 under the original development plan
to only 4,980. Variation Order No. 2 further reduced that number to 4,032. These
changes in the scope of work resulted in the reduction of the contract price
from the original P568,595,780.00 to P488,393,466.98.[26]
Because of the delays engendered by
the suspension orders and the changes in the scope of the contract works, NHA
granted time extensions to FUCC, to wit:
an additional 279 calendar days under Time Extension No. 1;[27]
another extension of 200 calendar days in conjunction with the issuance of Variation Order No. 2;[28]
and finally, 200 more calendar days under Resumption
Order No. 2.[29] All told, a total of 679 calendar days were
added to the original work duration stipulated in the Contract. From 15 March
1999, the contract completion date was moved, initially, to 19 December 1999,
and finally, to 11 November 2001.[30]
In the course of the contract works,
FUCC submitted five (5) Progress Billings, all of which were paid by NHA, to
wit: Progress Billing No. 1[31]
in the amount of P52,707,464.21, for the period 16 March to 30 June
1998; Progress Billing No. 2[32]
in the amount of P14,343,039.55, for the period 1 July to 31 December
1998; Progress Billing No. 3[33]
in the amount of P47,329,827.89, for the period 1 January to 15 October
1999; Progress Billing No. 4[34]
in the amount of P114,494,481.30, for the period 16 October 1999 to 31 January
2001; and Progress Billing No. 5[35]
in the amount of P42,333,109.23, for the period 31 January to 30 June
2001.
The FVR Project was never completed
as envisioned and planned because NHA abandoned the original concept of the
Project. In a Resolution passed on 25 September
2001,[36]
the Board of Directors of NHA reclassified the FVR Project from a resettlement
site of informal settlers into a mixed-market site and services type of
project, and terminated the Contract.[37]
In a letter dated 17 October 2001,[38]
NHA formally advised FUCC of the termination of the Contract.
NHA terminated the Contract under the
Contractor Not at Fault clause of the General Conditions of the Contract.[39]
At the time the Contract was
terminated, FUCC had various claims pending with NHA in connection with the FVR
Project.
It appears that over a period of
almost five (5) years, FUCC pleaded and negotiated with various NHA officials
for the payment of these claims but its pleas fell on deaf ears.[40]
This impelled FUCC to pursue its
claims before the CIAC pursuant to Article XVII[41]
of the Contract by filing a Complaint[42]
against NHA on 17 July 2003. The case was docketed as CIAC Case
No.14-2003 entitled First United
Constructors Corporation vs. National Housing Authority.
In its
Complaint, FUCC prayed thus:
WHEREFORE, it is respectfully prayed that after proper arbitration proceedings, claimant be adjudged entitled to the payment of its claims, as follows:
1)
Payment for Accomplished Works Not Yet Billed in the
amount of P9,672,784.98;
2)
Payment for the Cost of Materials, Equipment,
Facilities, etc. Included for the Project in the amount of P4,801,992.82;
3)
Payment for Price Escalation in the amount of P27,794,126.25;
4)
Payment for Price Adjustment in the amount of P14,768,770.22;
5)
Payment for Disengagement Costs in the amount of P83,242,365.73;
6)
Payment for Idle Equipment in the amount of P142,780,800.00;
7)
Payment for Interest on Idle Equipment in the amount of
P44,262,048.00;
8) Payment for Attorneys Fees equivalent to Ten Percent (10%) of the total of the foregoing claims; and
9) Payment of Twelve Percent (12%) interest on the total arbitration award from the date of promulgation of judgment until fully paid.
Other
reliefs just and equitable are likewise prayed for.[43]
The CIAC appointed a 3-member Arbitral Tribunal (CIAC
Arbitral Tribunal) to adjudicate FUCCs claims.
NHA initially filed a Motion to Dismiss,[44]
claiming that FUCC had failed to exhaust all administrative remedies, which was
opposed by FUCC. In an Order dated 8 September
2003, the CIAC Arbitral Tribunal denied the motion and ordered NHA to file its
answer to FUCCs Complaint.[45]
In its Answer,[46]
NHA raised the following defenses, viz: FUCC had no right of action since its
recourse to arbitration was premature; there was no actual suspension of
contract works notwithstanding the suspension orders issued by NHA; the Contract
was not unilaterally terminated by NHA; FUCCs Progress Billing No. 6 should
only be for the amount of P6,496,926.29; FUCCs claim for Price
Escalation for Progress Billings Nos. 1 to 5 came too late in the day, and that
the amount that should be paid is only P26,297,951.62 and payable only
after FUCC procured the required surety bond;
and the claims for Payment for Cost of Materials, Equipment and
Facilities, Disengagement Cost, Cost of Idle Equipment and interests thereon,
are non-arbitrable issues. By way of
counter-claim, NHA prayed that it be allowed to recover from FUCC the amount of
P38 Million, which represents the remaining balance or unliquidated
portion of the P85.2 Million that NHA had advanced to FUCC at the start
of the FVR Project.
The issues having been joined, the CIAC
Arbitral Tribunal called the parties to a Preliminary Conference. The parties
subsequently agreed upon a Terms of Reference[47]
and a Supplemental Terms of Reference[48]
to guide the CIAC Arbitral Tribunal in the arbitration process and in the
resolution of the case. The parties also submitted to the CIAC
Arbitral Tribunal their Joint Stipulations,[49]
which were incorporated in the Supplemental Terms of Reference as
Admitted Facts.[50]
Under the Terms of Reference and the
Supplemental Terms of Reference, the CIAC Arbitral Tribunal was called upon to
resolve the following issues to determine the validity of FUCCs claims against
NHA, to wit:
1. Did
Claimant exhaust all administrative remedies before filing this arbitration
case?
1.1 Is claimants recourse to arbitration
premature?
2. Is
claimant entitled to its claims for:
2.1 payment
for accomplished works not yet billed (Progress Billing No. 6)? If so, how much?
2.1.1 Is the submission by the Claimant of the
files and folders covering the unpaid claims of the planters/farmers necessary
for the processing of its claim for accomplished works not yet billed (Progress
Billing No. 6)?
2.2 payment
for cost of materials, equipment, pro-rated cost of facilities constructed for the
project, etc.? If so, how much?
2.2.1 Whether or not these claims are arbitrable
or not [sic]
2.3 Price Escalation? If so, how much?
2.4 Price Adjustment? If so, how much?
2.5 Disengagement Costs? If so, how much?
2.5.1 Whether or not this claim is arbitrable or
not [sic]
2.6 Idle Equipment? If so, how much?
2.6.1 Whether or not this claim is arbitrable or
not [sic]
2.6.2 Was
there actual or physical suspension of the works for the period covered by the
suspension orders?
2.7 Interest on Idle Equipment? If so, how much?
3. Is
Respondent entitled to the recoupment of the remaining portion of the advance
payment made for the Project?
4. Are
the parties entitled to their respective claims for interest on the total
arbitration amount that would be adjudged in their own favor?
4.1 If so at what rate and from what period?
5. Who
between the parties is liable for the cost of arbitration?
6. Whether
or not the termination of the Contract is unilateral
6.1 Whether or not the Claimant opposed, contested
or protested the termination
7. Who
caused the alleged delays in the processing or payment of Claimant FUCCs
claims, if any?
8. Did
Claimant FUCC procure a Payment Guarantee Bond (Surety Bond) from either the
GSIS or any bona fide private surety company?
9. Was
the procurement by Claimant FUCC of the Payment Guarantee Bond (Surety Bond) a
condition for the payment of its claims for Progress Billing No. 6 and Price
Escalation for Progress Billing Nos. 1 to 5?[51]
To prove its claims, FUCC
presented one witness in the person of Engr. Ben S. Dumaliang (Engr. Dumaliang),
the Project Director of FUCC for the FVR Project, and submitted his Affidavit
in Question-and-Answer Form dated 4 November 2003,[52]
which served as the witness direct testimony.
On the basis of said affidavit, Engr. Dumaliang was cross-examined by
NHAs counsel.[53]
FUCC adopted and marked Annexes A to GGGGGG of its
Complaint as Exhibits A to GGGGGG and submitted the same as part of its
documentary evidence. FUCC likewise
marked the documents attached to the Affidavit in Question-and-Answer Form of
Engr. Dumaliang as Exhibits HHHHHH to RRRRRR and likewise
submitted the same as part of its documentary evidence.[54]
FUCC thereafter rested its case.
To prove its defenses and counter-claim, NHA likewise
presented only one witness in the person of Engr. Mariano E. Raner III (Engr.
Raner), the Special Project Director of the FVR Project, and submitted his
Affidavit dated 2 December 2003[55]
in lieu of his direct testimony. Engr.
Raner was cross-examined by FUCCs counsel on the basis of said Affidavit.[56]
NHA marked 21 pieces of documentary evidence and
submitted the same as Exhibits 1 to 21,[57]
and thereafter rested its case.
On 7 January 2004, the CIAC Arbitral Tribunal
promulgated its Decision[58] (CIAC
Decision) containing findings and rulings on substantially all of the issues
presented by the parties, and rendering an award in favor of FUCC, as follows:
AWARD
WHEREFORE, on the basis of
the foregoing findings and rulings, an award is hereby rendered in favor of
Claimant, FIRST UNITED CONSTRUCTORS CORPORATION, and against the Respondent,
NATIONAL HOUSING AUTHORITY ordering the latter to pay the former the total of
the following amounts, less the amount for recoupment of the balance of the
advance payment including the interest viz;
1) Php 7,384,534.22 representing payment for
Billing No. 6;
2) Php 989,325.27 representing interest of No. 1
above;
3) P4,677,680.00
representing payment for cost of materials, equipment, facilities;
4) P415,993.13
representing interest of No. 3 above;
5) P26,297,951.62
representing payment for Price Escalation of PB Nos. 1-5;
6) P1,863,191.86
representing interest of No. 5 above;
7) P14,768,770.22
representing payment for Price Adjustment of PB Nos. 5 & 6;
8) P1,847,512.46
representing interest of No. 7 above;
9)
P65,842,309.72 representing payment for Disengagement
Costs;
10) P7,468,141.43 representing interest of No.
9 above;
11) P131,948,674.56 representing payment of
Idle Equipment;
12) P36,634,736.09 representing interest of No.
11 above.
P300,138,820.59 gross
total award in favor of Claimant
13)P * * * * * * * * representing12%
interest of the gross total award of P300,138,820.59, from the date of
promulgation of this decision, and until it is fully paid.
Note: * * * * * * * *is to be determined upon
execution of judgment.
Award to Respondents counter-claim:
1)
P37,951,201.14 representing the recoupment of the
balance of Advance payment made to the Claimant.
2)
P455,414.41 representing interest of No. 1 above.
P38,406,615.55 balance of recoupment plus interest.
Net Award to
be paid by Respondent to the Claimant;
P300,138,820.59
Gross Award of Claimants Claims
Less P 38,406,615.55 Balance of recoupment plus
interest
P261,732,205.04 Net Award to
be paid by Respondent to Claimant.
Finally, the Respondent is hereby ordered to pay
Claimant, one-half of the cost of arbitration in the amount of P768,219.76,
as its share in the arbitration cost, which was advanced by the Claimant during
the pendency of this case.[59]
On 30 January 2004, NHA appealed the CIAC Decision to the Court of Appeals by filing a Petition for Review Under Rule 43 (With
Prayer for Restraining Order & Injunctive Writ),[60]
which was docketed thereat as CA-G.R. SP No. 81635.[61]
NHAs prayer for a Temporary Restraining Order (TRO)
to prevent the execution of the CIAC Decision was granted by the Court of
Appeals in a Resolution dated 14 April 2004.[62]
Upon the lapse of the TRO, NHA filed an Urgent Motion
for Early Resolution of its application for the issuance of a Writ of
Preliminary Injunction, which was similarly granted by the Court of Appeals in
a Resolution dated 8 July 2004.[63]
The Writ of Preliminary Injunction issued by the appellate court enjoined
respondent and the agency a quo from
executing the disputed decision
during the pendency of [the] petition or until further order of the Court.[64]
On 26 February 2004, or prior to the issuance of the
TRO, the CIAC issued in favor of FUCC a Writ of Execution of the arbitral
award. Accordingly, Mr. Cristobal Florendo, Sheriff IV of the Office of the
Clerk of Court and Ex-Officio Sheriff
of the Regional Trial Court in Quezon City, who was appointed as the
Implementing Sheriff, issued and served Notices of Garnishment on the Land Bank
of the Philippines (Land Bank), the Development Bank of the Philippines (DBP), the
Philippine National Bank (PNB), the Veterans Bank of the Philippines (Veterans
Bank), the Bureau of Treasury, and on the Government Security and Insurance
Service Savings Bank. The Implementing Sheriff later served Orders of Delivery
of Money on the Land Bank, DBP, and the Bureau of Treasury.[65]
Petitioner filed a Motion to Lift Garnishment and for
the Issuance of Writ of Preliminary Mandatory Injunction on the ground that the
service of the Notices of Garnishment violated the Resolution dated 14 April
2004 (directing the issuance of a TRO) and the Resolution dated 8 July 2004
(granting the issuance of a Writ of Preliminary Injunction) to enjoin the
execution of the arbitral award. This
motion was denied by the Court of Appeals in a Resolution dated 13 December
2004.[66]
Petitioner subsequently filed a Very Urgent Motion to
Lift Writ of Garnishment citing essentially the same grounds as the previous
motion.[67]
Instead of merely acting upon the Very Urgent Motion
to Lift Writ of Garnishment, the Court of Appeals resolved the main petition
and promulgated the Decision dated 1 August 2006[68] that
affirmed with modification the CIAC Decision.[69] The appellate court denied petitioners Very
Urgent Motion to Lift Writ of Garnishment permanently[70]
and lifted the Writ of Preliminary Injunction it had earlier issued. The decretal portion of the CA Decision reads,
thus:
WHEREFORE, under the premises, we hereby dispose of this case as follows:
1. The following portions of the arbitral award are hereby AFFIRMED, thus:
WHEREFORE, on the basis of the foregoing findings and rulings, an award is hereby rendered in favor of Claimant, FIRST UNITED CONSTRUCTORS CORPORATION, and against the Respondent, NATIONAL HOUSING AUTHORITY ordering the latter to pay the former the total of the following amounts, less the amount for recoupment of the balance of the advance payment including the interest, viz:
1) P7,384,534.22 representing payment for
Billing No. 6;
2) P989,325.27 representing interest (on)
No. 1 above;
3) P4,667,680.00 representing payment for
cost of materials, equipment, facilities;
4) P415,993.00 representing interest (on)
No. 3 above;
5) P26,297,951.62 representing payment
for Price Escalation of PB Nos. 1-5;
6)
P1,863,191.86 representing
interest (on) No. 5 above;
7) P14,768,770.22 representing payment
for Price Adjustment of PB Nos. 5 & 6;
8)
P1,847,512.46 representing
interest (on) No. 7 above;
9) P131,948,674.56 representing payment
for Idle Equipment; and
10)
P36,634,736.09 representing interest on No. 11 above
xx xx xx
Award to Respondents (herein petitioners) counter-claim:
1) P37,951,201.14
representing the recoupment
of the balance of advance
payment made to the
claimant
2) P455,414.41 representing
interest on No.1
above
________________
P38,406,615.55 balance of recoupment
plus interest
xx xx xx
Finally, the Respondent (herein
petitioner) is hereby ordered to pay to Claimant (herein respondent) one-half of the cost of
arbitration the amount of P768,219.76, as its share in the arbitration
cost, which was advanced by the claimant
during the pendency of this case.
2. Determination of the correct amount to be paid by petitioner as disengagement costs and the interest due thereon is hereby REMANDED to the CIAC.
3. Computation of the total award in favor of respondent and the 12% interest due thereon is also REMANDED to the CIAC, with instruction that said 12% interest be computed from finality of this decision.
4. Computation of the net award which petitioner must pay respondent by deducting the gross total award for petitioner from the gross total award for petitioner [sic] from the gross total award with interest for respondent is also REMANDED to the CIAC.
Accordingly, with the foregoing disposition, the Writ of Preliminary Injunction earlier issued against respondent herein is hereby LIFTED.
On 17 August 2006, the CIAC submitted
its Compliance[71] to the
remand orders of the Court of Appeals, showing the re-computed arbitral award
in favor of FUCC.[72]
On 24 August 2006, NHA filed an
Omnibus Motion dated 22 August 2006[73]
that incorporated its Motion for Reconsideration of the CA Decision dated
1 August 2006 and its Motion to Require the CIAC to Explain and to Hold in
Abeyance the Re-Computation of Award.
FUCC, on the other hand, filed a
Motion to Act on the Compliance submitted by the CIAC, while the Land Bank
filed an Urgent Manifestation/ Motion for Clarification for the appellate court
to determine whether the bank could legally release the frozen funds of NHA.[74]
The Court of Appeals directed the
parties to file their respective comment to the cross-motions and to the
manifestation of Land Bank, and thereafter considered the issues submitted for resolution.[75]
On 31 January 2007, the Court of
Appeals issued a Resolution[76] denying
petitioners Omnibus Motion that included its Motion for Reconsideration of the
CA Decision dated 1 August 2006. The
appellate court did not act on the Compliance submitted by the CIAC and on
petitioners Motion to Require the CIAC to Explain and to Hold in Abeyance the
Re-Computation of Award. With respect to the Urgent Manifestation/Motion for
Clarification of Land Bank, the appellate court directed Land Bank to forthwith
release to respondent the garnished fund of petitioner not exceeding P147,894,629.24
in partial satisfaction of [the] Courts decision dated 1 August 2006.[77] The dispositive portion of the Resolution
reads thus:
WHEREFORE, for lack of merit, petitioners Omnibus Motion is DENIED. Respondents Motion to Act on the Compliance submitted by CIAC Ex Abundante Cautelam and petitioners Urgent Motion for Issuance of Temporary Restraining or Preliminary Injunctive Writ are merely NOTED.
With respect to its Urgent
Manifestation/ Motion for Clarification, the Land Bank of the Philippines is DIRECTED to forthwith release to
respondent the garnished fund of petitioner not exceeding P147,894,629.24
in partial satisfaction of this Courts decision dated August 1, 2006, upon
filing of a good and sufficient bond by respondent in the sum of P150,000,000.00
to answer for the restitution of the former amount and reparation of damages to
petitioner should said decision be reversed, whether totally or partially.[78]
Undaunted, NHA filed the present Petition for Review
on Certiorari under Rule 45 of the Revised Rules of Court. Petitioner prays
that this Court reverse and set aside the CA Decision dated 1 August 2006 and
the Resolution dated 31 January 2007 claiming, in the main, that in
promulgating the questioned Decision and Resolution, the Court of Appeals
allegedly egregiously overlooked, ignored or disregarded many discernible,
indisputable facts or circumstances of weight and significance that would
allegedly have logically altered the result of the case had they been
judiciously considered.[79]
The Issues
According to petitioner, instead of those alleged
indisputable facts or circumstances, the appellate courts findings were
premised merely on manifestly wrong presumptions, surmises, mistaken or
improbable inferences and misapprehension of facts.[80] Specifically, petitioner claims that the
Court of Appeals committed a grave and substantial error of judgment:
I
WHEN IT AFFIRMED THE AWARD FOR PROGRESS BILLING NO. 6 AND
PRICE ESCALATION FOR PROGRESS BILLING NOS. 1 TO 5 DESPITE THE INDISPUTABLE OR
ADMITTED FACT THAT RESPONDENT FUCC DID NOT POST ANY PERFORMANCE BOND, WHICH IS
DECIDEDLY A CONDITION PRECEDENT FOR THE PAYMENT OF THESE CLAIMS.
II
WHEN IT AFFIRMED THE AWARD FOR PROGRESS BILLING NO. 6 IN THE AMOUNT OF P7,384,534.22
DESPITE THE MANIFEST OR CLEAR FACT THAT RESPONDENT FUCCS CLAIM FOR SAID
BILLING WAS ONLY P6,496,926.29.
III
WHEN IT AFFIRMED THE AWARD FOR COST OF MATERIALS, EQUIPMENT AND
FACILITIES IN THE AMOUNT OF P4,677,680.00 AND DISENGAGEMENT COST ON THE
BASIS OF AN OBVIOUSLY ILLOGICAL AND ERRONEOUS INTERPRETATION OF EXHIBIT 19.
IV
WHEN IT AFFIRMED THE AWARD FOR IDLE EQUIPMENT IN THE AMOUNT OF P131,948,674.56
NOTWITHSTANDING THE CLEAR AND PATENT FACT THAT RESPONDENT FUCCS EQUIPMENT
NEVER WENT IDLE.
V
WHEN IT AFFIRMED THE AWARD FOR COST OF MATERIALS, EQUIPMENT AND
FACILITIES, DISENGAGEMENT COST AND IDLE EQUIPMENT DESPITE THE CLEAR OR MANIFEST
FACT THAT THESE CLAIMS WERE NON-ARBITRABLE AT THE TIME THE COMPLAINT WAS FILED
ON 17 JULY 2003.
VI
WHEN IT RULED THAT RESPONDENT FUCC DID NOT CONSENT TO THE
TERMINATION OF THE PROJECT NOTWITHSTANDING THE GLARING FACT THAT RESPONDENT
FUCC DID NOT PROTEST THE TERMINATION AND HAD EVEN STOPPED IMPLEMENTING THE
WORKS ON ITS OWN VOLITION EVEN BEFORE ITS RECEIPT OF THE NOTICE OF TERMINATION.[81]
The
Ruling of the Court
We deny the petition for lack merit.
I. Re: Payment Guarantee Bond
as Condition Precedent for Payment of Progress Billing No. 6 and Price
Escalation for Progress
Petitioner questions the award for Progress Billing No. 6 in the amount of P7,384,534.22
and for Price Escalation for Progress Billings Nos. 1 to 5 in the amount of P26,297,951.62.
In sustaining these items of award granted
by the CIAC to FUCC, the Court of Appeals ratiocinated as follows:
Petitioners
sole objection to the award of P7,384,534.22 as payment for Progress
Billing No. 6 and P26,297,951.62 as payment of price escalation for
Progress Billing Nos. 1-5 is that these claims did not become ripe for
adjudication for failure of respondent to fulfill a condition sine qua non, which is the filing of a
payment guarantee bond. Without this
bond, respondent had no right of action against petitioner at the time of
filing of the complaint in arbitration. x x x
Without question, the filing of a bond is a condition for the payment of the foregoing claims of respondent. We do not accept the reasoning of the CIAC that this requirement was rendered moot and academic by its granting of said claim; that sort of reasoning begs the question. However, we agree with CIAC that respondents omission to file bond was excusable. On October 4, 2002, respondent proposed an arrangement under which it would submit its bond only when petitioner is about to release the check but that petitioner will hold on to it until respondents bond is received and verified. Respondent was prompted to make this request in view of its unfavorable cash flow position, a dire situation it found itself in when the project was pre-terminated. x x x As found by CIAC, petitioner never responded to this request, giving rise to the presumption that it had not denied it. x x x. This presumption holds considering that, even at this stage, petitioner never explained its inaction.
Thus,
we sustain the award of P7,384,534.22 as payment for Progress Billing
No. 6 and P26,297,951.62 as payment of price escalation for Progress
Billing Nos. 1-5. However, consistent
with the provisions of the Contract, we require the latter to post the
requisite bond in the manner arranged by respondent with petitioner.[82]
Petitioner assails what it sees as a
flip-flopping of the Court of Appeals, i.e.
for ruling in one breath that (w)ithout question, the filing of a bond is a
condition for the payment of the foregoing claims of respondent, but
pronouncing in another that we agree with CIAC that respondents omission to
file bond was excusable, only to qualify in the third breath that consistent
with the provisions of the Contract, we require the latter to post the
requisite bond in the manner arranged by respondent with petitioner,[83]
and asserts that the posting of the bond is a government requirement that
cannot be excused under both the law and the Contract (citing Articles VII and
VIII thereof), and is simply indispensable.[84]
In fact, according to petitioner, it is a condition precedent for the payment
of FUCCs claims for Progress Billing No. 6 and for Price Escalation for
Progress Billings Nos. 1 to 5. And since
FUCC allegedly failed to comply with this condition precedent, it had no
existing or accrued cause of action to compel NHA to pay the two (2) claims.[85]
Respondent counters that the Payment
Guarantee Bond was required by NHA at the inception of the Project as a
condition for the release of the advance payment to FUCC in the amount P85.2
Million,[86] and not
as a requirement for the processing or release of FUCCs Progress Billings;[87]
that the Payment Guarantee Bond expired without the entire advance payment being
recouped by NHA because of the many work suspensions and delays suffered by the
FVR Project; and that FUCC tried to renew the bond but the GSIS refused because
the Contract for the FVR Project had already been terminated as of 16 October
2001.[88] It is respondents submission that since its inability
to submit a renewed Payment Guarantee Bond from the GSIS was NHAs very own act
of terminating the Contract, NHA cannot use the same as reason not to process
and pay FUCCs claims for Progress Billing No. 6 and for Price Escalation for
Progress Billing Nos. 1 to 5.[89]
We have meticulously examined the
record vis--vis the submissions of
the parties and find no reason to disturb the ruling of the Court of Appeals.
The record shows that at the start of
the FVR Project, FUCC received from NHA an advance payment for mobilization in
the amount of P85.2 Million, or fifteen percent (15%) of the contract
cost.[90] There is no dispute that this advance payment
was to be recouped by NHA from FUCC by taking partial amounts from the progress
payments to FUCC. There is likewise no dispute that to secure the recoupment of
this advance payment, NHA required FUCC to post a Payment Guarantee Bond in the
amount of P85.2 Million issued by GSIS prior to the release of the
advance payment.[91]
It appears that before NHA could
recoup from FUCC the entire advance payment, the Payment Guarantee Bond
expired. This, at a time when NHA had
yet to recover some P38 Million out of the P85.2 Million advance
payment.[92]
FUCC tried to renew and pay for the
extension of the bond but GSIS refused because the Contract for the FVR Project
had already been terminated as of 16 October 2001.[93]
Because of the inability of FUCC to
submit a renewed Payment Guarantee Bond from GSIS, NHA refused to process and
pay FUCCs claims for Progress Billing No. 6 and for Price Escalation for
Progress Billings Nos. 1 to 5.[94]
In two letters, one dated 23 May 2002,[95]
the other dated 6 June 2002,[96]
both addressed to the NHA General Manager, FUCC appealed for help in the
payment of these claims and proposed to procure an alternative surety bond from
a private surety firm accredited by the Insurance Commission to secure the
balance of the advance payment still to be recouped by NHA.[97]
As both letters drew no response from
NHA, FUCC wrote a third letter dated 13 June 2002[98]
reiterating its proposal to submit a bond from a private surety company instead
of a renewed Payment Guarantee Bond from the GSIS. It wrote thus:
The
unexpected termination of the contract has already caused untold injury to the
contractor. May we request NHA not to
add insult to the injury by allowing the private surety bond and by
subsequently releasing our claim for price escalation.[99]
NHA finally replied[100]
and acceded to FUCCs proposal provided that the private surety company was among
the top five (5) firms as endorsed by the Insurance Commission.[101]
FUCC immediately wrote back[102]
and provided NHA with a list of the top five non-life insurance companies as
endorsed by the Insurance Commission, and sought approval to procure a surety
bond from any one of the firms, but preferably from Malayan Insurance Company,
Inc.[103]
The foregoing evidence of record
indisputably establish that FUCC made the offer to submit a surety bond from a
private surety company instead of a renewed Payment Guarantee Bond issued by
the GSIS just so NHA would process and pay FUCCs claims for Progress Billing
No. 6 and for Price Escalation for Progress Billing Nos. 1 to 5. This offer was contained in three (3)
successive letters: the first dated 23 May 2002,[104]
the second dated 6 June 2002,[105]
and the third dated 13 June 2002.[106]
When NHA acceded to FUCCs proposal
in the letter dated 24 June 2002,[107]
it accepted FUCCs offer but
qualified its acceptance by imposing the condition that the surety firm be
among the top five surety firms as endorsed by the Insurance Commission. This
qualified acceptance constituted a counter-offer[108]
which FUCC immediately accepted by way of the letter dated 3 July 2002.[109] In that letter, FUCC submitted to NHA the
names of the top five surety companies from where it intended to obtain the
surety bond. Thus, a perfected agreement
was reached between the parties, to wit:
that FUCC would submit a surety bond from one of the top five private
surety companies to secure the balance of the advance payment still to be
recouped by NHA, while NHA would process and pay FUCCs claims for Progress
Billing No. 6 and for Price Escalation for Progress Billing Nos. 1 to 5. There was a perfected agreement because the
contractual elements of consent, object certain and cause had concurred.[110]
The evidence on record further show
that the parties subsequently reconciled their computations and agreed on the
amount of P26,297,951.62 as payment for Price Escalation for Progress
Billing Nos. 1 to 5.[111] In fact, in the letter dated 2 October 2002,[112] NHA
advised FUCC that it would proceed with the processing of the escalation
payment subject to the submission [of] the Surety Bond covering the balance for
the recoupment of the advanced payment for mobilization.[113] In
response, FUCC wrote NHA a letter dated 4 October 2002[114]
requesting that it be allowed to submit the surety bond immediately before [the]
release by NHA of the check for the price escalation, with the understanding
that until the bond is released and verified, NHA will hold the check, owing
to the unfavorable cash flow position of the project brought about by the
untimely termination of the contract.[115] Since
NHA did not respond to FUCCs request nor object thereto, respondent assumed
that NHA had tacitly accepted the same,[116]
a stance supported by the CIAC and affirmed by the Court of Appeals in this wise:
As
found by CIAC, petitioner never responded to this request, giving rise to the
presumption that it had not denied it. x x x This presumption holds considering
that, even at this stage, petitioner never explained its inaction.[117]
Indeed, petitioner has not explained
its inaction even in the instant petition.
It merely posits that its silence cannot give rise to the presumption
that it had accepted the counter-proposal of FUCC[118]
(referring to the request contained in the letter of FUCC dated 4 October 2002),[119]
which it claims to be a counter-proposal to the counter-proposal of petitioner
NHA (referring to the letter dated 24 June 2002).[120]
But this stance is untenable. As discussed above, the letter of NHA dated 24
June 2002, containing a qualified acceptance of FUCCs offer to submit a surety
bond from a private surety company, constituted a counter-offer or a
counter-proposal, if you will, which was already accepted by FUCC in the letter
dated 3 July 2002.[121] Thus, when FUCC wrote NHA the letter dated 4 October
2002,[122] there
was no more counter-proposal on the table to speak of. FUCC
wrote that letter in response to the letter of NHA dated 2 October 2002[123]
to make a reasonable request on a mere matter of procedure: that it be allowed
to submit the surety bond only when the check payment for its claim for price
escalation is about to be released, with the understanding that NHA will hold
on to the check until it had received and verified the surety bond.
The intended purpose of the surety
bond is self-evident: to ensure that NHA
would be able to recover the unrecouped balance of the advance payment in the still
substantial sum of P38 Million. Understandably,
NHA wanted the surety bond posted before releasing further payments to
FUCC. Clearly, therefore, for as long
as the surety bond was to be posted and properly verified before any check
payment to FUCC could be released, the bond would have served its purpose. This was precisely the arrangement sought by
FUCC. Thus, NHA had no reason to refuse FUCCs
request contained in the letter dated 4 October 2002,[124]
which is presumably the reason why it remained silent and gave no response,
giving rise to the correct presumption that it had tacitly agreed to FUCCs
request.
Based on the foregoing disquisition,
the Court cannot subscribe to the asseveration of petitioner that FUCC had no existing or accrued cause of action to
compel NHA to pay its claims for payment of Progress Billing No. 6 and for
Price Escalation for Progress Billing Nos. 1 to 5 at the time it filed its
Complaint since FUCC allegedly failed to comply with a condition precedent or sine qua non for the payment of said
claims the posting of the Payment Guarantee (or Performance) Bond.[125]
Cause of action is defined as an act or omission by
which a party violates the right of another. A
complaint is deemed to have stated a cause of action provided it has indicated
the following: (1) the legal right of the plaintiff, (2) the correlative
obligation of the defendant, and (3) the act or the omission of the defendant
in violation of the said legal right.[126]
Respondent had
the right to be paid its claim for Price Escalation for Progress Billing Nos. 1
to 5 after NHA recognized the validity of the claim and reconciled its
computations with FUCC on the correct amount of price escalation to be
paid. In fact, NHA had expressed readiness to process the
payment of the claim. As regards Progress Billing No. 6, petitioner
similarly recognized the validity of this claim. Indeed, petitioner does not contest the right
of private respondent to be paid Progress Billing No. 6. What it contests is merely the amount
thereof, insisting that FUCC is only entitled to an award of P6,496,926.29
as against the amount of P7,384,534.22 awarded by the CIAC.[127]
Petitioners subsequent refusal to
process and pay these claims despite FUCCs willingness to submit a surety bond
to secure the balance of the advance payment still to be recouped by NHA as
the parties had agreed upon which bond would be submitted when the check
payment for the claim is about to be released, clearly constitutes a violation
by NHA of FUCCs right to be paid these acknowledged and recognized claims. Thus,
respondent had an accrued cause of action against petitioner for these claims
at the time it filed its Complaint, the constitutive elements of which are
clearly set forth therein.
There is nothing to support petitioners stance that the posting of the
Payment Guarantee (or Performance) Bond is decidedly a condition precedent or sine qua non for the payment of FUCCs
claims for Progress Billing No. 6 and for Price Escalation for Progress Billing
Nos. 1 to 5.[128] The Court notes, upon a close examination of the Contract,
that there is no provision therein that requires FUCC to post a Payment
Guarantee Bond as an indispensable condition for the recognition of the
validity of its claim for price escalation or for the processing and payment of
its progress billings. Nor does the
Contract refer to any other document from where such a condition may be
inferred.
The source of FUCCs obligation to
post a surety bond as a substitute for the GSIS-issued Payment Guarantee Bond
is not the Contract but the subsequent agreement between the parties, to wit:
that FUCC would submit a surety bond from one of the top five private surety
companies to secure the balance of the advance payment still to be recouped by
NHA, while NHA would process and pay FUCCs claims for Progress Billing No. 6
and for Price Escalation for Progress Billing Nos. 1 to 5. And the timing of the posting of the bond was,
as requested by FUCC in the letter dated 4 October 2002,[129]
tacitly agreed to by NHA: that FUCC would
post the requisite bond only when the check payments for its acknowledged claims are about to be
released, with the understanding that NHA will hold on to the checks until it
had received and verified the surety bond.
Petitioners reference to Article VII
and VIII of the Contract to support its allegation that (t)he procurement or
posting of a Payment Guarantee (or Performance) Bond is a government
requirement that cannot be excused under both law and Contract[130]
is misplaced. Article VII refers
to the Performance Bond in the amount of P28,429,789.00 posted by FUCC to
guarantee the faithful performance of its scope of work,[131]
which is decidedly different from the Payment Guarantee Bond in the amount of P85.2
Million which NHA required FUCC to procure from GSIS and to post prior to the
release of the advance payment in the amount of P85.2 Million. A reading of Article VIII entitled
CONTRACTORS ALL RISKS INSURANCE, on the other hand, readily reveals that it
has no relation at all to the Payment Guarantee Bond required by NHA to cover the
recoupment of the advance payment to FUCC.[132]
It appears that petitioner pounced upon, and took
out of context, the Court of Appeals ruling that (w)ithout question, the
filing of a bond is a condition for the payment of the foregoing claims of
respondent to argue that since FUCC failed to comply with a condition
precedent or sine qua non for the
payment of said claims, FUCC had no cause of action against NHA at the time it
filed the Complaint. Read in the proper
context, the payment spoken of in the CA Decision actually pertains to the
physical act of releasing the check payments of FUCCs claims for Progress
Billing No. 6 and for Price Escalation for Progress Billings Nos. 1 to 5.
The word payment is a noun that is used in two
(2) general senses: as money paid, i.e.
an amount of money that is paid or due to be paid; or as the act of paying, i.e. the act of paying money, or fact of
being paid.[133] In the case at bar, the word payment was
obviously used by the Court of Appeals in the sense of the act of paying, or
more exactly, with respect to the mechanical act of releasing the check
payments for FUCCs claims for Progress Billing No. 6 and for Price Escalation
for Progress Billing Nos. 1 to 5. The
Court of Appeals decreed that NHA may release the payment (meaning, the
checks processed by NHA for FUCCs claims) provided FUCC would post the
requisite bond in the manner arranged by respondent with petitioner. [134]
The evidence on record indubitably show that even
as FUCC was ready to post the requisite bond in the manner agreed upon by the
parties, NHA still refused to process and pay FUCCs claims for Progress
Billing No. 6 and for Price Escalation for Progress Billing Nos. 1 to 5. In
fine, and for emphasis, FUCC had an accrued cause of action to compel NHA to
pay these claims at the time it filed its Complaint.
II. Re: Amount
of FUCCs Claim for Progress Billing No. 6
Petitioner ascribes grave error to the Court of
Appeals for affirming the award made by CIAC for Progress Billing No. 6 in the
amount of P7,384,534.22 when FUCCs claim for said billing was allegedly
only P6,496,926.29.
Anent this alleged error by the appellate court, it
appears that FUCC originally submitted to NHA an Abstract of Physical
Accomplishment in support of Progress Billing No. 6, showing that its physical
accomplishments during the period 1 July 2001 to 21 November 2001, amounted to P6,496,926.29.[135]
However, what FUCC attached to its Complaint[136]
was a different Abstract of Physical Accomplishment showing that its accomplished
works under Progress Billing No. 6 totalled P7,384,534.22.[137]
According to petitioner, (i)f ever [it] is legally
liable to pay respondent FUCC for Progress Billing No. 6, it should pay only
the amount of P6,496,926.29, and not P7,384,534.22,[138]
as the Abstract of Physical Accomplishments marked and offered as Exhibit 15 was submitted by FUCC itself, through its then
authorized representative, Engineer Edgardo S. De la Cruz, who had affixed his
conformity thereon, to support its claim for payments for the said
accomplishments.[139] Petitioner also cites the direct testimony of
its sole witness, Engr. Raner, to the effect that (t)he only Abstract of
Physical Accomplishment for Progress Billing No. 6 that was signed by FUCC and
NHA is Exhibit 15, in which the amount agreed by both parties was P6,496,926.29. According to Engr. Raner, (t)he alleged new
Abstract of Physical Accomplishment for Progress Billing No. 6 could only be a
fabricated document.[140]
The Court notes that a perusal of the Abstract of
Physical Accomplishments offered in evidence by FUCC as Exhibit IIII reveals
that it was also signed by both parties, just like the Abstract of Physical
Accomplishments offered in evidence by NHA as Exhibit 15. In his testimony,
FUCCs sole witness, Engr. Dumaliang, explained that many Abstracts for
Physical Accomplishments were caused to be prepared by NHA with different
reduced amounts reflected thereon, which explains the apparently oscillating
figures for Progress Billing No. 6. Engr. Dumaliang admitted that FUCC might have indeed also
signed Exhibit 15.[141] In short,
FUCC does not disown Exhibit 15. It is FUCCs stance that both Exhibit IIII and Exhibit 15 are
duly executed documents but Exhibit IIII, which it alleges was submitted
later, supersedes Exhibit 15 and contains the correct amount of FUCCs
accomplished works under Progress Billing No. 6.[142]
These conflicting claims between the
parties as to the correct amount that petitioner is legally liable to pay respondent for Progress Billing No. 6 was resolved by the CIAC in favor
of FUCC. The CIAC found that the amount of P7,384,534.22
governs over the claim of NHA in its Exhibit 15 for the amount of P6,496,926.29. According to the CIAC, both Exhibit IIII
and Exhibit 15 were signed by the representatives of FUCC and NHA. However, below the signatures in Exhibit 15
are handwritten notations saying that such document is not final but
conditional. The pertinent portion of
the CIAC Decision reads thus:
The
Arbitral Tribunal finds the abstract of Physical Accomplishment for Progress
Billing No. 6 in Exhibit IIII submitted by FUCC in the amount of P7,384,534.22
governs over the claim of NHA in its Exhibit 15 for the amount of P6,496,926.29
(see Stipulated Facts No. 25.1.2).
The
Arbitral Tribunals finding is based on the signature by a representative of
FUCC in Exhibit IIII together with that of NHA representative (Mr. Borlagdan,
Head Tech. Staff of FVRP), while in Exhibit 15 the signatures of both the NHA
and FUCC representatives had handwritten notations below their respective
signatures, both signifying that such document is not final but
conditional. Exhibit 15 therefore is
not controlling because of the signatures therein with handwritten conditions
signifying further claims. [143]
As
this finding of fact by the CIAC was affirmed by the Court of Appeals, and it
being apparent that the CIAC arrived at said finding after a thorough
consideration of the evidence presented by both parties, the same may no longer be reviewed by this Court. The all too-familiar rule is that the Court will
not, in a petition for review on certiorari,
entertain matters factual in nature, save for the most compelling and cogent
reasons, like when such factual findings were drawn from a vacuum or
arbitrarily reached, or are grounded entirely on speculation or conjectures,
are conflicting or are premised on the supposed evidence and contradicted by
the evidence on record or when the inference made is manifestly mistaken or
absurd.[144] This conclusion is made
more compelling by the fact that the CIAC is a quasi-judicial body whose
jurisdiction is confined to construction disputes.[145] Indeed, settled is the rule that findings of fact of administrative
agencies and quasi-judicial bodies, which have acquired expertise because their
jurisdiction is confined to specific matters, are generally accorded not only
respect, but finality when affirmed by the Court of Appeals.[146]
III.
Re: Award for Cost of Materials, Equipment and
Facilities
Petitioner questions the propriety of the award for Cost of Materials,
Equipment and Facilities in the amount of P4,677,680.00.
This award has two components: (1) an
award in the amount of P132,470.00 representing the cost of materials
delivered by FUCC to the project site but were not utilized due to the
termination of the Contract; and (2) an award in the amount of P4,545,182.82
representing the pro-rated cost of the facilities constructed by FUCC to
support field operations for the FVR Project.[147]
Central to the resolution of the
question raised by petitioner is Exhibit 19,[148]
an NHA Internal Routing Slip dated 17 November 1997 transmitted by the
Manager of the Southern Luzon and Bicol (SLB) Region to the Chairman of NHAs
PBAC, which reads as follows:
INTERNAL ROUTING SLIP
SUBJECT: MINIMUM REQUIRED OWNED
EQUIPMENT AND KEY STAFF
RE: LAND DEVELOPMENT OF
RESETTLEMENT PROJECT (PHASE 1), SITIO
BOSO-BOSO, BGY.
___________________________________________________________________
FOR/TO : FROM : DATE : SIGNATURE
___________________________________________________________________
The Chairman : The Manager : 17
November :
PBAC : SLB : 1997 : NEOFITO A. HERNANDEZ
___________________________________________________________________
Submitted
herewith is a listing of the minimum required owned equipment and key staff for
the Land Development of Freedom Valley Resettlement Project (Phase I) located
at Sitio Boso-Boso, Bgy.
A. EQUIPMENT NO. OF EQUIPMENTS
1. Tractors,crawler-type with dozer 6
2. Loaders, crawler-type 3
3. Grader, motorized 6
4. Road Roller, vibratory, smooth drum 6
5. Plate Compactor, vibratory 3
6. Backhoe, hydraulic, crawler-mounted 6
7. Slipform Concrete Paver 1
8. Wet-mix Concrete Batching Plant 1
9. Concrete Vibrator 6
10. Dump Trucks 8
11. Air compressor, portable 1
12. Pneumatic Breakers, hand held 2
13. Water Pump 3
14. Generator Sets, 500 KVA, total 1
15. Welding Machines 2
16. Water Trucks 3
17. Chain Saw 2
18. Concrete Cutter 1
19. Concrete Mixer, one bagger 1
20. Service Vehicles 4
21. Cranes 4
22. Transit Mixers 4
23. Total Stations 1
_____________
TOTAL 75
B.
KEY
STAFF NO.
OF MANPOWER
1.
Project
Manager 1
2.
Project
Engineers 3
3.
Field
Engineers 10
4.
Sanitary
Engineer 1
5.
Electrical
Engineer 1
6.
Mechanical
Engineer 1
7.
Geodetic
Engineer 1
8.
Architects 2
9.
Draftsmen 2
10.
Foremen 6
11.
Administrative
Officer 1
12.
Finance
Officer 1
13.
Liaison
Officer 1
14.
Purchasing
Officer 1
15.
Warehouseman 1
16.
Clerk
Typist 1
17.
Drivers
4
18.
Heavy
Equipment Operators 25
19.
Utilitymen 2
20.
Heavy
Equipment Mechanics 4
21.
Instrument
Men 3
22.
Survey
Aides 9
_____________
TOTAL 81
According to the Court of Appeals,
this Internal Memo shows that NHA itself determined the minimum equipment and key staff to be mobilized for the
project, and since the project was pre-terminated, respondent is justified in
seeking recovery of a portion of the costs already incurred. Thus:
x x x.
Petitioners own Exh.19 shows that it determined the minimum equipment and
key staff to be mobilized for the project x x x. It is implicit in these requirements that the
infrastructure to house such equipment and personnel (including NHA personnel)
and facilitate their mobilization within the project site were also expected to
be provided by respondent. Hence, when
respondent invested into such infrastructure, it did so with the expectation to
recover such costs at the end of the project.
As the project was pre-terminated, respondent is justified in seeking
recovery of a portion of the costs already incurred.[149]
The
appellate court thus affirmed the award made by the CIAC to FUCC in the amount
of P4,545,182.82 representing the pro-rated cost of the facilities
constructed by FUCC to support its field operations for the FVR Project (i.e.;
the second component under the award for Cost of Materials, Equipment and Facilities, and for
Disengagement Costs). The appellate court also affirmed the award in
the amount of P132,470.00 representing
cost of materials delivered by FUCC to the project site but were not utilized
due to the termination of the Contract
(i.e.; the first component under the award for Cost of Materials, Equipment and Facilities, and for
Disengagement Costs), upon the finding
that NHA was solely to be blamed for the lack of inventory of the unutilized
materials.[150]
Petitioner disputes the holding of the Court of
Appeals and maintains in the instant petition that it is not legally liable to pay FUCC for Cost
of Materials, Equipment and Facilities, and for Disengagement Costs because NHA
could not have dictated upon FUCC what equipment and key staff to mobilize in
the FVR Project, as it was FUCC, logically being the contractor, which
determined the kind and number of equipment that should be deployed for the
Project.[151] According to petitioner, Exhibit 19 was
transmitted by the Manager of the SLB Region to the PBAC Chairman in
preparation for the public bidding of the FVR Project. The SLB Manager listed the minimum required
equipment and key staff that a participating contractor should own (as
contradistinguished from mobilize) to insure that no fly-by-night or puny
contractor would participate in the bidding, as (t)he capability of the
contractor to build the Project is known by the equipment he owns.[152]
In short, it is petitioners
submission that Exhibit 19 was not meant to dictate and could not have
dictated the kind and number of equipment and key staff that FUCC should
mobilize and/or actually mobilized for the FVR Project. It was issued by the Manager of the SLB
Region to the PBAC Chairman merely to serve as a checklist on the minimum
required number of equipment and key staff that a would-be contractor for the
Project should own. Petitioner claims that there is a whale of difference
between owning and mobilizing, and that this difference completely
escaped the Court of Appeals when it scrutinized Exhibit 19.[153] Since NHA had allegedly nothing to do with
the deployment of FUCCs equipment and machineries for the FVR Project, it
should not be made accountable for the dire consequences, if any, of FUCCs
business decision or judgment in procuring, maintaining, constructing or
dismantling these equipment and facilities, etc.[154]
Petitioners arguments fail to
persuade. The Court subscribes to the
view expressed by private respondent that in a government infrastructure
project, the department or agency that owns the project dictates not only what
facilities, equipment and key technical staff the contractor should mobilize,
it dictates as well the financial resources the contractor should muster for
the project, the bonds, guarantees and sureties it should put up, the plans, specifications,
schedule, and the manner by which it should prosecute the contract works, how it
should bill for completed works, how it should document and claim variation
orders, etc.[155]
Indeed, this appears to be so in the
case of the FVR Project. The very
Contract entered into by the parties (which appears to be a standard form
contract with the blank spaces appropriately filled up) specifies the duration
of the contract works and the bonds, guarantees and sureties to be put up by
FUCC,[156] and
expressly states that, among other documents, the following shall form part of
the Contract, to wit: plans,
specifications, certificate of availability of
funds, concurrence of lending institutions, duly approved program of
work and cost estimates, PERT/CPM or equivalent schedule of work, etc.,[157]
all of which demonstrate that NHA, as the owner of the FVR Project, had full control over its
implementation. This would certainly
have included dictating or imposing, as it were, the minimum equipment and key
staff that had to be mobilized by FUCC to undertake the contract works. Otherwise, NHA would have been remiss in its
duty to ensure that the Project would be implemented properly and the peoples
money spent wisely. Indeed, there are rules and guidelines for the implementation
of government contracts[158]
that procuring entities must follow to promote transparency and ensure that all
contracts are performed strictly according to specifications.[159]
Be that as it may, even if Exhibit
19 was indeed issued merely to serve as a checklist on the minimum required
number of equipment and key staff that a would-be contractor for the FVR
Project should own, the document indubitably establishes that FUCC which was
awarded the Contract for the Project could not have but assembled and
mobilized a huge complement of men, materials and equipment to be able to
undertake the FVR Project consisting, at the very least, of the equipment and
key staff listed in said Exhibit 19, which were the minimum required by
NHA. Whether FUCC owned the equipment or
merely rented them does not alter the fact that it had to provide the infrastructure to house such equipment and key
personnel within the project site to support its field operations. FUCC
undoubtedly poured in money to put up such infrastructure, with the expectation that it would be able to recover the costs thereof at
the end of the Project. Thus, when the
FVR Project was terminated due to no fault of FUCC, respondent was eminently
justified in seeking recovery of a portion of the costs already incurred[160]
for such infrastructure, as correctly held by the Court of Appeals.
The Court notes that in ruling as it
did, the Court of Appeals merely affirmed the finding of the CIAC that (w)hen the whole amount of the contract for
facilities is not paid due to the termination of said contract which is caused
not at contractors fault, the Contractor should be paid the pro-rated balance
having prepared the facilities for the whole project.[161] The Court further notes that the amount of this award for the pro-rated cost of the facilities constructed by
FUCC to support its field operations for the FVR Project P4,545,182.82; as well as
the amount of the award for
the cost of the unutilized materials delivered by FUCC to the project site P132,470.00,
were not plucked out of thin of air. They
were meticulously derived by the CIAC based on the evidence submitted to the
Arbitral Tribunal, as is readily apparent from the following pertinent portion
of the CIAC Decision:
The work
item in the contract for facilities had the corresponding amount. When the
whole amount of the contract for facilities is not paid due to the termination
of said contract which is caused not at
contractors fault, the Contractor should be paid the pro-rated balance
having prepared the facilities for the whole project. These are consequences made in good faith and
for usage in the project.
The
construction facilities to support field operations are mandatory and necessary
in the implementation of the project where the contract usually provides in a
form of mobilization at the project start, and those needed during the full
operation stage, e.g. laboratory, etc., and demobilization at the close of the
project.
In the
claim of FUCC, it included the Land Development of Heavy Equipment Yard, Office
and Model Houses, Container Vans, Warehouse, Barracks, Shops, Working Areas,
Water Supply and Electrical Works. This
involves the total amount of P12,297,722.46.
The FUCC
is asking the pro-rated amount of this P12,297,722.46 computed as
follows:
Balance
of Works, divided by the cost of the whole works, multiplied by the cost of
facilities, thus;
P568,595,780.00 less P358,445,341.30
x P12,296,722.46
P568,595,780.00
This will result to P4,545,182.82 which the Arbitral Tribunal
supports as the valid claim of FUCC for component b) of its claim, or for
facilities.
For the two components a) and b) for materials and facilities, NHA
should pay FUCC the total of P132,498.00 plus P4,545,182.82 or
the total of P4,677,680.00 and not P4,801,992.82 as previously
claimed by FUCC.[162]
It must be pointed out that nowhere
in the instant petition does petitioner contest the foregoing formula and the figures
used by the CIAC or the amounts of the awards derived therefrom. Petitioner merely proffers the argument that
NHA had nothing to do with the deployment of equipment and machineries and,
hence, should not be made accountable for the consequences of FUCCs business
judgment or decisions as regards their procurement, mobilization or maintenance. But both the CIAC and the Court of Appeals
have spoken. And the CIACs factual
finding that FUCC ought to be paid the total amount of P4,677,680.00 for
the Cost of Materials, Equipment and Facilities remains uncontested. This factual finding, which was affirmed by the Court of Appeals, must be accorded respect and finality
by this Court, consistent with the settled rule that findings of fact of
administrative agencies and quasi-judicial bodies, which have acquired
expertise because their jurisdiction is confined to specific matters, are
generally accorded not only respect, but finality when affirmed by the Court of
Appeals.[163]
IV.
Re: Award for Idle Equipment
Petitioner asseverates that the award for Idle
Equipment in the amount
of P131,948,674.56 is not legally owing to FUCC and will unjustly
enrich FUCC at the expense of petitioner NHA because no perdition [was]
suffered by respondent FUCC from idle equipment, as there was allegedly no
actual or physical suspension of the contract works that occurred.[164]
Verily, the determination of whether
or not FUCC is entitled to an award for Idle Equipment hinges on a factual
issue: whether or not there was actual or physical suspension of the contract
works at the FVR Project.
The CIAC Arbitral Tribunal found that
there was such actual or physical suspension of the contract works a finding
not disturbed by the Court of Appeals.
This Court could very well just simply say that there is no cause to
review, must less overturn this finding of fact, invoking the established rule
that in petitions for review on certiorari, this Court is limited to
reviewing only errors of law, not of fact, unless the factual findings
complained of are devoid of support by the evidence on record, or the assailed
judgment is based on a misapprehension of facts.[165]
But considering that the award for
Idle Equipment involves a substantial sum P131,948,674.56 and if
only to ascertain that the factual findings of the CIAC are indeed not devoid
of support by the evidence on record, the Court shall examine at length the
nature of this award and the bases of the findings of the CIAC Arbitral
Tribunal and the judgment of the Court of Appeals.
First, it must be emphasized that
FUCCs claim for Idle Equipment is limited to the period from 10 June 1998,
when NHA issued Partial Suspension Order
No. 1, up to 15 March 1999, the original expiration date of the
Contract. This time frame is clearly
defined in FUCCs Complaint.[166] The same time frame is also acknowledged by
the CIAC as the period circumscribed by FUCCs claim for Idle Equipment.[167]
To support its claim for Idle
Equipment, FUCC attached to its Complaint a Summary (marked and offered in
evidence as Exhibit QQQQQ) showing the equipment that were rendered idle and
unproductive during the period 10 June 1998 to 15 March 1999, the duration of
their idleness, their rates per hour, and the cost of idleness per kind of
equipment. The cost of idle equipment added
up to a total of P142,780,800.00.[168]
In its Answer, NHA sought to defeat
FUCCs claim by interposing the defense that there is no basis for the award of
Idle Equipment because there was no actual or physical suspension of the
contract works as shown allegedly by the Abstracts of Physical Accomplishment
for Progress Billings Nos. 1, 2, 3, 4 and 5 of FUCC.[169]
During the presentation of evidence,
FUCCs sole witness, Engr. Ben S. Dumaliang testified that Partial Suspension Order No. 1was never lifted because NHA was not
able to fully address the farmers/planters demands and/or contain their
resistance; and that although Partial
Suspension Order No. 1 mentions only the suspension of works at Cluster 2,
it effectively stopped all contract works in both Clusters 1 and 2, allowing
FUCC to prosecute the FVR Project only in Cluster 3. According to Engr.
Dumaliang, he saw with [his] own two
eyes in [his] thrice a week visits to the project site that there was
practically no contract works going on in Clusters 1 and 2. [170] Thus:
Q
: The parties have stipulated that all
works at Cluster 2 were suspended effective 10 June 1998 due to the continued
resistance of farmers/planters and other residents within the area to the FVR
Project, under Partial Suspension Order No. 1.
When was this suspension lifted?
A
: It was never lifted because the NHA
was never able to fully address the demands and/or contain the resistance of
the farmers/planters and other residents within the area.
Q
: What contract works were affected by
this suspension?
A
: Although Partial Suspension Order
No. 1 only mentions the suspension of works at Cluster 2, it effectively
stopped all contract works in both Clusters 1 and 2, allowing FUCC to prosecute
the FVR Project only in Cluster 3.
Q
: According to the NHA, even with the
issuance of Partial Suspension Order No. 1, there was no actual or physical
suspension of the contract works, particularly in Clusters 2 and 3.
What can you say about this?
A
: That is not true. There was actual
suspension of contract works in Clusters 1 and 2. I know this of my own personal knowledge being
the Project Director of FUCC for the FVR Project. As I said earlier, FUCC was
able to prosecute the project only in Cluster 3. I saw with my own two eyes in my thrice a
week visits to the project site that there was no [sic] practically no contract
works going on in Clusters 1 and 2.
Q
: But FUCC collected from and was paid
the amount of P52.2 M for works done during the period supposedly
covered by Partial Suspension Order No. 1.
According to the NHA, this shows that there was no actual or physical
suspension of the works. What can you
say about this claim?
A :
This P52.2 M was payment made by NHA to FUCC under Progress Billing No.
1 for works actually accomplished during the period 16 March up to 30 June
1998. Partial Suspension Order No. 1 became
effective only on 10 June 1998. By that
time, FUCC had been working for almost three (3) months and had accomplished a
lot. Hence, the fact that it was paid P52.2M under Progress Billing No.
1 does not prove that there was no actual or physical suspension of the
contract works because of Partial Suspension Order No. 1.[171]
NHAs sole witness, Engr. Mariano E.
Raner III, on the other hand, testified that Partial Suspension Order No. 1 was lifted on 13 June 1999.[172]
Engr. Raner reiterated NHAs stance that there was no actual or physical
suspension of the contract works as shown by the Abstracts of Physical
Accomplishment submitted by FUCC in support of its Progress Billings Nos. 1, 2,
3 and 4.[173]
The CIAC Arbitral Tribunal found for
FUCC and in the Decision dated 7 January 2004 rendered an award for Idle
Equipment in the amount of P131,948,674.56.
The CIAC
Arbitral Tribunal debunked NHAs proposition that the Abstracts of Physical
Accomplishments and the payments made to FUCC under the Progress Billings show
that there was no actual or physical suspension of the contract works by
pointing out: (1) that the work
accomplishments under Progress Billing No. 1 were done during the first three
(3) months of the Contract (i.e. from 16 March 1998 up to June 1998) or before
the issuance of Partial Suspension Order
No. 1 on 10 June 1998; (2) that the work items covered by Progress Billing
No. 2 were mostly for slope protection, which were also partially done before
the issuance of Partial Suspension Order
No. 1; and (3) that the accomplishments under Progress Billing No. 3 also
consisted of slope protection and other items of work that did not involve the
use of the equipment that went idle. The
CIAC Arbitral Tribunal also gave credence to the testimony of Engr. Dumaliang
that he saw with his own eyes that there was no equipment activity for the
period 10 June 1998 to 15 March 1999.[174] The pertinent portions of the CIAC Decision
dated 7 January 2004 are reproduced hereunder as follows:
NHA on the other hand contested the claim for payment of Idle Equipment with the principal reason that there was no actual or physical suspension of the contract works during the Partial Suspension Order No.1, which was proven by the payments of Progress Billings Nos. 1, 2, 3, 4, and 5, showing the items of works done in the Abstract of Accomplishment, supporting the said Billings. x x x
In the Affidavit of the NHAs lone witness, Mr. Raner III, it stated that the alleged 25 February 1999 meeting was a blatant lie, because there was never a meeting on such date, more so that there was no agreement to pay the Idle Equipment claims. This allegations of the lone witness for NHA had been addressed and countered in the various letters that were never denied by the various officials of NHA who received the letters without any question, x x x except by the lone witness who only call it a blatant lie during the pendency of this case.
Upon perusal of the records in this case, it showed that in Admitted Fact No. 21, the period[s] for each billings [sic], are as follows;
Billing No. 1 16 March 1998 to 30 June 1998
Billing No. 2 01 July 1998 to 31 December 1998
Billing No. 3 01 January 1999 to 15 October 1999
Billing No. 4 16 October 1999 to 31 January 2001
Billing No. 5 31 January 2001 to 31 June 2001
Gleaned from this
data, only
It was alleged by NHAs lone witness, that there were works in Billings [sic] Nos. 1 to 5 described in the Abstract of Accomplishments attached therein, showing activities during the Partial Suspension period of 10 June 1998 to 15 March 1999.
This allegation of NHA was countered by the lone witness of FUCC that the Billing No. 1 were [sic] accomplishments for the first three years of the contract, done long before the issuance of Partial Suspension order No. 1. And that Billing No. 2 were [sic] composed of work items for slope protections, also partially done before the issuance of Partial Suspension No. 1. For Billing No. 3, the accomplishments, as records will bear, are mostly slope protections and other work items not involving the use of equipments.
Further, the lone witness for the FUCC testified categorically that he had visited the project thrice a week for the whole contract duration, and saw from [sic] his own eyes that there was no equipment activity for the period 10 June 1998 to 15 March 1999.
The above facts
had been addressed in sufficient details regarding the issue as to whether
there was actual or physical suspension of works for the period covered by the
Partial Work Suspension Order No. 1. To
discuss activities within the other Suspension Orders is immaterial to the
issue.[175]
After ruling that there was actual or
physical suspension of contract works in the FVR Project that left idle the
large complement of hardware, machinery, tools and equipment mobilized by FUCC,
the CIAC Arbitral Tribunal then proceeded to derive the value of the award for
Idle Equipment in this wise:
It is noted that the period from 10 June 1998 when Suspension Order No. 1 was in effect, to 15 March 1999 when the original contract expired, is 278 days that FUCC claimed for payment of the Idle Equipment.
In the
claim of payment for Idle Equipment for the 278 day period, FUCC listed
12-Bulldozers, 6-Backhoes, 2-Payloaders, 3-Graders, 3-Roadrollers, 4-Dump
Trucks, 1-Water Truck, 1-Conc. Batching Plant, and 3-Transit Mixers, all
working at the average of 2.224 hours per day for 278 days. The respective modified ACEL rates in Exhibit
TTTTT was [sic] applied for the corresponding equipment, such that the total
claims amounted to P142,780,800.00 (Exhibit QQQQQ).[176]
x x x
Perusal of the records in this case showed that the listed equipment and number of units in the claim for payment of Idle Equipment, are far below the Minimum Required Owned Equipment x x x, as listed during the bidding, except that of the Bulldozers. Instead of only six (6) bulldozers required, the claim for payment of Idle Equipment had twelve (12) bulldozers (see Exhibit 19).
The Arbitral Tribunal concluded that the claim for payment of Idle Equipment by FUCC is meritorious, except the 12 bulldozers which should be reduced to 6 bulldozers in the computations of the payment. This is because the increase of bulldozers from 6 to 12 is a business discretion of FUCC, decided at the start of the project, which does not bind the Owner, especially that it resulted to non-use for almost one year.
The corresponding amount for the excess six bulldozers to be
deducted is equal to 6 bulldozers multiplied by 298 days and by the rental rate
of P2920.00 per hour, further multiplied by 2.224 hours per day will
result to P10,832,125.44. This
should be deducted from the claimed total of P142,780,800.00 and will
result to P131,948,674.56.[177]
It cannot be gainsaid that the CIAC
Arbitral Tribunal sifted through the evidence presented by both parties before
making the finding of fact that there was actual or physical suspension of the
contract works that rendered the huge complement of FUCCs machineries and
equipment idle and unproductive during the period 10 June 1998 up to 15 March
1999. Further, the CIAC Arbitral
Tribunal painstakingly scrutinized the documents submitted by FUCC to support
its claim for Idle Equipment before arriving at the amount of P131,948,674.56 as its award for Idle
Equipment, which is less than FUCCs claim of P142,780,800.00. Clearly,
the factual findings of the CIAC are based on substantial evidence on record,
which are referred to in the CIAC Decision.
For example, the CIAC refers to the testimony of
FUCCs sole witness, Engr. Dumaliang, to support its finding that the physical
accomplishments subject of Progress Billing No. 1 were actually done during the
first 3 months of the works contract (from March to June 1998), or before the
issuance of Partial Suspension Order No. 1 on 10 June 1998,[178] which testimony is unrebutted.
Reference is also made to the
following testimony of Engr. Dumaliang, which is similarly unrebutted, pertaining
to the physical accomplishments under Progress Billing Nos. 2 and 3, which
belies the stance of NHA that there was no actual or physical suspension of the
contract works, to wit:
Q: Again, the NHA claims that even with the issuance of Suspension
Order No. 1 due to the CDO issued by the DENR, no actual or physical suspension
of works was implemented. In fact, according to the NHA, FUCC collected and was
paid P16.1 M under Progress Billing No. 2 for the period 01 July to 31
December 1998 and P57 M under Progress Billing No. 3 for the period 01
January to 15 October 1999, or during the supposed period of the suspension
order. What is your reaction to this?
A : For a period of almost one year, or from 31 July 1998 up to 15
June 1999, all of the contract works were actually and physically suspended
because of Suspension Order No. 1.
However, FUCC was allowed to do mitigating slope protection and drainage
works in Cluster 3. The amount of P16.1
M paid to FUCC under Progress Billing No. 2 was payment for: (1) works
accomplished before the suspension which were not paid under Progress Billing
No. 1; and (2) for slope protection and drainage works which were allowed by
the CDO issued by the DENR. Upon the other hand, the amount of P57 M
paid to FUCC under Progress Billing No. 3 was payment for: (1) slope excavation
and drainage works done before the suspension but which were not paid because
the covering variation order (Variation Order No.1) had not yet been issued
then; and (2) for slope protection works, consisting of gabions and riprap,
which were necessary to prevent further damage to the project while the
suspension was in effect. Verily, these payments do not prove that there was no
actual or physical suspension of the contract works because of Suspension Order
No. 1. [179]
It thus comes as no surprise that the
Court of Appeals affirmed the award of the CIAC for Idle Equipment in its Decision
dated 1 August 2006,[180]
where the appellate court additionally pointed out that petitioner had in fact
acknowledged its liability to FUCC for standby cost. Thus:
Petitioner
further disclaims liability for the amount of P131,948,674.56 awarded to
respondent as payment for idle equipment.
It argues that there is nothing in the contract or in PD 1594 and its
implementing rules which allows such award.
We are inclined, however, to agree with respondent that petitioner had acknowledged its liability for standby cost. Its officer-in-charge Engr. Raner wrote in his 8 June 1999 Memorandum regarding the fact-finding being conducted by the Office of Ombudsman, thus:
There is another
compelling reason for the expeditious resumption of the works. The contractor is claiming compensation for
the large fleet of equipment, plant and facilities rendered idle and
unproductive due to suspension. The contractor has billed us some P142 M
for the period June 1998 to March 1999.
This claim is of course subject to evaluation of its merits, but under the General Conditions of the contract, the contractor may be entitled to such compensation. x x x
Engr.
Raner affirmed the foregoing statement when he testified on 9 December 2003.[181] x x x
The Court notes that Engr. Raner did
affirm the recommendation contained in his Compliance Report to the Ombudsman[182]
when he testified on cross-examination during the hearing before the CIAC
Arbitral Tribunal held on 9 December 2003. Thus:
ATTY. ALMADRO:
You recall, Mr. Witness, that the Ombudsman fact-finding report focused on the fact that there was a delay in the project and that the Ombudsman wanted it immediately [resumed] because the FVR Project was a funded project of the government and the Ombudsman felt that every day of delay was causing so much cost to the government and reflecting a poor administration of a project and in your report, one of your recommendations was, in fact, to make sure that works would actually resume immediately, is that correct?
ENGR. RANER III:
Yes.
ATTY. ALMADRO:
In
fact, in Item 1 again of this report, there is a paragraph here and I would
like to quote for the record, there is another compelling reason for the
expeditious resumption of the works. The
contractor is claiming compensation for the large fleet of equipment, plant and
facilities rendered idle unproductive due to suspension. The contractor has billed us P142 M
for the period June 1998 to March 1999.
This claim is of course subject to evaluation of its merits, but under
the general conditions of the contract, the contractor may be entitled to such
compensation. So you were well aware that there was a claim amounting to P142
Million as of June 1999 in connection with the idle equipment of the
contractor?
ENGR. RANER III:
The claim that was expressed, we were informed at that time verbally.
ATTY. ALMADRO:
So you became aware at that time that is why it is your sentiments
ENGR. RANER III:
Yes.
ATTY. ALMADRO:
And you stated here that the contractor may be entitled to such compensation, at that time you felt there was a basis for this claim.
ENGR. RANER III:
Yes. At that time, I felt there was a need to
address the claim but as far as my level of position in the project is
concerned, my authority is but to recommend.
If there will be recommendations that Ill be submitting, of course,
that will be subject to evaluation by management.[183]
Citing the case of Public
Estates Authority vs. Elpidio Uy, et al.,[184]
where this Court affirmed the disputed arbitral award of CIAC (a portion of which
was for payment of the standby or idle time of equipment), the Court of Appeals
sustained the award for Idle Equipment and held that payment for standby time
due to prolonged work suspension is legally tenable.
This Court cannot but agree with the holding
of the Court of Appeals. More so because
the CIAC which carefully considered the conflicting claims of the parties and
painstakingly scrutinized both the oral and documentary evidence of record
possesses the required expertise in the field of construction arbitration, as
we had pointed out in the cited case of Elpidio Uy. In that case, as in this case, we find no
ground to disturb the arbitral award of the CIAC. Settled is the rule that findings of fact of administrative
agencies and quasi-judicial bodies, which have acquired expertise because their
jurisdiction is confined to specific matters, are generally accorded not only
respect, but finality when affirmed by the Court of Appeals.[185] Whatever questions there may be regarding the legality
of an award for standby time or Idle Equipment is put to rest by the case of Elpidio
Uy.
In the instant petition, NHA
reiterates and insists that FUCC does not deserve an award for Idle Equipment
because FUCC was actually and continuously performing contract works on the
FVR Project from 16 March 1999 to 21 November 2001; that its equipment never
went idle; and that it was paid for its contract works during this period.[186]
As heretofore shown, this stance of
NHA was found to be untenable by the CIAC Arbitral Tribunal whose factual
findings were affirmed by the Court of Appeals.
Further, the argument that FUCC continuously performed contract works on
the FVR Project from 16 March 1998 to 21 November 2001 so that its equipment
never went idle is flawed because FUCCs claim for Idle Equipment is
circumscribed within the period from 10 June 1998 to 15 March 1999 only. Quite obviously, works performed before 16 March
1998 and after 15 March 1999 are of no moment and are totally irrelevant to
FUCCs claim for Idle Equipment.
Petitioner dwells at
length on the Batching Plant of FUCC to show that FUCCs machineries and
equipment never went idle.[187] But this is woefully misplaced because, and
this bears repeating: FUCCs claim for Idle Equipment is only for the period 10
June 1998, when the contract works were first suspended by Partial Suspension Order No. 1, up to 15 March 1999, the original
expiry date of the Contract, and not from 16 March 1998 to 21 November 2001, as
petitioner adamantly insists in the present petition. Therefore, and as
correctly pointed out by respondent, even if FUCC had in fact used its
machinery and equipment after 15 March 1999 for other endeavors, it would not
in any way affect the validity of FUCCs claim for Idle Equipment.
V. Re: Whether
or Not Claims for Cost of Materials, Equipment and Facilities, Disengagement
Costs and Idle Equipment are Arbitrable by the CIAC
________________________
TOTAL
P65,842,309.72[188]
________________________
TOTAL P66,794,521.62
The
record shows that after the CIAC submitted its Compliance on 17 August 2006, NHA filed an Omnibus Motion dated 22
August 2006[208] that
incorporated its Motion for Reconsideration of the Decision dated 1 August
2006, and its Motion to Require the CIAC to Explain and to Hold in Abeyance the
Re-Computation of Award.
The Court examined the record and notes that
petitioner had not, either in its petition with the Court of Appeals, or in the
Omnibus Motion, or in the instant petition, assailed the correctness of the
amounts of the award for the three components of the Disengagement Costs
derived by CIAC. As the CIAC itself
emphasized, NHA never disputed FUCCs claim for Foregone Equipment Rental and
the amount of award thus reached by the CIAC.
What petitioner questioned before the
Court of Appeals in its Omnibus Motion was merely the legal basis of the
award for Disengagement Costs, reiterating the argument that NHA could not have
dictated what equipment and key staff to mobilize for the FVR Project, as it
was FUCC alone which determined the kind and number of equipment to be deployed
for the Project.[209]
But the Omnibus Motion was denied by the Court of Appeals in the Resolution
dated 31 January 2007.[210]
This Court, therefore, finds no cogent reason to
disturb the total amount of the award for Disengagement Costs derived and
re-computed by the CIAC, as summarized and shown above.
The Court is aware that in the Resolution dated 31 January
2007, the Court of Appeals did not act upon the Compliance submitted by the
CIAC on 17 August 2006
as it was made by only two arbitrators.
According to the Court of Appeals, it cannot be considered an award of
the Arbitral Tribunal, citing Section 16.2 of the Revised Rules of Procedure
Governing Construction Arbitration (the Revised CIAC Rules), in relation to
Section 10.4 thereof.[211]
We do not
agree with the Court of Appeals in this regard.
The Compliance is not an award, let alone the Final award spoken of in
Section 16.2 of the Revised CIAC Rules.
The CIAC Arbitral Tribunal already rendered a Final award in the
Decision dated 7 January 2004. The
Compliance merely clarifies and presents a re-computation of some items of the
Final award. It does not alter or supersede the Final award nor purport to
be a new award. Further, Section 10.4 of
the Revised CIAC Rules states that in case any Arbitrator should resign, etc.,
the CIAC may, within five days from the occurrence of a vacancy x x x,
appoint a substitute(s) to be chosen. The use of the permissive may, rather than
the mandatory shall indicates that the appointment of a third member of the
CIAC Arbitral Tribunal is not indispensable for the tribunal to discharge its
functions. The records show that a vacancy in the Arbitral Tribunal occurred
with the demise of Lauro M. Cruz. Nothing in the Revised CIAC Rules prevents the
remaining two members who constitute a majority from complying with the
remand orders of the Court of Appeals. The Court thus gives imprimatur and deems as approved the
Compliance submitted by the CIAC. We find that it sufficiently complies with
the remand orders contained in the CA Decision dated 1 August 2006 and presents
a correct method of computation of the arbitral award.
In the present petition, the sole
issue presented by petitioner against the award
for Disengagement Costs is that Disengagement Costs, like the Cost of
Materials, Equipment and Facilities, and Idle Equipment are business losses
which were non-arbitrable under the CIAC
Rules of Procedure Governing Construction Arbitration, which was in place
at the time FUCC filed its Complaint on 17 July 2003. According to petitioner, the Court of Appeals
gravely erred when it sustained the CIAC (which ruled that there is no basis to
exclude claims for business losses), and held in the Decision dated 1 August
2006 as follows:
We agree with CIAC. In fact, we need not indulge in
hair-splitting anymore. In Gammon
Philippines, Inc. versus Metro Rail Transit (G.R. No. 144792, January 31,
2006), the Supreme Court held that there is no basis for the exclusion of
claims for business losses from the jurisdiction of CIAC. It explained:
Relevantly, while the above-quoted provision of the Rules of Procedure
Governing Construction Arbitration lists as non-arbitrable issues claims for
opportunity/business losses and attorneys fees, this provision was not carried
over to the Revised Rules of Procedure Governing Construction Arbitration which
was approved on November 19, 2005. Such
omission is not without good reason. EO 1008 itself excludes from the coverage
of the law only those disputes arising from employer-employee relationships
which are covered by the Labor Code, conveying an intention to encompass a
broad range of arbitrable issues within the jurisdiction of CIAC. (Emphasis
added)
Moreover, as pointed
out by respondent, the second paragraph of Sec. 2 allows claims for unrealized
expected profits and those arising from the rescission or termination of a
contract. x x x (pp. 1576-1577, Rollo) Certainly, the claims sought to be
satisfied in this case arose from the early termination of the Contract which
deprived respondent of the prospect to make profit out of the investment it had
already poured into the venture. It
makes sense that respondent should be allowed to recover what opportunity it
may have lost, especially when it was not to blame for the aborted contract.[212]
We need not
belabor this issue any further. As the appellate court correctly
points out, we have already categorically ruled in Gammon Philippines, Inc. vs.
Metro Rail Transit,[213]
that there is no basis for the exclusion of claims for business losses from the
jurisdiction of CIAC because Executive Order No. 1008 (EO 1008), the law that
created the CIAC, excludes from the coverage of the law only those disputes
arising from employer-employee relationships which are covered by the Labor Code,
conveying an intention to encompass a broad range of arbitrable issues within
the jurisdiction of CIAC.
The
nature and bases of the awards for Disengagement
Costs consisting of three components, namely: Foregone Equipment Rental,
Extended Overhead Costs and Foregone Income; and the awards for Cost of
Materials, Equipment and Facilities, and Idle Equipment have been discussed at
length. They are either business or
opportunity losses or foregone profits that resulted from, or are the necessary
consequences of, the termination of the Contract. They arose from and are inextricably linked
to the construction dispute between NHA and FUCC that was the subject of
arbitration proceedings before the CIAC.
We find and so hold that they are arbitrable claims within the ambit of
Section 4 of EO 1008, which defines the jurisdiction of the CIAC. Thus:
SECTION 4. Jurisdiction.The CIAC shall have original and exclusive jurisdiction over disputes arising from, or connected with, contracts entered into by parties involved in construction in the Philippines, whether the disputes arises [sic] before or after the completion of the contract, or after the abandonment or breach thereof. These disputes may involve government or private contracts. For the Board to acquire jurisdiction, the parties to a dispute must agree to submit the same to voluntary arbitration.
The jurisdiction of the CIAC may include but is not limited to violation of specifications for materials and workmanship; violation of the terms of agreement; interpretation and/or application of contractual provisions; amount of damages and penalties; commencement time and delays; maintenance and defects; payment default of employer or contractor and changes in contract cost.
Excluded
from the coverage of this law are disputes arising from employer-employee
relationships which shall continue to be covered by the Labor Code of the
Section 4 provides that (t)he
jurisdiction of the CIAC may include but is not limited to x
x x, underscoring the expansive
character of the CIACs jurisdiction.
Very clearly, the CIAC has jurisdiction over a broad range of issues and
claims arising from construction disputes, including but not limited to claims
for unrealized profits and opportunity or business losses. What EO 1008 emphatically excludes is only
disputes arising from employer-employee relationships.
Section 2, Article IV of the previous CIAC Rules of Procedure Governing
Construction Arbitration cited by petitioner, which purports to exclude
claims for business losses,[214]
contravenes EO 1008 and is a patent nullity; it is void ab initio. In legal
contemplation, that section of the previous CIAC Rules never acquired force and
effect and cannot be applied to this case.
What applies is Section 2.1 of the Revised
Rules of Procedures Governing Construction Arbitration that was promulgated
on 19 November 2005. Indeed, and as pointed out by the Court of Appeals in the
Resolution dated 31 January 2007, CIAC Resolution No. 02-2006 (Defining the
Coverage of the Revised Rules of Procedure Governing Construction Arbitration)
states that the Revised Rules shall be applicable to all pending cases upon
its effectivity on 15 December 2005 and all cases which are to be filed
thereafter.[215] This case was filed on 17 July 2003 and was
pending as of 15 December 2005.
But even granting for the moment that
Section 2, Article IV of the previous CIAC Rules is a valid provision that may
be applied to the case at bar, still the CIAC was eminently correct in ruling
that under the first paragraph of Section 2, Article IV, only
opportunity/business losses in addition to liquidated damages are not
arbitrable. When the opportunity/
business losses are sought independently of liquidated damages, as in the
instant case, they are perforce arbitrable.[216] This ruling of the CIAC was upheld by the
Court of Appeals in the Decision dated 1 August 2006. The Court sees no reason
to hold otherwise.
VI.
Re: Whether or Not the Termination of Contract for
FVR Project was Unilateral
Was the termination of the Contract
for the FVR Project a unilateral act of NHA?
Without
doubt, said the Court of Appeals, thusly:
This brings us to the next assigned error. Petitioner insists that it should not be made to bear all the consequence of the termination of the project for respondent consented to it. It gave its tacit consent by not protesting the termination. x x x Moreover, even if it were true that the termination was unilateral on the part of petitioner, the latter is excused from any liability because the termination was due to reasons beyond its control. x x x.
Such argument is futile. Respondent could not have consented, tacitly or otherwise, to the termination of the project because that decision was made entirely by petitioners board of directors. Its September 25, 2001 Resolution No. 4450, reclassifying the project into a mixed-market site and services project, is clear evidence that respondent had no participation whatsoever in the formulation of the decision. Without doubt, the termination of the project was unilateral.
It was also due to factors well within the control of
petitioner. While geological or
geophysical conditions in the project site rendered work difficult, the Mines
and Geosciences Bureau (MGB) investigated landslides in the area merely for
revision of the design plan of the project.
x x x Petitioner, however, did
not act on this recommendation despite repeated requests by respondent.[217]
We find no cogent reason to disturb
this finding of the Court of Appeals.
The evidence on record plainly reveals that the decision to terminate
the Contract and to redraft the FVR Project as a mixed-use development under a
joint venture scheme with interested parties was made by NHAs Board of
Directors alone. There is no showing and petitioner does not allege that FUCCs
consent was sought by the Board of Directors directly or indirectly, through
responsible officers of NHA, before Resolution No. 4450[218]
was passed. Neither is there any showing
and petitioner does not allege that NHA made formal representations with
FUCC to negotiate the termination of the Contract for the FVR Project.
What the records reveal, according to
the CIAC, is that (i)n a letter dated 16 October 2001, a Memorandum by the OIC
of the FVR Project, recommended for the termination of the Contract. The approval of this Memorandum was
recommended by Neofito A. Hernandez, NHA Manager for Southern Luzon/Bicol, and
was approved by Edgardo D. Pamintuan, NHA General Manager (Exhibit 1). The following day, 17 October 2001, the NHA
General Manager advised FUCC of the termination of the Contract, citing among
others that FUCC should x x x immediately stop the ongoing works and avoid
further expenses including the provision of vehicles and other services for the
NHA Project Team.[219]
The foregoing findings of the CIAC
support the stance of respondent that NHA unilaterally terminated the Contract;
that FUCC was presented with a fait accompli, and there was nothing more
that it could do to stop the unilateral termination of the Contract.[220]
Moreover, as aptly held by the Court
of Appeals, the termination was due to factors well within the control of
petitioner.[221] Hence, NHA cannot invoke Clause 3.04.06 of
the General Conditions of the Contract, which provides that (t)he Authority
may terminate the Contract upon (10) days written notice to the Contractor, if
it is found that reasons beyond the control of either the Authority or
Contractor make it impossible or against the Authoritys interest to complete
the work.[222]
Petitioner argues in the instant
petition that (t)he geological or geographical make up of the Project site is
one reason that made it physically difficult if not impossible to pursue
the FVR Project, and that (i)t was precisely for this reason that the Project
was re-classified from a resettlement to a mixed-used [sic] project.[223]
But as correctly observed by respondent,
NHA, as Project owner, was supposed to
have known the geological or geographical make-up and the potential
hazards of the project site, and should
have taken these into account in the original development plan for the FVR
Project. It appears that NHA failed to
conduct a complete feasibility study and comprehensive technical evaluation of
the FVR Project before embarking thereon. Thus, it had to suspend the project
and revise the development plans in the middle of the contract works to avert a
tragedy, in light of the findings of the MGB, and eventually had to abandon the
project.[224]
Further, while petitioner now claims
that the geological or geographical make up of the Project site made it
physically difficult if not impossible to pursue the FVR Project, which reason
is allegedly beyond its control, this reason was never articulated in the
letter dated 17 October 2001. In that
letter, the NHA General Manager simply advised FUCC of the termination of the
Contract and directed that FUCC should immediately stop the ongoing works and
avoid further expenses.
It would appear to the Court that this
pretended reason was belatedly and purposely foisted to place the termination
within the ambit of the cited Clause 3.04.06.
But not only is the reason unavailing, it is utterly misplaced because
the letter dated 17 October 2001 does not comply with the 10 day written notice
to the contractor required by the very Clause 3.04.06 that petitioner
invokes. This letter-notice of NHA
imposes an immediate termination with its stern admonition that FUCC should immediately
stop the ongoing works and avoid further expenses including the provision of vehicles
and other services for the NHA Project Team.
In Home Development Mutual Fund vs. Court of Appeals, G.R. No. 118972, 3 April
1998, the Court held that requirements
of contracts as to notice as to the time of giving, form,
and manner of service thereof must be strictly observed because in an
obligation where a period is designated, it is presumed to have been
established for the benefit of both the contracting parties. Thus:
The law mandates that Obligations arising from contracts have the force of law between the contracting parties and should be complied with in good faith.
Did petitioners comply with their contractual obligation in good faith, when they served the requisite written notice to private respondents nine (9) days after the expiration of the Agreement? The answer to this crucial question is in the negative.
The second clause of the contractual provision in dispute is to the effect that written notice of termination should be served at least thirty (30) days in advance. As a rule, the method of terminating a contract is primarily determined by the stipulation of the parties. Thus, the requirements of contracts as to notice - as to the time of giving, form, and manner of service thereof - must be strictly observed because in an obligation where a period is designated, it is presumed to have been established for the benefit of both the contracting parties. Thus, the unilateral termination of the contract in question by the herein petitioners is violative of the principle of mutuality of contracts ordained in Art. 1308 of the New Civil Code. (Emphasis supplied)
Indeed, even if NHA is permitted to invoke
Clause 3.04.06 of the General Conditions of the Contract, its own failure to
comply with the notice requirement thereof being violative of the principle
of mutuality of contracts resulted in the unilateral termination of the
Contract.
In any case, and quite importantly, NHA
failed to present evidence to buttress its stance that the termination of the
Contract was due to factors beyond its control as to justify the application of
Clause 3.04.06. On the contrary, the fact that the NHA Board resolved to redraft
the FVR Project as a mixed-use development under a joint venture scheme with
interested parties shows that NHA had other options at hand and could have
chosen to negotiate with FUCC to amend the Contract instead of deciding to
terminate the same. The conclusion is
ineluctable: the termination of the Contract was well within the control of
NHA, as correctly held by the Court of Appeals.
Petitioner
posits that the letter of FUCC to NHA dated 27 August 2001[225]
reveals that FUCC explicitly, if not expressly, welcomed or accepted the
termination of the FVR Project with alacrity.[226]
The letter reads thus:
May we formally inform you that we have refrained from implementing the works under our FVR contract pursuant to your instructions that our contract will be terminated and that project costs should now be contained.
We were advised that NHA has found FVR to be unsuitable for squatter settlement owing to its unfavorable geology and terrain. It is therefore being redrafted for mixed-use development on a joint venture scheme.
This was conveyed to us by the Office of the General Manager and the same was confirmed by the SLB Manager and the FVR Officer-in-Charge.
Indeed,
several prospective parties have inspected the site for a possible joint
venture engagement with National Housing Authority.[227]
The Court does not agree. We believe that the letter cannot be read in isolation
but should be understood in relation to the situation of the parties and
juxtaposed against the contemporaneous events then affecting the FVR
Project. The records show that at the
time the letter was sent, FUCC had pending claims against NHA. It had a pending claim for payment of Idle
Equipment in the amount of P142,780,800.00,[228]
and a pending claim for payment of Price Adjustment in the amount of P15
Million.[229]
According to respondent, NHA wanted
FUCC to resume the contract works for the FVR Project full blast but FUCC
refused citing as reason NHAs failure to settle its pending claims,
particularly its claim for Price Adjustment.
During this time, talk was rife that NHA would terminate the contract
and redraft the FVR Project as a mixed-use development under a joint venture
with interested parties. In late August
2001, FUCC was verbally instructed to refrain from implementing the contract
works as the termination of the Contract was imminent. It was at this point that FUCC wrote the
letter dated 27 August 2001 advising NHA that it had refrained from
implementing the contract works pursuant to your instructions that our
contract will be terminated and that project costs should now be contained.[230]
Respondent explains that it wrote the
letter to put on record an added justification for its earlier refusal to
resume the contract works full blast. Since there was already a verbal
instruction to refrain from implementing the contract works as the termination
of the Contract was purportedly imminent, it simply did not make sense for FUCC
to be spending more for the FVR Project which would only end up as an added
claim against NHA, with no clear prospects of being immediately paid.[231]
Viewed in this light, i.e.: that FUCC
indeed had pending claims with NHA for the payment of substantial amounts that
had remained unpaid despite repeated follow-ups, FUCCs immediately stopping
the contract works even before its receipt of the Notice of Termination [232]
as petitioner puts it does not show tacit consent on the part of FUCC to the
termination of the Contract.
VII.
Re: Errors in Computation
In its Comment, respondent pointed out that errors
were committed by the CIAC when it complied with the remand orders of the Court
of Appeals in the Decision dated 1 August 2006.
One such error, as earlier noted, is the amount of the award for
Foregone Income. Instead of the correct
amount of P21,718,554.48,
what appears in the Compliance is the wrong figure of P25,300,493.46.
This
error appears to be purely typographical.
Respondent identified another error: an error of omission relating to the
computation of interest on the other items of award granted to FUCC. The Compliance shows that the CIAC Arbitral
Tribunal correctly re-computed the 6% interest on Foregone Equipment Rental
using as reckoning dates: (1) 9 January 2002, the date of demand by FUCC
against NHA for the claim, as the beginning date; and (2) 1 August 2006, or the
day of the promulgation of the Decision of the Court of Appeals, as the final
date, as this was the day the final arbitral award in favour of FUCC became
executory.[233]
But the CIAC Arbitral Tribunal inadvertently
omitted to re-compute the 6% interest on each of the other awards using the
same final date of 1 August 2006. We
refer specifically to: (1) the 6% interest on the award for Progress Billing No. 6; (2) the 6% interest on the award for Cost of Materials, Equipment,
Facilities, etc.; (3) the 6%
interest on the award for
Price Escalation; 4) the 6%
interest on the award for
Price Adjustment; and (5) the 6% interest
on the award for Idle
Equipment.
As reflected in the CIAC Decision
dated 7 January 2004, the 6% interest on each of these awards was reckoned by
the CIAC from the date of demand up to 1 December 2003 only.[234] In light of the CA Decision dated 1 August 2006, the CIAC should have re-computed the 6% interest on each of these awards
from the date of demand up to 1 August 2006.
In short, the CIAC inadvertently omitted to account for the 6% interest
accruing from an additional period of 973 days (i.e.; there are 973 days from 1
December 2003 up to 1 August 2006) for each of these awards.
The Court takes judicial notice that Mathematics is
an exact science.[235]
As the aforesaid error of omission is
susceptible of correction using a straightforward mathematical formula already
laid down by the CIAC in its Decision,[236]
which formula has never been questioned by petitioner, and considering further
that petitioner has not interposed any objection to the proposition of
respondent that the oversight committed by the CIAC in the Compliance ought to
be corrected, the Court shall no longer remand this case to the CIAC for
re-computation but shall proceed to re-compute the same. Needless to state, such a remand would not
serve any useful purpose but will only delay the final disposition of this
case.
Based on the mathematical formula already laid down
by the CIAC:
(1)
the 6%
interest on the award for
Progress Billing No. 6 is re-computed as follows:[237]
815 + 973 x P7,384,534.22 x
.06 = P2,170,446.11
365
(2)
the 6%
interest on the award for
Cost of Materials, Equipment, Facilities, etc. is re-computed as follows:[238]
541+ 973 x P4,677,680.00
x .06 = P1,164,165.62
365
(3)
the 6%
interest on the award for
Price Escalation is re-computed as follows:[239]
431+ 973 x P26,297,951.62
x .06 = P6,069,423.14
365
(4)
the 6%
interest on the award for
Price Adjustment is re-computed as follows:[240]
761 + 973 x P14,768,770.22
x .06 = P4,209,706.45
365
(5)
the 6%
interest on the award for
Idle Equipment is re-computed as follows[241]:
1689 + 973 x P131,948,674.56
x .06 = P57,739,293.97
365
WHEREFORE, the petition is DENIED for lack of
merit. The Decision of the Court of
Appeals dated 1 August 2006, which upheld with modification the Decision of the
Construction Industry Arbitration Commission in CIAC Case No. 14-2003, and the
Resolution dated 31 January 2007, as modified with the pronouncement that the
Compliance submitted by the CIAC on 17 August 2006 is deemed approved, are AFFIRMED.
The final arbitral award in favour of FUCC as re-computed and corrected in
accordance with the remand orders of the Court of Appeals, to summarized
hereunder, to wit:
(1)
Award for Progress Billing No. 6, P7,384,534.22;
(2)
6% Interest on Award for Progress Billing No. 6, P2,170,446.11;
(3)
Award
for Cost of Materials, Equipment, Facilities, etc. P4,677,680.00;
(4)
6%
Interest on Award for Cost of Materials, Equipment, Facilities, etc., P1,164,165.62;
(5)
Award for Price Escalation, P26,297,951.62;
(6)
6% Interest on Award for Price Escalation, P6,069,423.14;
(7)
Award for Price Adjustment, P14,768,770.22;
(8)
6 % Interest on Award for Price Adjustment, P4,209,706.45;
(9)
Award for Idle Equipment, P131,948,674.56;
(10)
6%
Interest on Award for Idle Equipment, P57,739,293.97;
(11)
Award
for Disengagement Costs, P70,376,467.60;[242]
(12)
6%
Interest on Award for
Foregone Equipment Rental, P19,238,797.99[243]
With costs against petitioner.
SO ORDERED. JOSE
Associate
Justice |
|
WE CONCUR: ANTONIO T.
CARPIO Associate Justice Chairperson |
|
ARTURO D. BRION Associate Justice |
DIOSDADO M. PERALTA Associate Justice |
LUCAS P. BERSAMIN Associate Justice |
ATTESTATION
I attest that the conclusions in the above
Decision were reached in consultation before the case was assigned to the
writer of the opinion of the Courts Division.
ANTONIO
T. CARPIO
Associate Justice
Chairperson, Second Division
C E R T I F I C A T I O N
Pursuant to Section 13, Article VIII
of the Constitution and the Division Chairpersons Attestation, I certify that
the conclusions in the above Decision had been reached in consultation before
the case was assigned to the writer of the opinion of the Courts Division.
RENATO
C. CORONA
Chief Justice
* Associate Justice Diosdado M. Peralta is designated Additional Member as per Special Order No. 1074 dated 6 September 2011.
** Associate Justice Lucas P. Bersamin is designated Additional Member as per Special Order No. 1066-A dated 23 August 2011.
[1] Penned by Associate Justice
Godardo A. Jacinto with Associate Justices Edgardo P. Cruz and Jose Catral
Mendoza (now a member of this Court), concurring; rollo, pp. 85-109.
[2] Penned by Associate Justice Edgardo P. Cruz with Associate Justices Jose C. Mendoza (now a member of this Court) and Myrna Dimaranan Vidal, concurring; Annex B of Petition; id. at 110-116.
[3]
4
[5]
[6]
[7]
[8]
[9] Annex Q of Petition, id. at
428-510.
[10] Annex S of Petition, id. at
518-686.
[11] Annex C of Petition, id. at
117-142.
[12] Annex E of Petition, id. at
149-152.
[13] Annex F of Petition, id. at 153.
[14] Annex C of Petition, id. at 118.
[15]
[16]
[17]
FUCC P
568,595,780.00
New
P
569,234,466.00
Atlantic
Erectors/ Consuelo/ Linear P
612,933,834.26
R-II Builders P
619,934,334.00
FF
Cruz & Co. P
699,888,000.00
[18] Annex C of Petition, id. at 119.
[19] Annex G of Petition, id. at
157-159.
[20] Annex F of Petition, id. at
153-156.
[21] Article III of Contract, id at 154.
[22] Annex C of Petition, id. at 120.
[23] The CIAC record shows that NHA issued Partial Suspension Order No. 1 dated 23 June 1998 (Cf. Expanding Envelope no. 1, 2nd folder of 4 Annex K of Complaint); Suspension Order No. 1 dated 31 July 1998 (Cf. Annex O of Complaint); and Suspension Order No. 2 dated 13 October 1999 (Cf. Annex V of Complaint).
Partial Suspension Order No. 1 was issued due to the continued resistance of farmers/planters and other residents in the area of the FVR Project (See also Item No. 12.1.1 of Joint Stipulations, rollo, Vol. I, pp. 122-123).
Suspension Order No. 1 came after the DENR issued a cease and desist order effective until an Environmental Compliance Certificate for the Project could be secured by NHA (See also Items Nos. 12.2.1 and 12.2.2 of Joint Stipulations, rollo, Vol. I, p. 123).
Suspension Order No. 2 was issued to stop the works and development of Cluster 3 until revisions of the plans could be made to avoid the occurrence of an incident similar to the Cherry Hills landslide, in light of the report submitted by the Geohazard Assessment Team of the Mines and Geosciences Bureau (MGB) after heavy rains triggered landslides at Cluster 3 (See also Items Nos. 12.3.1, 12.3.2 and 12.3.3 of Joint Stipulations, rollo, Vol. I, pp. 124 and 126).
[24] Rollo,
Vol. I, issued on 15 September 1999; Annex I of Petition, pp. 163-171.
[25] Issued on 4 December 2000; Annex
I-1 of Petition, id. at 172-176.
[26] Annex I-1 of Petition, id. at 174.
[27] Annex H of Petition, id. at 160.
[28] Annex H-1 of Petition, id. at 161.
[29] Annex H-2 of Petition, id. at 162.
[30] Annex H-2 of Petition, id. at 162.
[31] Annex K of Petition, id. at 180.
[32] Annex K-1 of Petition, id. at 197.
[33] Annex K-2 of Petition, id. at 213.
[34] Annex K-3 of Petition, id. at 233.
[35] Annex K-4 of Petition, id. at 244.
[36] Records, Annex ZZZ of Complaint, 3rd
folder of four, Expanding Envelope No. 1, Resolution No. 4450.
[37] Rollo.
See Letter of NHA dated 17 October 2001, Annex L of Petition, p. 256.
[38]
[39] Id.
Clause 3.04.06 of the General Conditions covering Termination of Contract by
the Authority (Contractor not at fault) provides: The Authority may terminate the Contract
upon ten (10) days written notice to the Contractor, if it is found that
reasons beyond the control of either the Authority or Contractor make it
impossible or against the Authoritys interest to complete the work.
[40] See paragraph 1.2 of FUCCs Complaint, id. at 433.
[41] Records, 1st Expanding
Envelope, Folder no. 2, Article
XVII provides thus: Should there be any dispute or controversy in connection
with this Contract or difference between the parties arising from the
interpretation of this Contract, the Parties hereto shall, as far as
practicable, settle the same amicably.
In the event that such dispute or disagreement be not resolved to their
mutual satisfaction, the matter shall be submitted to the Construction Industry
Arbitration Commission (CIAC) created by Executive Order No. 1008, implementing
Presidential Decree No. 1746 and R.A. 876, as amended, however (sic), that the
arbitration proceedings shall be without prejudice to the right of the
AUTHORITY to rescind, or terminate this Contract in accordance with provisions
of the following paragraph.
[42] Rollo,
pp. 428-509.
[43] See Prayer, Complaint in Arbitration, id. at 507-509.
[44] Annex R of Petition, id. at 512-516.
[45] CA rollo, Vol. II, pp 729-730.
Records, Expanding Envelope no. 3, Folder no. 1.
[46] Rollo,
pp. 556-561.
[47] Annex D of Petition, id. at 143.
[48] Annex
E of Petition, id. at 149-152.
[49] Annex C of Petition, id. at
117-142.
[50] See p. 1 of Supplemental Terms of
reference, id. at 149.
[51] Pages
2 to 3 of Terms of Reference and p. 1 of Supplemental Terms of Reference, id.
at 144-145 and 149.
[52] Annex U of Petition, id. at
692-805.
[53] See p. 19 of Petition, id. at 34.
[54]
[55] Annex V of Petition, id. at 806-819.
[56] See p. 20 of Petition, id. at 35.
[57] Annexes
W to W-20 of Petition, id. at 820-943.
[58]
[59] See pp. 36 to 37 of CIAC Decision
dated 7 January 2004, id. at 978-979.
[60] Annex Y of Petition, id. at
980-1024.
[61] See p. 22 of Petition, id. at 37.
[62] CA rollo, Vol II, pp. 1355-1366.
[63] Rollo,
Annex Z of Petition,
pp. 1026-1033.
[64]
[65] See pp. 8 to 9 of CA Decision, id. at 92-93.
[66] CA rollo, Vol. IV, pp.
2449-2452.
[67] Rollo,
p. 94.
[68]
[69]
[70] See p. 10 of CA Decision, id. at 94.
[71] Annex BB of Petition, id. at
1034-1041.
[72] Page 25 of Petition and p. 85 of Comment, id. at 40 and1279.
[73] Annex CC of Petition, id. at
1056-1087.
[74] See p. 26 of Petition, id. at 41.
[75]
[76]
[77] See p. 6 of CA Resolution, id. at 116.
[78]
[79] See p. 27 of Petition, id. at 42.
[80] See
pp. 27-28 of Petition, id. at 42-43.
[81] See pp. 28-29 of Petition, id. at 43-44.
[82] Pages 14-15 of CA Decision, id. at 98-99.
[83] See pp. 29-30 of Petition, id. at 44-45.
[84] See p. 32 of Petition, id. at 47.
[85] See p. 30 of Petition, id. at 45.
[86] See Paragraph 16.1 of Comment, id. at 1208.
[87] See Paragraph 16.3 of Comment, id. at 1209-1210.
[88] See Paragraph 16.2 of Comment, id. at 1209.
[89] See Paragraph 16.3 of Comment, id.
at 1209-1210.
[90] See Paragraph 16.1 of Comment; and p. 34 of Petition, id. at 49 and
1208.
[91] In Paragraph 16.1 of its Comment,
respondent alleges as follows: The bond spoken of in the questioned Decision of
the Court of Appeals is the Payment
Guarantee Bond which the NHA required FUCC to post at the inception of the
FVR Project to secure the liquidation or recoupment of the advance payment for
mobilization in the amount of P85.2 Million (equivalent to 15 % of the
contract cost) that FUCC received from the NHA.
The bond was a condition for the release of the advance payment to
FUCC. As agreed upon between the
parties, the advance payment was to be recouped by taking partial amounts from
the progress payments to FUCC. But
nowhere in the contract documents does it state that the Payment Guarantee Bond
is a requirement for the processing or release of FUCCs Progress Billings, id.
at 1208.
The
following allegation appears in page 33-34 of NHAs Petition; id. at 48-49: x
x x As earlier stated, the procurement or posting of a Payment Guarantee (or
Performance) Bond is both a legal and contractual requirement that cannot be
excused nor waived, least of all by an entity like petitioner NHA performing a vital governmental
mandate or function and publicly accountable for every single cent spent in its
operations. Such bond, to put it curtly,
is a safety net mechanism to ensure recovery of NHAs P38 Million claim
for recoupment, which represents the remaining portion of the P85.2
Million (equivalent to 15% of the contract cost) advance payment for
mobilization that it still had to recover from or apply to the project billings
(See Par. 54 of Affidavit dated 2 December 2003 of Engr. Mariano E. Raner III,
id. at 816.
[92] See page 34 of Petition, id. at 49.
[93] See Paragraph 16.2 of Comment, id. at 1209.
[94] See Paragraph 16.3 of Comment, id. at 1209-1210.
[95] Annex 1 of Comment; (Note: The
existence and/or due execution and authenticity of this letter is admitted by
the NHA [Cf. Paragraph 31 of the
Joint Stipulations] and NHAs receipt thereof was duly established by the
testimony of Engr. Dumaliang), id. at
1287.
[96] Annex 2 of Comment; (Note: The
existence and/or due execution and
authenticity of this letter is likewise admitted by the NHA [Cf. Paragraph 31 of the Joint
Stipulations] and NHAs receipt thereof was duly established by the testimony
of Engr. Dumaliang), id. at 1288.
[97] See Paragraphs 16.4 and 16.5 of Comment, id. at
1210-1211.
[98]
Annex
3 of Comment; (Note: The existence and/or due execution and authenticity of
this letter is also admitted by the NHA [Cf.
Paragraph 31 of the Joint Stipulations] and NHAs receipt thereof was duly
established by the testimony of Engr. Dumaliang), id. at 1289.
[99] See Paragraph 16.6 of Comment, id. at 1211-1212.
[100] See Letter of NHA GM dated 24 June 2002, Annex M of Petition, id. at
257.
[101] See Paragraph 16.6 of Comment, id. at 1211-1212.
[102] See FUCCs letter to NHA dated 03
July 2002, Annex 4 of Comment; (Note: The existence and/or due execution and
authenticity of this letter and NHAs receipt thereof was duly established by
the testimony of Engr. Dumaliang), id. at 1290.
[103] See Paragraph 16.6 of Comment, id. at 1211-1212.
[104]
[105]
[106]
[107]
[108] See
Art. 1319 of the Civil Code, which provides as follows: Consent is manifested
by the meeting of the offer and the acceptance upon the thing and the cause
which are to constitute the contract. The offer must be certain and the
acceptance absolute. A qualified acceptance constitutes a counter-offer.
[109] Rollo,
p. 1290.
[110] Pursuant
to Article 1318 of the Civil Code which provides thus:
Art. 1318 There is no contract unless
the following requisites concur:
(1) Consent of the contracting parties;
(2) Object certain which is the subject matter of the
contract;
(3) Cause of the obligation which is established.
[111] Rollo. See Letter of FUCC to NHA dated 25 September 2002, Annex 6 of Comment,
and letter of NHA to FUCC dated 2
October 2002, Annex 7 of Comment, confirming that the computations for FUCCs
claim for Price Escalation had already been completed and resulted to the gross
amount of P26,297,951.62. See also Paragraph 19 of Comment,
pp. 1292-1293 and 1222-1223.
[112] Annex N of Petition, id. at 258.
[113]
[114] Annex DD of Petition, id. at 1178.
[115] See Paragraph 21 of Comment, id. at 1223.
[116] See p. 94 of the Affidavit in Question-and-Answer
Form of Engr. Ben
[117] See
p. 14 of the CA Decision, id. at 98.
[119]
[120]
[121]
[122]
[123]
[124]
[125] See
p. 30 of Petition, id. at 45.
[126] Philrock, Inc. v. Construction Industry Arbitration Commission, 412 Phil. 236, 247 (2001).
[127] Rollo. See p. 36 of Petition, p. 51.
[128] See p. 30 of Petition, id. at 45.
[129]
[130] See p. 32 of Petition, id. at 47.
[131] See Article VII of Contract, id. at
154.
[132] See Article VIII of Contract, id. at
155.
[133] Microsoft Encarta Dictionary, 2006
Edition.
[134] Rollo, vol. I, Annex A of Petition, CA Decision, pp. 98-99.
[135] Exhibit
15 of NHA attached as Annex W-14 of Petition, id. at 917-925.
[136] As Annex IIII of the Complaint.
Annex IIII was later marked and offered as Exhibit IIII for FUCC,
id. at 1294-1303.
[137]
[138] See p. 36 of Petition, id. at 51.
[139]
[140] See p. 11 of Affidavit of Engr. Mariano E. Raner III dated 2 December
2003, id. at 816.
[141] See pp. 82 to 83 of the Affidavit in Question-and-Answer Form of Engr.
Ben
[142] See p. 38 of Comment, id. at 1232.
[143] See
p. 18 of CIAC Decision dated 7 January 2004, id. at 962.
[144] R-II
Builders, Inc. v. Construction Industry Arbitration Commission, 511 Phil.
523, 534 (2005) citing Sunshine Finance and Investment Corp. v. IAC,
G.R. Nos. 74070-71, 28 October 1991, 203 SCRA 210 and Go v. Court of Appeals and Moldex Products, G.R. No. 158922, 28 May
2004, 430 SCRA 358.
[145] See Section 4 of E.O. No. 1008, dated 4 February 1985.
[146] Public Estates Authority v. Elpidio
Uy, 423 Phil. 407,
416 (2001) citing Cagayan Robina Sugar
Milling Co v. Court of Appeals, 396
Phil. 830, 840 (2000).
[147] Rollo, Vol. I.
See p. 15 of CA Decision, p. 99.
[148] Annex W-18 of Petition, id. at 940-941.
[149] See p. 16 of CA Decision dated 1
August 2006, id. at 100.
[150]
[151] See p. 40 of Petition, id. at 55.
[152] See p. 39 of Petition, id. at 54.
[153] See p. 39 to 40 of Petition, id. at 54-55.
[154] See p. 41 of Petition, id. at 56.
[155] See pp. 43 to 44 of Comment, id. at 1237-1238.
[156] Refer to Articles VII, VIII and IX of the Contract, id. at 154-155.
[157] Refer to Article XI of the Contract, id. at 155.
[158] See Section 42 of Republic Act No. 9184, otherwise known as the
Government Procurement Reform Act, and the Implementing Rules and Regulations
promulgated pursuant to Section 75 of said Republic Act No. 9184.
[159] See Section 3 (a) and (e) of the Implementing Rules and Regulations of
RA 9184.
[160] See p. 16 of CA Decision dated 1 August 2006, Annex A of Petition, rollo, Vol. I, p. 100.
[161] Rollo. See p. 21 of CIAC Decision dated 7 January 2004, p. 965.
[162]
[163] Public Estates Authority v. Elpidio
Uy, Supra
note 146.
[164] Rollo. See p. 41 of Petition, p. 56.
[165] Calang v. People, G.R. 190696, 3 August 2010, 626
SCRA 679, 682-683.
[166] Rollo,
pp. 498-499 and 501. See Paragraph 4.35 of Complaint, which contains
the following allegation: As heretofore shown, the FVR Project was subjected
to work suspensions and suffered various delays all traceable to the faults
and/or acts or omissions of the NHA, to the gross negligence, plain
incompetence or simple lack of concern of its officials, and to the abject
refusal of its technical team to cooperate with FUCC on the field. Because of
these work suspensions and delays, a large part of FUCCs huge assembly of
plant, equipment, tools, materials and manpower were rendered idle and
unproductive since 10 June 1998. FUCC
incurred a huge cost for its idle equipment which, as of 15 March 1999 the
original expiry date of the contract amounted to P142,780,800.00 x x
x.
See also Paragraph 4.40 that alleges
as follows: In the meantime, the original contract period for the FVR Project
expired on 15 March 1999. On 12 April
1999, FUCC wrote the NHA a letter and appended thereto a summary of the cost of
its idle equipment from 10 June 1998, when Partial Suspension Order No. 1 was
issued, suspending all works at Cluster 2, up to 15 March 1999, the expiry date
of the original contract period. The
total cost of idle equipment as of 15 March 1999 amounted to P142,780,800.00.
x x x.
[167] Records. See p. 28 of CIAC Decision dated 7 January 2004, Folder no. 2, Expanding
Envelope no. 3, where the following appears: The claims of FUCC for payment of
idle equipment pertains to the equipments rendered idle due to the Partial
Suspension Order No. 1, effective 10 June 1998 and until the original contract
time expiration on 15 March 1999. x x x The total claim by FUCC for payment of
Idle Equipment was P142,780,800.00.
[168] Rollo. See Paragraph 4.35 of Complaint, pp. 498-499.
[169] See
Paragraph 96 of Answer, id. at 550.
[170]
[171] See p. 4 of Affidavit in Question-and-Answer
Form of Engr. Ben S. Dumaliang dated 4 November 2003, id. at 696.
[172] See paragraph 16, p. 3 of Affidavit of Engr. Mariano E. Raner III dated
2 December 2003, id. at 808.
[173] See paragraph 59, p. 12 of Affidavit of Engr. Mariano E. Raner III dated
2 December 2003, id. at 817.
[174] Records. See pp. 29 to 30 of CIAC Decision dated 7 January 2004, Expanding
Envelope no. 3, Folder no. 2.
[175]
[176] See p. 28 of CIAC Decision, dated 7
January 2004, Expanding
Envelope No. 3, Folder no. 2, id.
[177] Rollo. See p. 30 of CIAC Decision dated 7 January 2004, p. 972.
[178] See p. 4 of Affidavit in
Question-and-Answer Form of Engr. Ben S. Dumaliang dated 4 November 2003, id. at 696.
[179] See p. 6 of Affidavit in
Question-and-Answer Form of Engr. Ben S. Dumaliang dated 4 November 2003, id.
at 698.
[180]
[181] See pp. 16 to 17 of CA Decision dated 1 August 2006, id. at 100-101.
[182] See
Exhibit HHHHHH, Annex 9 of Comment, id. at 1304-1308.
[183] See pp. 11 to 12 of TSN of the
hearing held on 9 December 2003 attached as Annex 10 of Comment, id. at
1319-1320.
[184] Supra note 146.
[185]
[186] Rollo.
Annexes K, K-1, K-2, K-3 and K-4 thereof, pp. 56-58; 180; 197; 213;
and 244.
[187] See
pp. 43 to 51 of Petition, id. at 58-66.
[188] See p. 27 of CIAC Decision dated 7 January 2004, id. at 971.
[189] See p. 26 of CIAC Decision dated 7 January 2004, id. at 970.
[190] See pp. 66 to 67 of Comment, id. at 1260-1261.
[191] See p. 26 of CIAC Decision dated 7 January 2004, id. at 970.
[192] See p. 27 of CIAC Decision dated 7
January 2004, id. at 971.
[193] See p. 65 to 66 of Comment, id. at 1259-1260.
[194]
[195] See p. 27 of CIAC Decision dated 7 January 2004, id. at 971.
[196] See p. 66 of Comment, id. at 1260.
[197] See dispositive portion of CA Decision dated 1 August 2006, id. at 107-108.
[198] See p. 19 of CA Decision dated 1 August 2006, id. at 103.
[199]
[200] See p. 5 of Compliance dated 17 August 2006, id. at 1038.
[201] See p. 3 of Compliance dated 17 August 2006, id. at 1036.
[202]
[203] See p. 20 of CA Decision dated 1 August 2006, id. at 104.
[204]
[205] See p. 5 of Compliance dated 17 August 2006, id. at 1038.
[206]
[207]
[208]
[209] See pp. 26 to 27 of Omnibus Motion dated 22 August 2006, id. at
1080-1081.
[210]
[211] See p. 4 of Resolution dated 31
January 2007, id. at 114.
Section 16.2 of the
Revised Rules of Procedure Governing Construction Arbitration provides as
follows:
SECTION 16.2. Form of Award
The Final Award shall be in writing and signed by the Arbitral Tribunal. A dissent from the decision of the majority
or a portion thereof shall be in writing and signed by the dissenting member.
Section 10.4 reads
thus:
SECTION 10.4.
Vacancies If any Arbitrator
should resign, be incapacitated, refuse or be unable, or be disqualified for
any reason to perform the duties of his office, CIAC may, within five (5) days
from the occurrence of a vacancy or refusal/inability to accept appointment,
appoint a substitute(s) to be chosen.
[212] See pp. 12 to 13 of CA Decision dated 1 August 2006, id. at 96-97.
[213] G.R. No. 144792, 31 January 2006, 481 SCRA 209, 224.
[214] Section 2 of the previous CIAC Rules of Procedure Governing Construction
Arbitration provides as follows:
Sec. 2. Non-arbitrable
Issues Pursuant to Section 4 of Executive Order no. 1008, claims for
moral damages, exemplary damages, opportunity / business losses in addition to
liquidated damages and attorneys fees are not abitrable except when the
parties acquiesce or mutually agree to submit the same for arbitration and to
abide by the decision of the arbitrator thereon.
Claims for unrealized expected profits (built-in in
the contract price) and issues on rescission or termination of a contract,
however, are arbitrable.
[215] Rollo.
See p. 2 of Resolution dated 31 January 2007, p. 112.
[216] See p. 20 of CIAC Decision dated 7 January 2004, id. at 964.
[217] CA Decision, pp. 20-21 dated 1 August 2006, id. at 104-105.
[218]
Supra note 28.
[219] Rollo.
See pp. 33 to 34 of CIAC Decision dated 7 January 2004, pp. 975-976.
[220] See Affidavit in Question-and-Answer
Form of Engr. Ben S. Dumaliang dated 4 November 2003, id. at 692-805.
[221] See p. 20 of CA Decision dated 1 August 2006, id. at 104.
[222] See p. 34 of CIAC Decision dated 7 January 2004, id. at 976.
[223] See p. 59 of Petition, id. at 74.
[224] See pp. 83 to 84 of Comment, id. at 1277-1278.
[225] Annex EE of Petition, id. at 1179.
[226] See p. 57 of Petition, id. at 72.
[227]
[228] The record shows that as early as 19
June 1998, FUCC already advised NHA that its bulldozers and other equipment had
been rendered idle because of the suspension of the contract works. On 3 March 1999, FUCC requested a partial
payment by way of compensation for its idle resources. On 12 April 1999, FUCC wrote NHA a letter
with a summary of the cost of its idle equipment in the amount of P142,780,800.00
as of 15 March 1999. On 28 April 1999,
FUCC wrote another letter following up its claim for Idle Equipment. This was followed by the letter dated 3
August 1999, and then another letter dated 28 October 1999 (See pp. 68 to 72 of
Complaint), id. at 499-503.
[229] The record shows that on 13 June
2000, FUCC requested NHA for the adjustment of contract prices which was later
formalized in a letter dated 11 August 2000.
In a Memorandum dated 22 February 2001, Engr. Raner recommended the
approval of the claim but the recommendation was not acted upon. FUCC followed up this claim for Price
Adjustment in the letters dated 17 April 2001, 23 May 2001 and 22 June 2001
(See pp. 45 to 48 of Complaint), id. at 476-479.
[230] See pp. 76 to 77 of Comment, id. at
1270-1271.
[231] See p. 77 of Comment, id. at 1271.
[232] See p. 57 of Petition, id. at 72.
[233]
See p. 6 of Compliance dated 17 August 2006,
id. at 1039.
[234] See pp. 19, 22-23, 25 and 31 of CIAC Decision dated 7 January 2004, id.
at 963; 966-967; 969 and 973.
[235] The Supreme Court held that things of
common knowledge, of which courts take judicial notice of, are matters coming
to the knowledge of men generally in the course of the ordinary experiences of
life, or matters which are generally accepted by mankind as true and are
capable of ready and unquestioned demonstration. [See Expert Travel & Tours, Inc. v. Court of Appeals, 498 Phil.
191, 206 (2005)].
[236] Rollo.
A common formula was used
by the CIAC in computing the interest on the various awards as may be gleaned
from the computation shown on pp. 19, 22-23, 25 and 31 of CIAC Decision dated 7
January 2004, pp. 963; 966-967; 969 and 973.
[237] Compare to the computation on p. 19 of CIAC Decision dated 7 January
2004, id. at 963.
[238] Compare to the computation on p. 22 of CIAC Decision dated 7 January
2004, id. at 966.
[239] Compare to the computation on p. 23 of CIAC Decision dated 7 January
2004, id. at 967.
[240] Compare to the computation on p. 25 of CIAC Decision dated 7 January
2004, id. at 969.
[241] Compare to the computation on p. 31 of CIAC Decision dated 7 January
2004, id. at 973.
[242] Please refer to pp. 5-6 of Compliance dated 17 August 2006, id. at 1038-1039.
[243] Please refer to p. 7 of Compliance dated 17 August 2006, id. at 1040.