Republic
of the Philippines
Supreme Court
Manila
AMERICAN
HOME INSURANCE CO. OF NEW YORK,
Petitioner, - versus F.F. CRUZ & CO., INC., Respondent. |
G.R. No. 174926 Present: CARPIO,* J., VELASCO,
JR., J., Chairperson, BRION,** PERALTA, and SERENO,***
JJ. Promulgated: August 10, 2011 |
x-----------------------------------------------------------------------------------------x
PERALTA, J.:
This is a petition for
review on certiorari under Rule 45 of the Rules of Court filed by
American Home Insurance Co. of New York (American Home) assailing the Court of
Appeals (CA) Decision[1]
dated September 29, 2005 and Resolution[2]
dated September 25, 2006 in CA-G.R. CV No. 73960. The assailed Decision
affirmed the Decision[3]
of the Regional Trial Court (RTC) of Makati, Branch 137 in Civil Case No.
93-2585, while the assailed Resolution denied American Homes motion for
reconsideration.
The case stemmed from the following facts:
In June 1990, the Philippine Ports Authority (PPA)
conducted a bidding of a project for the dredging of the entrance channel and
harbor basin of the Cebu International Port in Cebu City. The PPA awarded the
contract to the winning bidder, F.F. Cruz & Co., Inc. (FF Cruz). Pursuant to their earlier agreement, FF Cruz
and Genaro Reyes Construction, Inc. (hereafter referred to as G. Reyes)
executed a Sub-Contract Agreement[4]
whereby the latter agreed to undertake the performance of 50% of the dredging projects
estimated volume of 600,000 cubic meters. The sub-contract was subject to the
following terms and conditions:
x x x x
5. That the SUB-CONTRACTOR shall
file immediately upon its receipt of NOTICE TO PROCEED, a PERFORMANCE BOND
(callable anytime on demand) from a duly accredited surety company equivalent
to 10% of the SUBCONTRACTS TOTAL COST;
6. That the SUB-CONTRACTOR agrees
to start to work on the PROJECT within thirty (30) calendar days or as directed
by the PPA, from the date of NOTICE TO PROCEED for the PROJECT, and obligates
itself to finish the work within the contract time stipulated in the contract
entered into by the CONTRACTOR and PPA;
x x x x[5]
FF Cruz gave G. Reyes an advance payment of P2.2
million guaranteed by a surety bond for the same amount issued by American Home.
The surety bond was issued to guarantee payment of the advance payment made by FF
Cruz to G. Reyes for the dredging project in the event that the latter fail to
comply with the terms and conditions of the sub-contract.[6]
As a security for the
issuance of the bond, Genaro Reyes, as president of G. Reyes, and his wife
Lydia Reyes, executed an Indemnity Agreement where they agreed to jointly and
severally indemnify American Home and keep the latter harmless against all
damages, losses, costs, stamps, taxes, penalties, charges and expenses of
whatever kind and nature which it may sustain or incur as a consequence of
having become a surety, or any extension, renewal, substitution or alteration
made thereof.[7]
They likewise undertook to pay, reimburse and make good to American Home all
sums which the latter shall pay on account of the bond.[8]
It was also agreed upon that their liability attaches as soon as demand is
received by American Home from FF Cruz, or as soon as it becomes liable to make
payment under the terms of the surety bond.
In a letter dated March 6, 1991, FF Cruz informed G. Reyes
that the former mobilized its dredger and started operation on March 3, 1991.
In the same letter, FF Cruz requested G. Reyes to mobilize its equipment on or
before March 20, 1991.[9]
On October 21, 1991, G. Reyes complained to the PPA about
the great deal of silt and waste materials that had accumulated in the area
which adversely affected its work accomplishment. In December 1991, G. Reyes
informed FF Cruz that the equipment used for the project had been encountering difficulties
because of siltation problems. G. Reyes finally admitted that continuing the
project was no longer a wise investment and called on FF Cruz to take over the
project. FF Cruz thus took over the unfinished project.[10]
Consequently, FF Cruz demanded from American Home the
payment of P2.2 million representing the amount of the bond. American
Home, in turn, informed G. Reyes of FF Cruzs demand. As the claim left
unheeded, FF Cruz made a final demand on American Home on July 10, 1993. G. Reyes
likewise ignored American Homes demand to fulfill its obligation set forth in
the Indemnity Agreement it executed in favor of the latter.
On July 29, 1993, American Home filed a Complaint for Sum of Money[11]
against G. Reyes, Genaro G. Reyes and Lydia A. Reyes for the payment of P2,200,000.00
corresponding to the amount of the bond, plus attorneys fees and litigation
expenses.[12]
In its complaint, American Home sought the enforcement of the Indemnity
Agreement undertaken by G. Reyes in conjunction with FF Cruzs demand for the
payment of the amount of the surety bond.
G. Reyes et al.,
in turn, filed an Answer with Counterclaim and Third-Party Complaint[13]
against FF Cruz. G. Reyes denied liability to American Home on the ground that G.
Reyes did not fail to comply with its obligation to FF Cruz. It explained that its (G. Reyes) liability
would arise only in case of its failure to comply with the terms and conditions
of the sub-contract. It insisted that it was FF Cruz who was guilty of breach
of its obligations. In its Third-Party Complaint against FF Cruz, G. Reyes
argued that the siltation problems caused by the former resulted in the
reduction of G. Reyes project accomplishment and failure to finish the
project. It also claimed that FF Cruz
still has an unpaid balance of more than P5 million as it recognized
only the accomplishment of 57,284.44 cubic meters instead of 184,210 cubic
meters claimed by G. Reyes.
In answer to the third-party complaint of G. Reyes, FF Cruz
denied that it caused the siltation problems and argued that the former abandoned
the project because it was incapable of performing its obligations. It also
explained that it had no unpaid obligation to G. Reyes as it paid its
accomplishment based on the report of the PPA.[14]
FF Cruz thereafter filed a Fourth-Party Complaint against
American Home calling on the surety bond it provided in favor of G. Reyes.[15]
During the pre-trial, the parties agreed to limit the
issues, to wit:
1)
Is the fourth-party defendant AMERICAN HOME free from liability on
the claim of fourth-party plaintiff FF Cruz as set forth in the fourth-party complaint
because:
a)
The provision in American Surety Bond No. 304-67535575 that the
same is callable anytime on demand is null and void?
b)
Assuming that it is not, is fourth-party defendant AMERICAN HOME
free from liability because Genaro G. Reyes Construction, Inc. had fulfilled
all its obligations under the sub-contract it had with fourth-party plaintiff?
2)
Is AMERICAN HOME free from liability relative to the fourth-party
plaintiff claim as set forth in the complaint because the damages suffered by
fourth-party plaintiff arose from force
majeure?
3)
If [fourth-party] defendant AMERICAN HOME is liable on the surety
bond, what is the amount and nature of the damages that should be awarded to
fourth-party plaintiff?[16]
After the presentation of
the parties respective evidence, the RTC rendered a Decision,[17]
the dispositive portion of which reads:
WHEREFORE, judgment is hereby
rendered ordering plaintiff American Home Insurance Company of New York and
third-party plaintiff Genaro G. Reyes Construction, Incorporated, jointly and
severally, to pay third-party defendant F.F. Cruz and Company the amount of P2,200,000.00
representing the full amount of the surety bond.
The third-party complaint of
third-party plaintiff Genaro G. Reyes Construction, Incorporated, against
third-party defendant F.F. Cruz and Company, and the counterclaim for
attorneys fees of third-party plaintiff Genaro G. Reyes Construction,
Incorporated, against plaintiff American Home Insurance Company of New York,
are both dismissed, for lack of sufficient merit.
On the counterclaim of
third-party defendant F.F. Cruz and Company, judgment is hereby rendered
ordering third-party plaintiff Genaro G. Reyes Construction, Incorporated, to
pay said third-party defendant the following amounts:
1.
P310,150.21
representing the overpayment received by third-party plaintiff Genaro G. Reyes
Construction, Incorporated, from third-party defendant F.F. Cruz and Company,
with 6% interest per annum from the filing of the third-party complaint on 8
April 1994 until full payment;
2.
10% of the above amount as attorneys fees; and
3.
costs of suit.
On the complaint of plaintiff
American Home Insurance Company of New York against defendants and third-party
plaintiff Genaro G. Reyes Construction, Incorporated, Genaro G. Reyes and Lydia
A. Reyes, judgment is hereby rendered ordering defendants and third-party
plaintiffs Genaro G. Reyes Construction, Incorporated, Genaro G. Reyes and
Lydia A. Reyes, jointly and severally, to pay plaintiff American Home Insurance
Company of New York the amount of P2,200,000.00, representing the full
amount of the indemnity agreement, plus 10% thereof as attorneys fees and
costs of suit.
SO ORDERED.[18]
American Home and G.
Reyes et al. appealed to the CA. On
September 29, 2005, the appellate court rendered the assailed decision
dismissing their appeal and, consequently, affirming the RTC decision. The CA
sustained the findings of the RTC that G. Reyes indeed failed to fulfill its
obligation to dredge 300,000 cubic meters as it only finished dredging 57,000
cubic meters. The court opined that there was no proof to show that the
abandonment of the project by G. Reyes was caused by heavy siltation. Considering
that such failure to finish the project constitutes a violation of G. Reyes agreement
with FF Cruz, American Home was held liable under the bond it issued to G.
Reyes.[19]
G. Reyes and American Homes motions for reconsideration were denied on
September 25, 2006.
Aggrieved, G. Reyes
assailed the CA decision and resolution before this Court in a petition for
review on certiorari, [20]
but the same was denied by the Court in a Minute Resolution[21]
dated March 5, 2007.
In this petition under
consideration, American Home likewise assails the same decision and resolution
with the following assigned errors:
I.
THE
COURT OF APPEALS COMMITTED SERIOUS ERROR IN CONSIDERING THE BOND ISSUED BY
PETITIONER TO BE A PERFORMANCE BOND CONTRARY TO THE EXPRESS TERMS OF THE BOND
ITSELF THAT IT WAS TO GUARANTEE PAYMENT FOR THE 15% ADVANCE PAYMENT MADE
BY RESPONDENT TO GENARO G. REYES CONSTRUCTION CORPORATION.
II.
THE
COURT OF APPEALS COMMITTED SERIOUS ERROR IN NOT DISCHARGING PETITIONER FROM ITS
OBLIGATIONS UNDER THE BOND DUE TO THE ABANDONMENT OF THE PROJECT BY GENARO G.
REYES CONSTRUCTION CORPORATION AND THE TAKE-OVER BY RESPONDENT WITHOUT
PETITIONERS PRIOR NOTICE AND CONSENT.
III.
ASSUMING, WITHOUT ADMITTING, THAT
PETITIONER IS LIABLE UNDER THE BOND, THE COURT OF APPEALS COMMITTED SERIOUS
ERROR IN ADJUDGING PETITIONER LIABLE FOR THE ENTIRE OR FACE VALUE OF THE BOND
IN THE AMOUNT OF P2.2 MILLION CONSIDERING THAT THE BOND WAS NOT A
PERFORMANCE BOND TO GUARANTEE THE COMPLETION OF THE PROJECT BUT MERELY TO
GUARANTEE THE PAYMENT OF THE ADVANCES MADE BY RESPONDENT TO GENARO G. REYES
CONSTRUCTION.[22]
American Home faults the
CA in considering the surety bond as a performance bond. It insists that the
bond guaranteed only the payment of the 15% advance payment made by FF Cruz to
G. Reyes amounting to P2.2 million and not the performance of the
latters obligations nor the completion of the dredging operations. It also
avers that making it (American Home) liable under the bond because of G. Reyes
abandonment of the project is tantamount to enlarging its liability. American Home also claims that it was not
informed that G. Reyes already abandoned the project and that FF Cruz took over
to complete the same. This, according to American Home, is a material
alteration of the terms of the surety bond which thus discharged it of
liability on the surety agreement.
The petition is without
merit.
The only issue for
resolution is whether or not American Home is liable to FF Cruz for P2.2
million representing the face value of the surety bond it issued to G. Reyes.
We rule in the
affirmative.
It is well to note that
G. Reyes petition in G.R. No. 174913 has been denied by the Court. Hence, the
same CA decision and resolution assailed in this present petition have become
final and executory as to G. Reyes, Genaro Reyes and Lydia A. Reyes and, in that
respect, it shall not be disturbed by the Court. Consequently, their liability
to American Home pursuant to the Indemnity Agreement has been settled with
finality. They are, therefore, bound to pay American Home P2,200,000.00
representing the full amount of the Indemnity Agreement, plus 10% thereof as
attorneys fees and costs of suit. Their liability to FF Cruz has also been
resolved with finality.
The Court also notes that
the issues raised by American Home in this petition were not raised during the
trial of the case before the RTC. It must be recalled that the case below was
commenced by American Home for the collection of sum of money against G. Reyes
pursuant to the Indemnity Agreement executed by the latter. The issue on
American Homes liability to FF Cruz was squarely raised only in the
fourth-party complaint filed by the latter against the former.
Settled is the rule that
points of law, theories, issues, and arguments not adequately brought to the
attention of the trial court need not be, and ordinarily will not be,
considered by a reviewing court. They cannot be raised for the first time on
appeal. To allow this would be offensive to the basic rules of fair play,
justice and due process.[23]
In order, however, to remove doubt on its liability to FF Cruz, we will discuss
the merits of American Homes arguments.
It is undisputed that FF
Cruz gave G. Reyes P2.2 million as advance payment. As a security
thereof, G. Reyes posted a surety bond issued by American Home in favor of FF
Cruz, the pertinent portion of which reads:
To guarantee payment for the 15% advance
payment made by the obligee [FF Cruz] to the herein principal [G. Reyes] for
the Dredging of Entrance Channel and Harbor Basin of Cebu International Port
Project in the event of the principals failure to comply with the terms and
conditions of the Sub-Contract Agreement dated June 11, 1990, copy of which is
hereto attached and made an integral part hereof; it being expressly understood
that the liability of the surety under this bond shall in no case exceed the
amount of PESOS TWO MILLION TWO HUNDRED THOUSAND ONLY (P2,200,000.00),
Phil. Cy.[24]
It is clear from the
foregoing that indeed, the surety bond was issued to guarantee the payment of
the 15% advance payment of P2.2 million made by FF Cruz to G. Reyes. The
bond was not issued to guarantee the completion of the project. However, the
above provision shows that in order for American Homes liability to attach,
two conditions must be fulfilled: first,
that the advance payment made by FF Cruz to G. Reyes remains unpaid; and second, G. Reyes fails to comply with
any of the terms and conditions set forth in the sub-contract.
There may be a dispute as to the amount of liability as
will be discussed later, but it has been adequately established that FF Cruz
was not yet reimbursed of the advance payment it made. The fulfillment of the
first condition is, therefore, settled.
In the sub-contract agreement, G. Reyes agreed
to finish the work within the time stipulated in the contract between FF Cruz
and the PPA. Admittedly, not only did G. Reyes fail to finish the work on time,
it did not altogether complete the project. If failure to finish the work on
time is violation of the sub-contract agreement, with more reason that
abandonment of the work is covered by the stipulation. As held by the CA:
By G. REYES own claim, it
dredged only 184,000 cubic meters. There thus is no dispute that G. REYES
failed to dredge the 300,000 cubic meters as agreed in the contract. But even
if [w]e are to assume that G. REYES indeed dredged 184,210 cubic meters, this
would still be short of the 300,000 cubic meters it bound itself under the
contract.
In the middle of the project, G
REYES unilaterally abandoned its dredging work and its obligations under the
Sub-Contract Agreement. Without a doubt, G. REYES failed to fulfill its
contractual obligation. x x x[25]
The appellate court did
not also sustain G. Reyes explanation that the abandonment of the project was
due to force majeure. We quote with
approval the CA ratiocination in this wise:
The proffered reason that the
abandonment was due to force majeure
fails to convince this Court. G. REYES excuse that it was forced to abandon
the dredging work due to heavy siltation is not supported by facts on record.
There is no evidence of the alleged heavy siltation. On the contrary, after G
REYES abandoned its dredging work and FF CRUZ took over the dredging, FF CRUZ
was still able to finish the dredging work on time. There is thus no basis for
G REYES justification of force majeure.
Such was a lame excuse for the abandonment of the project.[26]
With the violation of the
sub-contract, which means fulfillment of the second condition, the liability to
pay the advance payment arose.
The payment of the P2.2
million advanced by FF Cruz is the principal liability of G. Reyes. However,
with the issuance of the surety bond, a contract of suretyship was entered into
making American Home equally liable.
A contract of suretyship
is an agreement whereby a party called the surety, guarantees the performance
by another party, called the principal or obligor, of an obligation or
undertaking in favor of another party called the obligee. By its very nature, under the laws regulating
suretyship, the liability of the surety is joint and several but is limited to
the amount of the bond, and its terms are determined strictly by the terms of
the contract of suretyship in relation to the principal contract between the
obligor and the obligee.[27]
The surety is considered
in law as possessed of the identity of the debtor in relation to whatever is
adjudged touching upon the obligation of the latter. Their liabilities are so
interwoven as to be inseparable. Although the contract of suretyship is, in
essence, secondary only to a valid principal obligation, the suretys liability
to the creditor is direct, primary, and absolute; he becomes liable for the
debt and duty of another although he possesses no direct or personal interest
over the obligations nor does he receive any benefit therefrom.[28]
As to the amount of
American Homes liability, the RTC found that G. Reyes did not pay back the
full amount of P2.2 million advance payment. American Home, however,
claims (for the first time) that G. Reyes actually reimbursed P598,880.52
to FF Cruz. As plaintiff in its complaint and defendant in FF Cruzs
fourth-party complaint, American Home was duty-bound to prove that it was
entitled to its claim against G. Reyes under the Indemnity Agreement and that
it was not liable to FF Cruz under the surety bond. Yet, American Home chose
not to present its evidence to substantiate its claim and defense. For lack of
evidence to show the fact of payment, we find no reason to disturb the findings
of the trial court as affirmed by the appellate court that P2.2 million
is due FF Cruz.
Factual findings of the
trial court, particularly when affirmed by the CA, are generally binding on the
Court.[29]
We have repeatedly held that we are not a trier of facts. We generally rely
upon, and are bound by, the conclusions on factual matters made by the lower
courts, which are better equipped and have better opportunity to assess the
evidence first-hand, including the testimony of the witnesses.[30]
The Courts jurisdiction
over a petition for review on certiorari is
limited to reviewing only errors of law, not of facts, unless the factual
findings complained of are devoid of support from the evidence on record or the
assailed judgment is based on a misapprehension of facts.[31]
With the foregoing
disquisition, we need not discuss the other issues raised by American Home.
WHEREFORE, premises considered, the petition is DENIED. The Court of Appeals Decision dated September 29, 2005 and
Resolution dated September 25, 2006 in CA-G.R. CV No. 73960, are AFFIRMED.
SO ORDERED.
DIOSDADO
M. PERALTA
Associate
Justice
WE CONCUR:
ANTONIO T. CARPIO
Associate Justice
PRESBITERO J. VELASCO, JR. ARTURO D. BRION
Associate Justice Associate Justice
Chairperson
MARIA LOURDES P. A. SERENO
Associate
Justice
ATTESTATION
I attest that the conclusions in the above Decision had been reached in
consultation before the case was assigned to the writer of the opinion of the
Courts Division.
PRESBITERO
J. VELASCO, JR.
Associate
Justice
Third
Division, Chairperson
CERTIFICATION
Pursuant to Section 13, Article VIII of the Constitution and the
Division Chairpersons Attestation, I certify that the conclusions in the above
Decision had been reached in consultation before the case was assigned to the
writer of the opinion of the Courts Division.
RENATO
C. CORONA
Chief Justice
* Designated as an additional member in lieu of Associate Justice Roberto A. Abad, per Special Order No. 1059 dated August 1, 2011.
** Designated as an additional member in lieu of Associate Justice Jose Catral Mendoza, per Special Order No. 1056 dated July 27, 2011.
*** Designated as an additional member, per Special Order No. 1028 dated June 21, 2011.
[1] Penned by Associate Justice Vicente S.E. Veloso, with Associate Justices Amelita G. Tolentino and Danilo B. Pine, concurring; rollo, pp. 51-68.
[2] Penned by Asociate Justice Amelita G. Tolentino, with Associate Justices Portia Alio-Hormachuelos and Lucas P. Bersamin (now a member of this Court), concurring; rollo, pp. 71-72.
[3] Penned by Judge Santiago Javier Ranada; CA rollo, pp. 101-118.
[4] Rollo, pp. 181-183.
[5] Id. at 133.
[6] Id. at 64.
[7] CA rollo, p. 103.
[8] Rollo, p. 161.
[9] CA rollo, p. 103.
[10] Id. at 103-104.
[11] Rollo, pp. 159-168.
[12] Id. at 167.
[13] Id. at 169-180.
[14] CA rollo, p. 105.
[15] Id.
[16] Id.
[17] Supra note 3.
[18] CA rollo, pp. 117-118.
[19] Rollo, pp. 61-67.
[20] The petition was entitled Genaro G. Reyes Construction, Inc. et al. v. American Home Insurance Co. of New York and docketed as G.R. No. 174913.
[21] The resolution reads:
x x x x
Considering the allegations, issues and arguments adduced in the petition for review on certiorari assailing the Decision dated 29 September 2005 of the Court of Appeals in CA-G.R. CV No. 73960, the Court resolves to DENY the petition for failure to sufficiently show that the Court of Appeals had committed any reversible error in the questioned judgment to warrant the exercise of this Courts discretionary appellate jurisdiction, and for raising essentially factual issues.
[22] Rollo, pp. 28-29.
[23] Stronghold Insurance Company, Incorporated v. Tokyo Construction Company, Ltd., G.R. Nos. 158820-21, June 5, 2009, 588 SCRA 410, 420.
[24] Rollo, p. 64.
[25] Id. at 63-64.
[26] Id. at 65.
[27] Stronghold Insurance Company, Incorporated v. Tokyo Construction Company, Ltd., supra note 23, at 421-422.
[28] Id. at 422-423.
[29] Raquel-Santos v. Court of Appeals, G.R. Nos. 174986, 175071 and 181415, July 7, 2009, 592 SCRA 169, 195.
[30] Stronghold Insurance Company, Incorporated v. Tokyo Construction Company, Ltd., supra note 23, at 420-421.
[31] Raquel-Santos v. Court of Appeals, supra note 29, at 195-196.