ALCATEL PHILIPPINES, INC., G.R. No. 182946
Petitioner,
Present:
VELASCO, JR., J., Chairperson,
- versus - PERALTA,
ABAD,
MENDOZA, and
PERLAS-BERNABE, JJ.
I.M.
BONGAR & CO., INC. and
STRONGHOLD
INSURANCE Promulgated:
CO.,
INC.,
Respondents. October 5, 2011
x
---------------------------------------------------------------------------------------
x
ABAD, J.:
This case is about a trial courts
award of attorneys fees in the dispositive portion of its decision but with no
discussion of its entitlement in the body of that decision.
The Facts and the Case
Philippine Long Distance Telephone
Company (PLDT) engaged the services of Alcatel Philippines, Inc. (Alcatel) to
do the civil works needed for its Fast Track Project in North Paraaque. To carry out these works, on June 20, 1991 Alcatel
entered into a P12,047,407.00 subcontract with I.M. Bongar and Co., Inc.
(Bongar) for the construction of needed manholes and conduits. Alcatel gave Bongar a down payment of 20% of
the contract price or P2,409,481.40.
Two of the requirements of their
agreement were that Bongar was to post 1) a performance bond equivalent to 25%
of the total value of the subcontract and 2) an advance payment bond guarantee. Complying with these requirements, on June
27, 1991 Bongar and Stronghold Insurance Co., Inc. (SIC) executed a Surety Bond
and a Performance Bond, binding themselves jointly and severally to pay Alcatel
P2,409,481.40 and P3,011,851.75, respectively, in the event of Bongars
failure to perform faithfully and within the agreed time, its obligations under
its contract.
The contract with Bongar took effect
on July 29, 1991. The parties agreed to
have the project completed within 90 days from July 29 or by October 29. In the course of periodic inspection of the
progress of the works, however, Alcatel noted that Bongar had fallen behind schedule. Alcatel also received reports of inferior
work from the homeowners association in Paraaque. As it turned out, Bongar failed to finish the
required works by October 29.
After several meetings between the
parties, on December 1, 1991 Bongar wrote Alcatel submitting an adjusted work
schedule that set a new completion target by May 31, 1992. On April 20, 1992, however, Bongar altogether
stopped further construction activities, forcing Alcatel to take over the works. In a letter dated June 1, 1992, Alcatel cancelled
Bongars contract, demanded that it vacate and turn over possession of the
construction area, and hand over all uninstalled Alcatel-supplied materials
within 24 hours from receipt of the letter.
Since Bongar ignored the letter,
Alcatel sent it another one dated August 7, 1992, this time with notice to SIC,
demanding payment of their liabilities under their bonds. Both Bongar and SIC refused to comply, thus
prompting Alcatel to file an action for damages against them before the Makati
Regional Trial Court (RTC).
On September 24, 2001 the RTC rendered
judgment, ordering Bongar and SIC to pay Alcatel, jointly and severally, the
value of the uninstalled materials given to Bongar worth P919,471.10 and
attorneys fees and costs of P500,000.00. But the RTC denied for lack of evidence Alcatels
claims for P500,482.41 in overpayment and P1,098,208.02 in additional
costs spent for completing the subject works.
Alcatel appealed to the Court of Appeals (CA).
On August 31, 2007 the CA affirmed
the RTC Decision but deleted the award of attorneys fees and costs for the
reason that, while these are stated in the dispositive portion, they are not
mentioned in the body of the decision. Alcatel
seeks the review of the CA decision.
The Issues Presented
The issues in this case are whether
or not the CA erred in ruling that Alcatel is not entitled to a) an award of attorneys
fees; b) a refund of overpayment; and c) payment of additional costs for
completion.
The Rulings of the Court
Although attorneys fees are not allowed in the absence of
stipulation, the court can award the same when the defendants act or omission
has compelled the plaintiff to incur expenses to protect his interest or where the defendant acted
in gross and evident bad faith in refusing to satisfy the plaintiff's plainly
valid, just, and demandable claim.[1]
Still,
the award of attorneys fees to the winning
party lies within the discretion of the court, taking into account the
circumstances of each case. This means
that such an award should have factual,
legal, and equitable basis, not founded on pure speculation and
conjecture. Further, the court should
state the reason for the award of attorneys fees in the body of the decision. Its unheralded appearance in the dispositive
portion is, as a rule, not allowed.[2]
Here, however, although the RTC did not specifically discuss in
the body of its decision its basis for awarding attorneys fees, its findings
of fact clearly support such an award. For
instance, the RTC found, based on the record, that Bongar persistently and
clearly violated the terms of its contract with Alcatel. It failed to finish the works by October 29,
1991, the stipulated date. It sought on
December 1, 1991, more than a month after it was in violation, to finish its
job by May 31, 1992, an extra seven months for just a three-month project. Worse, when Alcatel had to take over the job
to save its own undertaking to PLDT, Bongar refused to return to Alcatel the
uninstalled materials that it provided for the works.[3] Alcatel was forced to litigate to protect its
interest.[4]
With respect, however, to Alcatels claims for refund of what it overpaid Bongar and for recovery of the costs incurred in procuring needed materials anew, the Court sees no reason to deviate from the findings of the RTC and the CA. Alcatel mainly asserts that, since Bongar failed to specifically deny those claims, it should be deemed to admit them. But, as the CA aptly held, Bongar vehemently disputed and rejected such claims in its answer to the complaint.[5]
Notably,
Alcatel averred that it paid Bongar P7,056,449.31 when the value of its work
amounted to only P6,555,966.92, showing an excess payment of P500,482.41. But, in its Answer, Bongar said that it
received only P6,505,049.61.[6] Besides, the receipts that Alcatel presented
were only for P2,409,481.40,[7] P1,300,000.00,[8]
and P2,795,568.71.[9] It adduced no receipts for the amounts of P315,790.00
and P234,609.70.[10] The same is true of Alcatels claim for re-procurement
costs. It adduced no evidence to substantiate
such claim. Indeed, Alcatel expressed
the belief that it did not have to prove its two claims since Bongar did not
specifically deny them,[11] an
unfounded belief.
WHEREFORE,
the Court PARTLY GRANTS the petition,
SETS ASIDE the decision of the Court
of Appeals in CA-G.R. CV 74652 dated August 31, 2007, and REINSTATES the decision of the Regional Trial Court of Makati,
Branch 66, in Civil Case 93-2323 dated September 24, 2001.
SO
ORDERED.
ROBERTO A. ABAD
Associate Justice
WE
CONCUR:
PRESBITERO J. VELASCO, JR.
Associate Justice
Chairperson
DIOSDADO M. PERALTA JOSE CATRAL MENDOZA
Associate Justice Associate Justice
ESTELA M. PERLAS-BERNABE
Associate Justice
ATTESTATION
I attest that the conclusions in the
above Decision had been reached in consultation before the case was assigned to
the writer of the opinion of the Courts Division.
PRESBITERO J. VELASCO, JR.
Associate Justice
Chairperson, Third Division
CERTIFICATION
Pursuant to Section 13, Article VIII
of the Constitution and the Division Chairpersons Attestation, I certify that
the conclusions in the above Decision had been reached in consultation before
the case was assigned to the writer of the opinion of the Courts Division.
RENATO C. CORONA
Chief Justice
[1] Civil Code of the Philippines, Article 2208.
[2] Pagsibigan v. People, G.R.
No. 163868, June 4, 2009, 588 SCRA 249, 258.
[3] Exhibits R, S, T, U, V, V-1, W,
and W-1, records, Vol. III, pp. 96-113 and 117-118.
[4] Civil
Code of the Philippines, Article 2208. In the absence of stipulation, attorney s
fees and expenses of litigation, other than judicial costs cannot be recovered
except:
x x x x
2. When
the defendants act or omission has compelled the plaintiff to litigate with
third persons or to incur expenses to protect his interest.
[5] See paragraphs 21 and 22 of the Answer to the Complaint, records, Vol. I, p. 273.
[6] Id. at 270.
[7] Exhibit N, records, Vol. III, p. 62.
[8] Exhibit O, id. at 63.
[9] Exhibits P to P-29, id. at 64-93.
[10]
TSN, April 20, 1998, pp. 52-53.
[11] Rollo, p. 25.