Republic of the Philippines
Supreme Court
Manila
THIRD DIVISION
LANDOIL
RESOURCES CORPORATION, Petitioner, -
versus - AL RABIAH
LIGHTING COMPANY,
Respondent. |
G.R. No. 174720 Present: CARPIO, *
J.,
VELASCO, JR., J.,
Chairperson, PERALTA, ABAD, and MENDOZA, JJ. Promulgated: September 7, 2011 |
x
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - -x
D E C I S I O N
PERALTA, J.:
Assailed in the instant petition for review on certiorari filed by petitioner are the
Decision[1]
dated August 14, 2003 and the Resolution[2]
dated August 29, 2006 of the Court of Appeals issued in CA-G.R. CV No. 52003.
The facts, as borne by the records, are as
follows:
Respondent Al Rabiah Lighting Company (Al Rabiah)
is a foreign corporation existing under the laws of Kuwait. Defendant
Construction Consortium, Inc. (CCI) and petitioner Landoil Resources
Corporation (Landoil) are both domestic corporations organized under the
Philippines Laws.
On December 20, 1981, CCI and respondent Al Rabiah
entered into a Sub-Contract Agreement[3]
wherein respondent was assigned to carry out the electrical works of Kuwait Oil
Company's New Industrial Training Centre project in Ahmadi, Kuwait in the total
amount of Three Hundred Forty- Three Thousand Five Hundred Kuwaiti Dinar.
Respondent started carrying out its work as agreed upon. Later, the project
owner had withdrawn the principal contract which led to the termination of
petitioners and CCIs services.[4]
Consequently, respondent's works were stopped before being completed.
On September 12, 1982, petitioner, through its Regional Managing
Director for Operations Robert J. Brown, sent a letter[5] to
respondent through Mr. Said Y. Al Imam, confirming that based on the July
progress billing, petitioner owed respondent the sum of KD 21,930,317 which was
already due and proposed the payment of 12% interest on the overdue account
until payment has been made.
In a letter dated June 4, 1983, petitioner informed respondent that
the Prime Contractor Al Fahd Company had already terminated its contract; that
petitioner agreed to pay respondent 12% interest per year on the unpaid bills
of completed works. The letter was signed by both Robert Brown and Gerald Love.[6]
On June 9, 1983, petitioner acknowledged its indebtedness to
respondent in the amount of KD 91,580.059, plus general overtime pay of KD
8,126 and promised to pay it in installments.[7]
As petitioner failed to pay respondent any part of the amount due, together with the contractual interest of
12%, the latter referred their dispute to the Commercial Kully Court of Kuwait
for arbitration as provided under the Sub-Contract Agreement. The parties were
duly notified of the scheduled sessions of arbitration, but only respondent and
its counsel appeared thereat.[8]
On April 14, 1984, the Arbitrator
rendered its award as follows:
The court decides that Land Oil Resources Company (Construction
Consortium Incorporation) is indebted to [Al] Rabiah Lighting Company by KD
108,368.860 and that it is compelled to pay this sum in settlement of the
account of the contract concluded between them on 20th December,
1981. The said sum includes also the contractual interest until the date of
issue of this Award.[9]
Respondent then filed with the
Regional Trial Court (RTC) of Makati, an action[10]
for Enforcement of Foreign Judgment Plus Damages against defendant CCI and
petitioner. The case was raffled off to
Branch 64 and was docketed as Civil Case No. 11578.
In its Answer,[11]
petitioner admitted the existence of the Sub-Contract Agreement, but claimed to
have no knowledge as to its genuineness and due execution. By way of Special
and Affirmative Defenses, petitioner argued among others that respondent had no
cause of action; respondent's claims had
been paid, set-off or extinguished; the Commercial Kully Court of Kuwait did
not acquire jurisdiction over petitioner;
and the arbitral award was contrary to public policy, hence, illegal.
Petitioner also alleged that since it had not been paid by its principal
contractor the value of the corresponding accomplishments done by respondent,
respondents cause of action had not yet accrued; and that the termination of
the contract by the primary contractor occurred without the fault or negligence
of petitioner and defendant CCI, nor were they responsible for force majeure under the contract.
On the other hand, defendant CCI, in
its Answer,[12]
specifically denied the Sub-Contract Agreement for lack of knowledge, claiming
that it was not a party to the contract and that G.W. Love was not an employee
nor authorized to act for and in behalf of CCI; and that the Commercial Kully
Court of Kuwait did not acquire jurisdiction over it and the arbitral award was
contrary to public policy.
After trial, the RTC rendered its
Decision[13]
dated July 31, 1995, the dispositive portion of which reads:
WHEREFORE, in view of
the foregoing, this Court finds the petition of plaintiff AL RABIAH Company to
be well-taken, and judgment is hereby rendered finding defendants Landoil
Resources Corporation and Construction Consortium solidarily liable to
plaintiff Al Rabiah Lighting Company in the sum indicated in Arbitral Award with
legal interest thereon from July 1984 (Certification of Non-occurrence of
Appeal) until payment is made. Defendants are likewise ordered to pay to
plaintiff the sum of P250,000.00 as attorneys fees and P100,000.00
as exemplary damages.
SO
ORDERED.[14]
In resolving the main issue of whether
the RTC can validly set aside the foreign arbitral award rendered against
petitioner and defendant CCI on the bases of the defenses raised in the
parties respective Answers, the RTC ruled in the negative. The RTC found that
petitioner and CCI were estopped from claiming that they were not parties to
the Sub-Contract Agreement. Petitioner's Answer alleged that it admitted the
existence of the sub-contract agreement, although claimed that it has no
knowledge as to its genuineness and due execution; that such lack of knowledge
was belied or negated by petitioner's own allegations in its Answer
acknowledging indebtedness to respondent. The RTC found that petitioner's
letter dated September 12, 1982 to respondent confirmed that it owed respondent
the sum of KD 21,930,317 and anticipated that payment would be made in early
October 1982, together with the other due accounts. This letter was submitted
as respondent's Exhibit C and the RTC noted that this letter was among the
documents submitted by respondent to the foreign arbitrator in support of its
claim against petitioner and CCI.
The RTC said that while it appeared in
the Sub-Contract Agreement that the
contracting parties were CCI and
respondent, however, in paragraph VIII thereof, petitioner Landoil appeared
together with CCI as the First Party to whom notices shall be sent. The RTC
then concluded that the inclusion of petitioner as first party to whom the
notices shall be sent and the conduct exhibited by petitioner led to the
inevitable conclusion that the two defendants, petitioner and CCI, were the
parties with whom respondent entered into the sub-contract agreement; and that
this conclusion was even strengthened by the fact that as between the two
defendants, petitioner and CCI, there
existed a pooling agreement for undertaking projects abroad pursuant to Presidential
Decree (PD) 929. Since petitioner and CCI were the parties with whom respondent
contracted, they were bound by the terms of the agreement, including the
referral of their dispute to arbitration in accordance with the Rules and
Regulations of the State of Kuwait.
Dissatisfied, petitioner appealed the
RTC Decision to the CA. After the submission of the parties' respective briefs,
the case was submitted for resolution.
On August 14, 2003, the CA issued its
assailed Decision which dismissed the appeal and affirmed the RTC decision.
The CA ruled, among others, that
petitioner was already estopped from claiming that it was not a party to the Sub-Contract
Agreement as the agreement itself mentioned petitioner Landoil as one of the
contracting parties and that petitioner had made representations in the past,
binding itself for the overdue accounts in favor of respondent.
Petitioner's motion for
reconsideration was denied in a Resolution dated August 29, 2006.
Hence, this petition wherein
petitioner raises the following issues:
(a) whether
a Philippine Court, in enforcing a foreign judgment that has become final and
executory, has the jurisdiction to alter, amend or expand such final foreign
judgment;
(b) Whether a foreign judgment may
be enforced against a party other than the party decreed and held liable
therein; and
(c) Whether Estoppel was properly
appreciated in this case.[15]
Petitioner contends that as appearing
in the dispositive portion of the foreign arbitral award, there is only one
defendant adjudged liable to respondent, i.e.,
Land Oil Resources Company (Construction Consortium Incorporation); thus, the
party against whom the Writ of Execution may be directed. Petitioner claims
that it is not the same as Land Oil Resources Company (Construction Consortium
Incorporation) as its Articles of Incorporation does not indicate any such
appellation; that it was not a party to the proceedings before the foreign
arbitrator as it is a different entity. Thus, enforcing an award against a
non-party such as petitioner would be executing on properties owned by a third
person other than the judgment debtor; and that to allow the same would amount
to a deprivation of property without due process of law. Petitioner avers that the RTC and the CA
erred and committed grave abuse of discretion in amending and modifying the
foreign arbitral award so as to include petitioner which is a corporation
different from the entity adjudged liable in the foreign arbitral award.
We are not convinced.
As correctly found by the CA,
petitioners argument that the party adjudged liable under the foreign arbitral
award was a different entity from it was only raised for the first time in
petitioner's motion for reconsideration filed with it; thus, could not be
entertained. We quote with approval what the CA said when it denied
petitioners motion for reconsideration in this wise:
The defendant mainly argues that it was never a party to the
subcontract agreement. We find its argument meritless, because it is now too
late for the defendant to claim that the party adjudged liable under the
foreign arbitral award was a different entity. Moreover, we note that this is
the first time that the defendant raises such defense. It is settled in
jurisprudence that an issue cannot be raised for the first time on appeal. With
more reason should we disallow and disregard the issue if it is initially
raised in a motion for reconsideration of the decision of the appellate
court.
From the outset of the case, the defendant's stance has always been to
deny any participation in the sub-contract agreement between Construction
Consortium Inc. and the plaintiff and, in the alternative, to bewail the
failure of the arbitral award to spell out the factual distinctions between its
liability and that of the Construction Consortium Inc. for they were separate
and distinct entities. Thus, this is the first time that it asserts that it was
not the defendant in the case before the Commercial Kully Court of the State of
Kuwait. The defendant thus asserts the existence of a third corporation against
whom the arbitral award was supposedly rendered, Landoil Resources Company
(Construction Consortium Incorporated). Not only is the Court precluded from
entertaining such first-time issue but we also frown upon the apparent
self-contradiction. We note that the defendant had, in the course of this case,
repeatedly affirmed that it was the same party as the defendant against whom
the foreign judgment had been rendered.
In its Answer to the Complaint, it stated that:
12. The award directs the Landoil to pay and makes Construction
Consortium Incorporated liable. x x x
Likewise,
in its appeal brief, it also acknowledged being the defendant against whom the arbitral award was being
enforced, thuswise:
x x x the foreign judgment subject of the case before the court a quo is an arbitral award rendered by
the Commercial Kully Court of the State of Kuwait on April 14, 1984, compelling
defendant CCI and defendant appellant to pay the sum of KD 108,368.860 in
settlement of the contract allegedly concluded between them and
plaintiff-appellee, which included a 10% contractual interest until the time of
said award.[16]
Indeed, petitioner had never claimed
in the RTC that it was not the party
referred to in the foreign arbitral award. On the contrary, petitioner's Answer with Counterclaim filed in the RTC
even established its knowledge and participation in the Sub-Contract Agreement.
Under the heading of Special and Affirmative Defenses, petitioner alleged,
among others that:
6. plaintiff's claims have been paid, set-off, or extinguished.
x x x x
14. That under the
Sub-Contract, Annex A of the complaint, it is provided as follows:
14.1 FIRST PARTY
agrees to pay SECOND PARTY at monthly intervals based on actual monthly
progress accomplishment, plus 50% on material on Site less 5% retention and
less advance payments, to be paid within 15 days of FIRST PARTY'S receipt from
Client subject to any changes imposed by the Client in approving the monthly
Valuation Certificate. Details of any such modifications will be available to
the Sub-Contractor insofar as they affect his previously agreed valuation
amount.
Defendant has not been paid by its principal contractor the
payment/value of the corresponding accomplishments done by plaintiff and that,
therefore, plaintiff's cause of action against answering defendant has not
accrued;
15. That in any event, the alleged claim was
discharged on September 12, 1983 by assignment to plaintiff in the full amount
of the true and actual measure and valuation calculated upon termination of the
contract by the Primary Contractor;
16.
In any event, the termination of the contract of the primary contractor
occurred without the fault or negligence of the defendants; neither was it responsible
for the force majeure under the terms
of the contract.[17]
Moreover, in petitioner's Memorandum
of Authorities on the Invalidity and Unenforceability of the Foreign Judgment[18]
filed with the RTC, it again made admission that it was the party referred to
in the foreign arbitral award, thus:
x x x x
Likewise, the foreign
arbitral award rendered judgment against both defendants by placing the name of
defendant LANDOIL RESOURCES COMPANY (sic
corporation) and thereafter enclosed in parenthesis the name of the other
defendant Construction Consortium, Inc. without however specifying the specific
liabilities of either of the defendants. Being corporations, defendants have
legal personalities separate and distinct from each other and as such must be
taken distinctly and separately from one another x x x[19]
Section 4,
Rule 129 of the Rules of Court provides:
Sec.
4. Judicial admissions. An
admission, verbal or written, made by a party in the course of the proceedings
in the same case, does not require proof. The admission may be
contradicted only by showing that it was made through palpable mistake or that
no such admission was made.
A party may make judicial admissions
in (a) the pleadings; (b) during the trial, either by verbal or written
manifestations or stipulations; or (c) in other stages of the judicial
proceeding.[20]
It is well-settled that judicial admissions cannot be contradicted by the
admitter who is the party himself[21] and binds the
person who makes the same, and absent any showing that this was made thru
palpable mistake, no amount of rationalization can offset it.[22]
Finally, we find no reversible error committed by the CA in affirming the RTC decision finding petitioner
estopped from denying its participation and liability under the Sub-Contract Agreement
and the enforcement of the foreign arbitral award against it. We find apropos
what the CA said in this wise:
Defendant-appellant cannot deny its participation in the Subcontract. The agreement itself mentioned Landoil as one
of the contracting parties.
Specifically, a perusal of the Subcontract Agreement reveals in Article
8, Section 1 thereof that:
8.1 All
notices to a party hereto shall be sent as follows:
FIRST PARTY: LANDOIL
RESOURCES CORPORATION
CONSTRUCTION CONSORTIUM INCORPORATED
P.O.
Box 49393
Omariyah,
Kuwait
For
the attention
of
Or delivered
To: K.O.C. Project Manager
Project
Office of Ahmadi
SECONDARY
PARTY: AL RABIAH LIGHTING COMPANY W.L.I.
P.O.
Box 22015
Sarat
Kuwait
For
the attention
of
Or delivered
To: Mr. Said
Y. Al Imam
Further,
it is of record that on September 12, 1982, Landoil, thru its Regional
Marketing Director Robert J. Brown, wrote to plaintiff Al Rabiah confirming
that Landoil owes Al Rabiah the sum of KD21,930.317 and that said sum was due
on August 22, 1982. It was further
acknowledged in said letter that inasmuch as the sum cannot be paid
immediately, an interest at the rate of 12% on the overdue amount shall be paid
until the principal amount can be satisfied.
Landoil signified that it expected to pay such amount by October 1982
together with other due accounts. This
letter is part of the evidence on record and was not refuted by
defendant-appellant Landoil.
The
foregoing persuades this Court of Landoils participation in the Subcontract
Agreement. It is apparent that Landoil
is named as a first party to the subject Agreement and it represented itself as
an obligor in the September 12, 1982 letter acknowledging overdue accounts in
favor of Al Rabiah.
Moreover,
notwithstanding its denial, defendant-appellant did allege in Paragraph 14 of
its Answer to the Complaint a quo
that:
14. x x x x
Defendant had not been paid by its principal contractor the
payment/value of the corresponding accomplishments done by plaintiff and that
therefore, plaintiffs cause of action against answering defendant has not
accrued. (RTC Records, p. 43)
Such statement impliedly admits defendant-appellants liability under
the Subcontract Agreement, but raises as a special defense that
plaintiff-appellees action is allegedly premature, as Landoil itself had not
received any payment from its principal contractor.
Thus,
Landoils argument, that it is a distinct corporation from CCI and cannot be
accountable for breaches made by such other corporation, must fail. We find that Landoil itself is a party to the
Subcontract Agreement and has made representations in the past binding itself
to Al Rabiah for overdue accounts in favor of the latter. Under the doctrine of estoppels, an admission
or representation is rendered conclusive upon the person making it, and cannot
be denied or disproved as against the person relying thereof. (Ayala Corporation v. Ray Burton Development
Corporation, 294 SCRA 48).[23]
Petitioner is indeed barred from
adopting an inconsistent position, attitude, or course of conduct that would
cause loss or injury to respondent.[24]
WHEREFORE, the
petition for review is DENIED. The Decision dated August 14, 2003 and the
Resolution dated August 29, 2006 of the Court of Appeals are hereby AFFIRMED.
SO ORDERED.
DIOSDADO
M. PERALTA
Associate Justice
WE
CONCUR:
ANTONIO T. CARPIO
Associate
Justice
PRESBITERO
J. VELASCO, JR. ROBERTO
A. ABAD
Associate Justice Associate Justice
Chairperson
JOSE CATRAL MENDOZA
Associate
Justice
ATTESTATION
I attest that the conclusions in
the above Decision had been reached in consultation before the case was
assigned to the writer of the opinion of the Courts Division.
PRESBITERO J. VELASCO, JR.
Associate Justice
Third Division, Chairperson
CERTIFICATION
Pursuant to Section 13, Article
VIII of the Constitution and the Division Chairpersons Attestation, I certify
that the conclusions in the above Decision had been reached in consultation
before the case was assigned to the writer of the opinion of the Courts
Division.
RENATO
C. CORONA
Chief
Justice
* Designated
additional member in lieu of Associate Justice Maria Lourdes P. A. Sereno, per
Special Order No. 1076-a dated September 6, 2011.
[1] Penned
by Associate Justice Elvi John S. Asuncion, with Associate Justices Eugenio S.
Labitoria and Lucas P. Bersamin (now a
member of this Court), concurring; rollo,
pp. 27-35.
[2] Penned
by Associate Justice Lucas P. Bersamin, with Associate Justices Martin S.
Villarama, Jr. (now a member of this Court), and Monina Arevalo-Zenarosa,
concurring; id. at 46-49.
[3] Records, pp. 8-15.
[4] Id.
at 16-22.
[5] Id.
at 135.
[6] Id. at 20.
[7] Id. at 21.
[8] Id.
at 19.
[9] Id.
at 22.
[10] Id.
at 1-5.
[11] Id.
at 41-44.
[12] Id.
at 45-49.
[13]
Id. at 463-473; Per Judge
Delia H. Panganiban.
[14] Id. at 473.
[15] Rollo, p. 15.
[16] Id. at 48-49.
[17] Records,
pp. 41-43.
[18] Id. at 196-200.
[19] Id. at 200.
[20] See
Binarao v. Plus Builders, Inc., G.R.
No. 154430, June 16, 2006, 491 SCRA 49, 54.
[21] Id. citing Granada,
et al. v. PNB, G.R. No. L-20745, September 2, 1966, 18 SCRA 1.
[22] Id. citing Yuliongsiu
v. PNB, G.R. No. L-19227, February 17, 1968, 22 SCRA 585.
[23] Rollo,
pp. 30-32.
[24] See Caldo v. Caldo-Atienza, G.R. No. 164453,
March 28, 2006, 485 SCRA 504, 511, citing Cruz
v. Court of Appeals, 354 Phil. 1036, 1054 (1998).