Republic of the Philippines EN BANC
|
|
GREGORIO
R. VIGILAR, SECRETARY OF THE DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH), DPWH
UNDERSECRETARIES TEODORO E. ENCARNACION AND EDMUNDO E. ENCARNACION AND
EDMUNDO V. MIR, DPWH ASSISTANT SECRETARY JOEL L. ALTEA, DPWH REGIONAL
DIRECTOR VICENTE B. LOPEZ, DPWH DISTRICT ENGINEER ANGELITO M. TWAÑO, FELIX A.
DESIERTO OF THE TECHNICAL WORKING GROUP VALIDATION AND AUDITING TEAM, AND
LEONARDO ALVARO, ROMEO N. SUPAN, VICTORINO C. SANTOS OF THE DPWH PAMPANGA 2ND
ENGINEERING DISTRICT, Petitioners, - versus - ARNULFO
D. AQUINO, Respondent. |
G.R. No. 180388 Present: CARPIO, CARPIO MORALES, VELASCO, JR., NACHURA, LEONARDO-DE CASTRO, BRION, PERALTA, BERSAMIN, ABAD, VILLARAMA, JR., PEREZ, SERENO, JJ. Promulgated: January
18, 2011 |
x
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -x
D E C
I S I O N
SERENO, J.:
Before the Court is a Petition for Review on
Certiorari[1] under
Rule 45 of the Rules of Court, assailing the Decision[2] of the
Court of Appeals in C.A.-G.R. CV No. 82268, dated 25 September 2006.
The antecedent facts are as follows:
On
19 June 1992, petitioner Angelito M. Twaño, then Officer-in-Charge
(OIC)-District Engineer of the Department of Public Works and Highways (DPWH) 2nd
Engineering District of Pampanga sent an Invitation to Bid to respondent
Arnulfo D. Aquino, the owner of A.D. Aquino Construction and Supplies. The
bidding was for the construction of a dike by bulldozing a part of the Porac
River at Barangay Ascomo-Pulungmasle, Guagua, Pampanga.
Subsequently, on 7 July
1992, the project was awarded to respondent, and a “Contract of Agreement” was
thereafter executed between him and concerned petitioners for the amount of PhP1,873,790.69,
to cover the project cost.
By 9 July 1992, the
project was duly completed by respondent, who was then issued a Certificate of
Project Completion dated 16 July 1992. The certificate was signed by Romeo M.
Yumul, the Project Engineer; as well as petitioner Romeo N. Supan, Chief of the
Construction Section, and by petitioner Twaño.
Respondent Aquino,
however, claimed that PhP1,262,696.20 was still due him, but petitioners
refused to pay the amount. He thus filed a Complaint[3] for
the collection of sum of money with damages before the Regional Trial Court of
Guagua, Pampanga. The complaint was docketed as Civil Case No. 3137.
Petitioners, for their
part, set up the defense[4] that
the Complaint was a suit against the state; that respondent failed to exhaust
administrative remedies; and that the “Contract of Agreement” covering the
project was void for violating Presidential Decree No. 1445, absent the proper
appropriation and the Certificate of Availability of Funds.[5]
On 28 November 2003, the
lower court ruled in favor of respondent, to wit:
WHEREFORE,
premises considered, defendant Department of Public
Works and Highways is hereby ordered to pay the plaintiff Arnulfo D. Aquino the
following:
1. PhP1,873,790.69, Philippine Currency, representing
actual amount for the completion of the project done by the plaintiff;
2. PhP50,000.00 as attorney’s fee and
3. Cost of this suit.
SO ORDERED. [6]
It is to be noted that respondent was only asking
for PhP1,262,696.20; the award in paragraph 1 above, however, conforms to the
entire contract amount.
On appeal, the Court of Appeals reversed and set
aside the Decision of the lower court and disposed as follows:
WHEREFORE, premises considered, the appeal is GRANTED.
The “CONTRACT AGREEMENT” entered into between the plaintiff-appellee’s
construction company, which he represented, and the government, through the
Department of Public Works and Highway (DPWH) – Pampanga 2nd
Engineering District, is declared null and void ab initio.
The assailed decision of the court a quo is hereby
REVERSED AND SET ASIDE.
In line with the pronouncement in Department of Health vs. C.V. Canchela &
Associates, Architects,[7]
the Commission on Audit (COA) is hereby ordered to determine and ascertain
with dispatch, on a quantum meruit
basis, the total obligation due to the plaintiff-appellee for his undertaking
in implementing the subject contract of public works, and to allow payment
thereof, subject to COA Rules and Regulations, upon the completion of the said
determination.
No pronouncement as to costs.
SO ORDERED.[8]
Dissatisfied with the Decision of the Court of
Appeals, petitioners are now before this Court, seeking a reversal of the
appellate court’s Decision and a dismissal of the Complaint in Civil Case No.
G-3137. The Petition raises the following issues:
1. WHETHER OR NOT THE COURT OF APPEALS ERRED IN HOLDING
THAT THE DOCTRINE OF NON-SUABILITY OF THE STATE HAS NO APPLICATION IN THIS
CASE.
2. WHETHER OR NOT THE COURT OF APPEALS ERRED IN NOT
DISMISSING THE COMPLAINT FOR FAILURE OF RESPONDENT TO EXHAUST ALL
ADMINISTRATIVE REMEDIES.
3. WHETHER OR NOT THE COURT OF APPEALS ERRED IN
ORDERING THE COA TO ALLOW PAYMENT TO RESPONDENT ON A QUANTUM MERUIT BASIS
DESPITE THE LATTER’S FAILURE TO COMPLY WITH THE REQUIREMENTS OF PRESIDENTIAL
DECREE NO. 1445.
After a judicious review of the case, the Court
finds the Petition to be without merit.
Firstly, petitioners claim that the Complaint filed
by respondent before the Regional Trial Court was done without exhausting
administrative remedies. Petitioners aver that respondent should have first
filed a claim before the Commission on Audit (COA) before going to the courts.
However, it has been established that the doctrine of exhaustion of
administrative remedies and the doctrine of primary jurisdiction are not
ironclad rules. In Republic of the
Philippines v. Lacap,[9] this
Court enumerated the numerous exceptions to these rules, namely: (a) where
there is estoppel on the part of the party invoking the doctrine; (b) where the
challenged administrative act is patently illegal, amounting to lack of
jurisdiction; (c) where there is unreasonable delay or official inaction that
will irretrievably prejudice the complainant; (d) where the amount involved is
relatively so small as to make the rule impractical and oppressive; (e) where
the question involved is purely legal and will ultimately have to be decided by
the courts of justice; (f) where judicial intervention is urgent; (g) where the
application of the doctrine may cause great and irreparable damage; (h) where
the controverted acts violate due process; (i) where the issue of
non-exhaustion of administrative remedies has been rendered moot; (j) where
there is no other plain, speedy and adequate remedy; (k) where strong public
interest is involved; and (l) in quo
warranto proceedings. In the present case, conditions (c) and (e) are
present.
The government project contracted out to respondent
was completed almost two decades ago. To delay the proceedings by remanding the
case to the relevant government office or agency will definitely prejudice
respondent. More importantly, the issues in the present case involve the
validity and the enforceability of the “Contract of Agreement” entered into by
the parties. These are questions purely of law and clearly beyond the expertise
of the Commission on Audit or the DPWH. In Lacap,
this Court said:
... It
does not involve an examination of the probative value of the evidence
presented by the parties. There is a question of law when the doubt or
difference arises as to what the law is on a certain state of facts, and not as
to the truth or the falsehood of alleged facts. Said question at best could be
resolved only tentatively by the administrative authorities. The final decision on the matter rests not
with them but with the courts of justice. Exhaustion of administrative remedies
does not apply, because nothing of an administrative nature is to be or can be
done. The issue does not require technical knowledge and experience but one
that would involve the interpretation and application of law. (Emphasis
supplied.)
Secondly, in ordering the payment of the obligation
due respondent on a quantum meruit basis, the Court of Appeals correctly relied
on Royal Trust Corporation v. COA,[10]
Eslao v. COA,[11]
Melchor v. COA,[12] EPG Construction Company v. Vigilar,[13]
and Department of Health v. C.V.
Canchela & Associates, Architects.[14] All
these cases involved government projects undertaken in violation of the
relevant laws, rules and regulations covering public bidding, budget
appropriations, and release of funds for the projects. Consistently in these
cases, this Court has held that the contracts were void for failing to meet the
requirements mandated by law; public interest and equity, however, dictate that
the contractor should be compensated for services rendered and work done.
Specifically, C.V.
Canchela & Associates is similar to the case at bar, in that the contracts
involved in both cases failed to comply with the relevant provisions of
Presidential Decree No. 1445 and the Revised Administrative Code of 1987.
Nevertheless, “(t)he illegality of the subject Agreements proceeds,
it bears emphasis, from an express declaration or prohibition by law, not from
any intrinsic illegality. As such, the Agreements are not illegal per
se, and the party claiming thereunder may recover what had been paid or
delivered.”[15]
The government project involved in this case, the
construction of a dike, was completed way back on 9 July 1992. For almost two
decades, the public and the government benefitted from the work done by
respondent. Thus, the Court of Appeals was correct in applying Eslao to the present case. In Eslao,
this Court stated:
...the Court finds that the contractor should be duly compensated for services rendered, which were for the benefit of the general public. To deny the payment to the contractor of the two buildings which are almost fully completed and presently occupied by the university would be to allow the government to unjustly enrich itself at the expense of another. Justice and equity demand compensation on the basis of quantum meruit. (Emphasis supplied.)
Neither can petitioners
escape the obligation to compensate respondent for services rendered and work
done by invoking the state’s immunity from suit. This Court has long established in Ministerio v. CFI of Cebu,[16] and
recently reiterated in Heirs of Pidacan
v. ATO,[17]
that the
doctrine of governmental immunity from suit cannot serve as an instrument for
perpetrating an injustice to a citizen. As this Court enunciated in EPG Construction:[18]
To our mind, it would be the apex of injustice and highly inequitable to
defeat respondent’s right to be duly compensated for actual work performed and
services rendered, where both the government and the public have for years
received and accepted benefits from the project and reaped the fruits of
respondent’s honest toil and labor.
... ... ...
Under these circumstances, respondent may not
validly invoke the Royal Prerogative of
Dishonesty and conveniently hide under the State's cloak of invincibility
against suit, considering that this principle yields to certain settled
exceptions. True enough, the rule, in any case, is not absolute for it does
not say that the state may not be sued under any circumstance.
... ... ...
Although the Amigable
and Ministerio cases generously
tackled the issue of the State's immunity from suit vis a vis the payment of just compensation for expropriated
property, this Court nonetheless finds the doctrine enunciated in the
aforementioned cases applicable to the instant controversy, considering that
the ends of justice would be subverted if we were to uphold, in this particular
instance, the State's immunity from suit.
To be sure, this Court — as the staunch guardian of the citizens' rights
and welfare — cannot sanction an injustice so patent on its face, and allow
itself to be an instrument in the perpetration thereof. Justice and equity
sternly demand that the State's cloak of invincibility against suit be shred in
this particular instance, and that petitioners-contractors be duly compensated
— on the basis of quantum meruit —
for construction done on the public works housing project. (Emphasis supplied.)
WHEREFORE, in view of the
foregoing, the Petition is DENIED for lack of merit. The assailed Decision
of the Court of Appeals in CA-G.R. No. 82268 dated 25 September 2006 is AFFIRMED.
SO
ORDERED.
MARIA
LOURDES P. A. SERENO
Associate Justice
WE CONCUR:
RENATO
C. CORONA
Chief Justice
ANTONIO
T. CARPIO CONCHITA
CARPIO MORALES
Associate Justice
Associate Justice
PRESBITERO
J. VELASCO, JR. ANTONIO EDUARDO B.
NACHURA
Associate Justice Associate Justice
TERESITA J. LEONARDO-DE CASTRO ARTURO
D. BRION
Associate Justice Associate Justice
DIOSDADO M. PERALTA LUCAS P. BERSAMIN
Associate Justice Associate
Justice
MARIANO C. DEL CASTILLO
ROBERTO A. ABAD
Associate Justice
Associate Justice
MARTIN S. VILLARAMA, JR.
JOSE PORTUGAL PEREZ
Associate Justice Associate Justice
JOSE CATRAL
MENDOZA
Associate
Justice
Pursuant to Section 13, Article VIII
of the Constitution, I certify that the conclusions in the above Decision had
been reached in consultation before the case was assigned to the writer of the
opinion of the Court.
RENATO
C. CORONA
Chief
Justice
[1] Rollo at 10-32.
[2] Penned by Associate
Justice Amelita G. Tolentino, with Associate Justices Portia Aliño-Hormachuelos
and Arcangelita Romilla-Lontok concurring, rollo
at 33-48.
[3] Rollo at 51-55.
[4] Petitioners’ Answer, rollo at 56-59.
[5] Sections 85-87,
Ordaining and Instituting a Government Auditing Code of the
[6] Rollo at 60-64.
[7]G.R. Nos. 151373-74, November 17, 2005,
475 SCRA 218.
[8] Rollo at 47.
[9] G.R. No. 158253,
March 2, 2007, 517 SCRA 255.
[10]Supreme Court
Resolution En Banc, G.R. No. 84202, November 22, 1988, cited in Eslao v. COA, 195 SCRA 730.
[11] G.R. No. 89745, April
8, 1991, 195 SCRA 730.
[12] G.R. No. 95938,
August 16, 1991, 200 SCRA 705.
[13] G.R. 131544, March
16, 2001, 354 SCRA 566.
[14] Supra at note 7.
[15] DOH v. C.V. Canchela Associates, Architects, G.R. Nos. 151373-74, November 17, 2005,
475 SCRA 218.
[16] G.R.
No. L-31635, August 31, 1971, 40 SCRA 464.
[17] G.R. No. 186192,
August 25, 2010.
[18] G.R. No. 131544,
March 16, 2001, 354 SCRA 566.