Republic of the
Supreme Court
SECOND DIVISION
SARGASSO CONSTRUCTION & DEVELOPMENT
CORPORATION/PICK & SHOVEL, INC.,/ATLANTIC ERECTORS, INC. (JOINT VENTURE), Petitioner, - versus - pHILIPPINE PORTS AUTHORITY,
Respondent. |
|
G.R. NO. 170530 Present: CARPIO, J., Chairperson, NACHURA, PERALTA, ABAD, and MENDOZA, JJ. Promulgated: July 5, 2010 |
X
--------------------------------------------------------------------------------------
X
D E C I S I O N
MENDOZA, J.:
This is a petition for review on
certiorari under Rule 45 which seeks to annul and set aside the August 22, 2005
Decision[1] of
the Court of Appeals (CA) in CA-G.R. CV No. 63180 and its November 14, 2005 Resolution[2]
denying petitioner’s motion for the reconsideration thereof. The questioned CA
decision reversed the June 8, 1998 Decision[3] of
the Regional Trial Court of Manila, Branch 14, in Civil Case No. 97-83916,
which granted petitioner’s action for specific performance.
The factual
and procedural antecedents have been succinctly recited in the subject Court of
Appeals decision in this
wise:[4]
Plaintiff Sargasso Construction and Development
Corporation, Pick and Shovel, Inc. and Atlantic Erectors, Inc., a joint
venture, was awarded the construction of Pier 2 and the rock causeway (R.C.
Pier 2) for the P4,280
square meters intended for the reclamation project as part of the overall port
development plan.
In a letter dated P36,294,857.03.
Defendant replied thru its Assistant General Manager Teofilo H. Landicho who
sent the following letter dated
“This is to acknowledge receipt of your letter
dated
“Your proposal to undertake the project at a total
cost of THIRTY SIX MILLION TWO HUNDRED NINETY FOUR THOUSAND EIGHT HUNDRED FIFTY
SEVEN AND 03/100 PESOS (P36,294,857.03) is not acceptable to PPA. If you
can reduce your offer to THIRTY MILLION SEVEN HUNDRED NINETY FOUR THOUSAND TWO
HUNDRED THIRTY AND 89/100 (P30,794,230.89) we may consider
favorably award of the project in your favor, subject to the approval of
higher authority.
Please signify your agreement to the reduced amount
of P30,794,230.89 by signing in the space provided below. (emphasis in
the original)
On P30,794,230.89 and instructing
it to “enter into and execute the contract agreement with this Office” and to
furnish the documents representing performance security and credit line.
Defendant likewise stated [and] made it a condition that “fendering of Pier No.
2 Port of San Fernando, and the
At its meeting held on
September 9, 1994, the Board decided not to approve the contract proposal, as
reflected in the following excerpt of the minutes taken during said board
meeting:
“After due deliberation,
the Board advised Management to
bid the project since there is no strong legal basis for Management to award
the supplemental contract through negotiation.
The Board noted that the Pier 2 Project was basically for the construction of a
pier while the supplemental agreement refers to reclamation. Thus there is no
basis to compare the terms and conditions of the reclamation project with the
original contract (Pier 2 Project) of Sargasso.”[5]
It
appears that PPA did not formally advise the plaintiff of the Board’s action on
their contract proposal. As plaintiff learned that the Board was not inclined
to favor its Supplemental Agreement, Mr. Go wrote General Manager Agustin
requesting that the same be presented again to the Board meeting for approval.
However, no reply was received by plaintiff from the defendant.
On
June 30, 1997, plaintiff filed a complaint for specific performance and damages before the
Regional Trial Court of Manila alleging that defendant PPA’s unjustified
refusal to comply with its undertaking, unnecessarily leading to the delay in
the implementation of the award under the August 26, 1993 Notice of Award, has
put on hold plaintiff’s men and resources earmarked for the project, aside from
effectively tying its hands in undertaking other projects for fear that
plaintiff’s incapacity to undertake work might be spread thinly and it might
not be able to function efficiently if the PPA project and other projects
should require simultaneous attention. Plaintiff averred that it sought
reconsideration of the P1,000,000.00), exemplary damages (P1,000,000.00),
attorney’s fees (P300,000.00) and expenses of litigation and costs (P50,000.00).
Defendant
PPA thru the Office of the Government Corporate Counsel (OGCC) filed its Answer with Compulsory Counterclaim contending that the alleged Notice of
Award has already been properly revoked when the Supplemental Agreement which
should have implemented the award was denied approval by defendant’s Board of
Directors. As to plaintiff’s pre-disqualification from participating in the
bidding for the extension of R.C. Pier No. 2 Project at the
After trial, the lower court rendered a decision in favor of the
plaintiff, the dispositive portion of which reads:
“WHEREFORE, and in view of
the foregoing considerations, judgment is hereby rendered ordering the
defendant to execute a contract in favor of the plaintiff for the reclamation
of the area between the Timber Pier and Pier 2 located at P30,794,230.89
and to pay the costs.
The counterclaim is
dismissed for lack of merit.
SO ORDERED.[6]
In addressing affirmatively the basic issue of whether there was a
perfected contract between the parties for the reclamation project, the trial
court ruled that the “higher authority x x adverted to does not necessarily
mean the Board of Directors (Board). Under IRR, P.D. 1594
(1)B10.6, approval of award and contracts is vested on the head of the infrastructure
department or its duly authorized representative. Under Sec. 9 (iii) of P.D. 857 which has
amended P.D. 505 that created the PPA, one of the particular powers and duties
of the General Manager and Assistant General Manager is to sign contracts.”[7] It went on to say that “in the case of the
PPA, the power to enter into contracts is not only vested on the Board of
Directors, but also to the manager” citing Section 9 (III) of P.D. No. 857.[8]
The trial court added that the tenor of the Notice of Award implied that
respondent’s general manager had been empowered by its Board of Directors to
bind respondent by contract. It noted that whereas the letter-reply contained
the phrase “approval of the higher authority,” the conspicuous absence of the
same in the Notice of Award supported the finding that the general manager had
been vested with authority to enter into the contract for and in behalf of
respondent. To the trial court, the
disapproval by the PPA Board of the supplementary contract for the reclamation
on a ground other than the general manager’s lack of authority was an explicit
recognition that the latter was so authorized to enter into the purported
contract.
Respondent moved for a reconsideration of the RTC decision but it was
denied for lack of merit. Respondent then filed its Notice of Appeal.
Subsequently, petitioner moved to dismiss the appeal on the ground that
respondent failed to perfect its appeal seasonably. On
Undaunted, respondent elevated its problem to this Court via a petition
for review on certiorari under Rule 45 assailing the denial of its appeal. On
On August 22, 2005, the CA rendered the assailed decision reversing the
trial court’s decision and dismissing petitioner’s complaint for specific
performance and damages. Thus, the
dispositive portion thereof reads:
WHEREFORE, premises
considered, the present appeal is hereby GRANTED. The appealed Decision dated
June 8, 1998 of the trial court in Civil Case No. 97-83916 is hereby REVERSED
and SET ASIDE. A new judgment is hereby entered DISMISSING the complaint for
specific performance and damages filed by Plaintiff Sargasso Construction and
Development Corporation/Pick & Shovel, Inc./Atlantic Erectors, Inc., (Joint
Venture) against the Philippine Ports Authority for lack of merit.
In setting aside the trial court’s decision, the CA ruled that the law
itself should serve as the basis of the general manager’s authority to bind
respondent corporation and, thus, the trial court erred in merely relying on
the wordings of the Notice of Award and the Minutes of the Board meeting in
determining the limits of his authority; that the power of the general manager
“to sign contracts” is different from the Board’s power “to make or enter
(into) contracts”; and that, in the execution of contracts, the general manager
only exercised a delegated power, in reference to which, evidence was wanting
that the PPA Board delegated to its general manager the authority to enter into
a supplementary contract for the reclamation project.
The CA also found the disapproval of the contract on a ground other than
the general manager’s lack of authority rather inconsequential because Executive
Order 380[12] expressly
authorized the governing boards of government-owned or controlled corporations
“to enter into negotiated infrastructure contracts involving… not more than
fifty million (P50 million).” The CA further noted that the Notice of
Award was only one of those documents that comprised the entire contract and,
therefore, did not in itself evidence the perfection of a contract.
Hence, this petition.
The issue to be resolved in this case is whether or not a
contract has been perfected between the parties which, in turn, depends on
whether or not the general manager of PPA is vested with authority to enter
into a contract for and on behalf of PPA.
The petition fails.
Petitioner contends that the existence of “Notice of Award of
Contract and Contractor’s Conforme thereto,” resulting from its negotiation
with respondent, proves that a contract has already been perfected, and that
the other documents enumerated under the amended Rules and Regulations[13]
implementing P.D. 1594[14] are
mere physical representations of the parties’ meeting of the minds; that the
“Approval of Award by Approving Authority” is only a “supporting document,” and
not an evidence of perfection of contract, and which merely “facilitates the
approval of the contract;”[15]
that PPA is bound by the acts of its general manager in issuing the Notice of
Award under the doctrine of apparent authority; and that the doctrine of estoppel, being an equitable doctrine, cannot
be invoked to perpetuate an injustice against petitioner.
At the outset, it must be stated that there are two (2)
separate and distinct, though related, projects involving the parties herein,
viz: (i) the construction of Pier 2 and the rock causeway for the
Every contract has the following essential elements: (i)
consent, (ii) object certain and (iii) cause. Consent has been defined as the
concurrence of the wills of the contracting parties with respect to the object
and cause which shall constitute the contract.[16]
In general, contracts undergo three distinct stages, to wit: negotiation,
perfection or birth, and consummation. Negotiation[17] begins
from the time the prospective contracting parties manifest their interest in
the contract and ends at the moment of their agreement. Perfection or
birth of the contract takes place when the parties agree upon the essential
elements of the contract, i.e., consent, object and price. Consummation
occurs when the parties fulfill or perform the terms agreed upon in the
contract, culminating in the extinguishment thereof. The birth or the
perfection of the contract, which is the crux of the present controversy, refers
to that moment in the life of a contract when there is finally a concurrence of
the wills of the contracting parties with respect to the object and the cause
of the contract.[18]
A government or public contract
has been defined as a contract entered into by state officers acting on behalf
of the state, and in which the entire people of the state are directly
interested. It relates wholly to matter of public concern, and affects private
rights only so far as the statute confers such rights when its provisions are
carried out by the officer to whom it is confided to perform.[19]
A government contract is essentially similar to a private
contract contemplated under the Civil Code. The legal requisites of consent of the contracting
parties, an object certain which is the subject matter, and cause or
consideration of the obligation must likewise concur. Otherwise, there is no
government contract to speak of.[20]
As correctly found by the CA, the issue
on the reclamation of the area between Timber Pier and Pier 2 of the
On the matter of entering into negotiated
contracts by government-owned and controlled corporations, the provisions of
existing laws are crystal clear in requiring the governing board’s approval
thereof. The Court holds that the CA correctly applied the pertinent laws, to
wit:
Executive
Order No. 380… provides for revised levels of authority on approval of
government contracts. Section 1 thereof authorizes… GOCCs:
1.
To enter into infrastructure contracts awarded through public bidding
regardless of the amount involved;
2.
To enter into negotiated infrastructure contracts involving not more
than one hundred million pesos (P100 million) in the case of the Department of
Transportation and Communications and the Department of Public Works and
Highways, and not more than fifty million pesos (P50 million) in the case
of the other Departments and governments corporations; Provided, That contracts exceeding the said amounts shall
only be entered into upon prior authority from the Office of the President; and
Provided, Further, That said contracts shall only be awarded in strict
compliance with Section 5 of Executive Order No. 164, S. of 1987.
xxx
The rule on negotiated contracts, as amended on
1. Negotiated contract may be entered into only
where any of the following conditions exists and the implementing
office/agency/corporation is not capable of undertaking the contract by
administration:
a.
In times of
emergencies arising from natural calamities where immediate action is necessary
to prevent imminent loss of life and/or property or to restore vital public
services, infrastructure and utilities such as…
b.
Failure to
award the contract after competitive public bidding for valid cause or causes
c.
Where the
subject project is adjacent or contiguous to an on-going project and it could
be economically prosecuted by the same contractor provided that subject
contract has similar or related scope of works and it is within the contracting
capacity of the contractor, in which case, direct negotiation may be undertaken
with the said contractor…
x x x
In cases a and b above,
bidding may be undertaken through sealed canvass of at least three (3)
qualified contractors… Authority to negotiate contract for projects
under these exceptional cases shall be subject to prior approval by heads of
agencies within their limits of approving authority.”[21]
(emphasis in the original)
Furthermore, the Revised
Administrative Code[22]
lays down the same requirement, thus:
Sec. 51. Who
May Execute Contracts. Contracts
in behalf of the Republic of the
Contracts in behalf of the political subdivisions and corporate agencies or instrumentalities shall be approved by their respective governing boards or councils and executed by their respective executive heads.
Petitioner neither disputes nor admits the application of the foregoing
statutory provisions but insists, nonetheless, that the Notice of Award itself
already embodies a perfected contract having passed the negotiation stage[23] despite
the clear absence thereon of a condition requiring the prior approval of
respondent’s higher authority.
Petitioner’s argument is untenable. Contracts to which the government is
a party are generally subject to the same laws and regulations which govern the
validity and sufficiency of contracts between private individuals.[24] A government contract, however, is perfected[25] only
upon approval by a competent authority, where such approval is required.[26]
The contracting officer
functions as agent of the Philippine government for the purpose of making the
contract. There arises then, in that regard, a principal-agent relationship
between the Government, on one hand, and the contracting official, on the
other. The latter though, in contemplation of law, possesses only actual
agency authority. This is to say that his contracting power exists, where
it exists at all, only because and by virtue of a law, or by authority
of law, creating and conferring it. And
it is well settled that he may make only such contracts as he is so
authorized to make. Flowing from these
basic guiding principles is another stating that the government is bound only
to the extent of the power it has actually given its officers-agents. It goes
without saying then that, conformably to a fundamental principle in agency, the
acts of such agents in entering into agreements or contracts beyond the scope
of their actual authority do not bind or obligate the Government. The moment
this happens, the principal-agent relationship between the Government and the
contracting officer ceases to exist.[27]
(emphasis supplied)
It was stressed that
…the contracting official
who gives his consent as to the subject matter and the consideration ought to
be empowered legally to bind the Government and that his actuations in a
particular contractual undertaking on behalf of the government come within the
ambit of his authority. On top of that, the approval of the contract by a
higher authority is usually required by law or administrative regulation as a
requisite for its perfection.[28]
Under Article 1881 of the Civil Code, the agent must act within the scope
of his authority to bind his principal. So long as the agent has authority,
express or implied, the principal is bound by the acts of the agent on his
behalf, whether or not the third person dealing with the agent believes that
the agent has actual authority.[29] Thus,
all signatories in a contract should be clothed with authority to bind the
parties they represent.
P.D. 857 likewise states that one of the corporate powers of respondent’s
Board of Directors is to “reclaim… any part of the lands vested in the
Authority.” It also “exercise[s] all the powers of a corporation under the
Corporation Law.” On the other hand, the law merely vests the general manager
the “general power… to sign contracts” and “to perform such other duties as the
Board may assign…” Therefore, unless respondent’s Board validly
authorizes its general manager, the latter cannot bind respondent PPA to a
contract.
The Court completely agrees with the CA that the petitioner failed to present
competent evidence to prove that the respondent’s general manager possessed
such actual authority delegated either by the Board of Directors, or by
statutory provision. The authority of government officials to represent the
government in any contract must proceed from an express provision of law or
valid delegation of authority.[30] Without
such actual authority being possessed by PPA’s general manager, there could be
no real consent, much less a perfected contract, to speak of.
It is of no moment if the phrase “approval of higher authority” appears
nowhere in the Notice of Award. It
neither justifies petitioner’s presumption that the required approval “had
already been granted” nor supports its conclusion that no other
condition (than the completion of fendering of Pier 2 as stated in the Notice
of Award) ought to be complied with to create a perfected contract.[31] Applicable
laws form part of, and are read into, the contract without need for any express
reference thereto;[32]
more so, to a purported government contract, which is imbued with public
interest.
Adopting the trial court’s
ratiocination, petitioner further argues that had it been true that
respondent’s general manager was without authority to bind respondent by
contract, then the former should have disapproved the supplemental contract on
that ground.[33] Petitioner
also interprets the Board’s silence on the matter as an explicit recognition of
the latter’s authority to enter into a negotiated contract involving the
reclamation project. This posture, however, does not conform with the basic
provisions of the law to which we always go back. Section 4 of P.D. 1594[34] provides:[35]
Section
4. Bidding. Construction
projects shall generally be undertaken by contract after competitive public
bidding. Projects may be undertaken by administration or force account or by
negotiated contract only in exceptional cases where
time is of the essence, or where there is lack of qualified bidders or
contractors, or where there is a conclusive evidence that greater economy and
efficiency would be achieved through this arrangement, and in accordance with
provision of laws and acts on the matter, subject to the approval of the
Ministry of Public Works, Transportation and Communications, the Minister of
Public Highways, or the Minister of Energy, as the case may be, if the project
cost is less than P1 Million, and of the President of the Philippines,
upon the recommendation of the Minister, if the project cost is P1
Million or more.
Precisely, the Board of Directors of the
respondent did not see fit to approve the contract by negotiation after finding
that “the Pier 2 Project was basically for the construction of a pier while the
supplemental agreement refers to reclamation. Thus, there is no basis to
compare the terms and conditions of the reclamation project with the original
contract (Pier 2 Project) of Sargasso.” So even granting arguendo that
the Board’s action or inaction is an “explicit” recognition of the authority of
the general manager, the purported contract cannot possibly be the basis of an
action for specific performance because the negotiated contract itself basically
contravenes stringent legal requirements aimed at protecting the interest of
the public. The bottom line here is that the facts do not conform to what the
law requires.
No wonder petitioner conveniently omitted any attempt at presenting its
case within the statutory exceptions, and insisted that respondent’s
disapproval of the supplemental agreement was “a mere afterthought” “perhaps realizing
the infirmity of its excuse” (referring to petitioner’s belated
pre-disqualification in the construction project). But the Court, at the very
outset, has previously clarified that the two projects involved herein are
distinct from each other. Hence, petitioner’s
disqualification in the construction project due to its lack of certain
requirements has no significant bearing in this case.
Lastly, petitioner’s invocation of the doctrine of apparent authority[36]
is misplaced. This doctrine, in the realm of government contracts, has been
restated to mean that the government is NOT bound by unauthorized acts of its
agents, even though within the apparent scope of their authority.[37] Under
the law on agency, however, “apparent authority” is defined as the power to
affect the legal relations of another person by transactions with third persons
arising from the other’s manifestations to such third person[38]
such that the liability of the principal for the acts and contracts of his
agent extends to those
which are within the apparent scope of the authority conferred on him, although no actual authority to do such acts
or to make such contracts has been conferred.[39]
Apparent authority, or what is sometimes referred to as the “holding out”
theory, or doctrine of ostensible agency, imposes liability, not
as the result of the reality of a contractual relationship, but rather
because of the actions of a principal or an employer in somehow misleading the
public into believing that the relationship or the authority
exists.[40] The existence of apparent authority may be ascertained
through (1) the general manner in which the corporation holds out an officer or agent as having the power to act or, in other words, the apparent authority to act in general,
with which it clothes him; or (2) the acquiescence in his acts of a particular
nature, with actual or constructive knowledge thereof, whether within or beyond
the scope of his ordinary powers. It requires presentation of evidence of
similar act(s) executed either in its favor or in favor of other parties.[41]
Easily discernible from the foregoing is that apparent
authority is determined only by the acts of the principal and not by the acts
of the agent. The principal is, therefore, not responsible where the agent’s
own conduct and statements have created the apparent authority.[42]
In this case, not a single act of respondent, acting through
its Board of Directors, was cited as having clothed its general manager with
apparent authority to execute the contract with it.
With the foregoing disquisition, the Court finds it unnecessary to
discuss the other arguments posed by petitioner.
WHEREFORE, the petition is
DENIED.
SO ORDERED.
JOSE
CATRAL
Associate Justice
WE CONCUR:
ANTONIO T. CARPIO
Associate Justice
Chairperson
ANTONIO EDUARDO B. NACHURA DIOSDADO M. PERALTA
Associate Justice Associate Justice
ROBERTO A.
ABAD
Associate Justice
A T T E S T A T I O N
I attest that the conclusions in the
above Decision had been reached in consultation before the case was assigned to
the writer of the opinion of the Court’s Division.
ANTONIO T.
CARPIO
Associate Justice
Chairperson, Second Division
C E R T I F I C A T I O N
Pursuant to Section 13, Article VIII of
the Constitution and the Division Chairperson’s Attestation, I certify that the
conclusions in the above Decision had been reached in consultation before the
case was assigned to the writer of the opinion of the Court’s Division.
RENATO C. CORONA
Chief Justice
[1] Penned by Associate Justice Martin S. Villarama, Jr., (now a member of this Court) with Associate Justice Bienvenido L. Reyes and Associate Justice Lucenito N. Tagle concurring.
[2] Rollo, p. 30.
[3] Penned by Judge Inocencio D. Maliaman.
[4] Rollo, pp. 11-29.
[5] Emphasis in the original.
[6] Decision of the Trial Court, rollo, pp. 158-167.
[7]
[8] Providing
for the Reorganization of Port Administrative and Operation Functions in the
Section 9.
General Powers and Duties of the General Manager and Assistant General Managers
a) General Powers and Duties of the General Manager. —
The General Manager shall be responsible to the Board, and shall have the
following general powers, functions, and duties: xxx
(iii) To sign contracts, to approve expenditures and payments within the budget provisions, and generally to do any all acts or things for the proper operations of the Authority or any of the Ports under the jurisdiction, control or ownership of the Authority.
[9] Rollo, pp. 268-271.
[10]
[11] Philippine Ports Authority v. Sargasso Construction and Development Corp., Pick & Shovel, Inc./ Atlantic Erectors, Inc. (Joint Venture), G.R. No. 146478, July 30, 2004, 435 SCRA 512.
[12] Revising
the Levels of Authority on Approval of Government Contracts (1989).
[13] IB [2.10] 2.8 Documents Comprising The Contract
The following documents shall form part of the contract:
1. Contract Agreement
2. Conditions of Contract
3. Drawings/Plans
4. Specifications
5. Invitations to Bid
6. Instructions to Bidders
7. Addenda
8. Bid Form including the following Annexes:
a. Authority of the Signing Official
b. Bid Prices in the Bill of Quantities
c. Detailed Estimates
d. Construction Schedule
e. Construction Methods
f. Project Organizational Chart
g. Manpower Schedule
h. Equipment Utilization Schedule
i. Cash Flow and Payments Schedule
j. [Certification] AFFIDAVIT of Site Inspection
9. Performance Bond
10. Prequalification [and Post qualification Statements]
11. Certificate of Cash Deposit for Operating Expenses (IF NECESSARY)
12. Notice of Award of Contract and Contractor’s “Conforme” thereto
13. Other Contract Documents that may be required by the Office/Agency/Corporation concerned
[14] Prescribing
Policies, Guidelines, Rules and Regulations for Government Infrastructure
Contracts (1978).
[15] IB [2.11] 2.9 Supporting Documents
To facilitate the approval of the contract, the following supporting documents shall be submitted:
1. xxx
6. Approval of Award by Approving Authority
xxx
[16] Jurado. Desiderio P., Comments and Jurisprudence on Obligations and Contracts, 1993, Tenth Revised Edition, p. 396; citing 3 Castan, 7th Ed., pp. 326-327, 8 Manresa, 5th Ed., Bk. P. 365, and Sanchez Roman 191.
[17] A negotiation is formally initiated by an offer
which should be certain with respect to both the object and the cause or
consideration of the envisioned contract. In order to produce a contract, there
must be acceptance, which may be express or implied, but it must not
qualify the terms of the offer. The acceptance of an offer must be unqualified
and absolute to perfect the contract. In other words, it must be identical in
all respects with that of the offer so as to produce consent or meeting of the
minds.
[18] Supra note 16 at 390.
[19] Cobacha, Agapito P. and Lucenario, Domingo O, Law on Public Bidding and Government Contracts, 1960, p. 283, citing People v. Palmer, 35 N.Y.S. 222, 14 Misc. 41.
[20] Fernandez, Jr., Bartolome C., A Treatise on Government Contracts under Philippine Law, 2003 Revised Edition, p. 10.
[21] Decision of the Court of Appeals, pp. 14,16-17; rollo, pp. 86, 88-89.
[22] Chapter II Book I Section 51.
[23] Memorandum for the Petitioner, p. 20; rollo, p. 401.
[24] Manual on Contracts Review, March 1997, p. 14.
[25] The Court in Central Bank of the
[26] Supra note 19.
[27] Supra note 20 at 8.
[28]
[29] De
[30] Manual on Contracts Review, March 1997, p. 25.
[31] Memorandum for Petitioner, p. 24; rollo, p. 405.
[32] Intra-Strata Assurance Corp. and Philippine Home Assurance Corp. v. Republic, G.R. No. 156571, July 9, 2008, 557 SCRA 363.
[33] Memorandum for the Petitioner, p. 29; rollo, pp. 410-412.
[34] Now expressly repealed by R.A. 9184 (An Act Providing for the Modernization, Standardization and Regulation of the Procurement Activities of the Government and for Other Purposes) otherwise known as Government Procurement Reform Act of 2003.
[35] Cited in the Decision of the Court of Appeals.
[36] Memorandum for Petitioner, p. 32, citing the case of First Phil. International Bank v. Court of Appeals, 252 SCRA 259,295; rollo, p. 413.
[37] Supra note 19 at 294-295.
[38] 3 Am. Jur. 2d § 79.
[39] 2 Am. Jur. 82.
[40] Professional Services, Inc. v.
[41] People’s
Aircargo and Warehousing Co., Inc. v. CA, 357
Phil. 850 (1998).
[42] 3 Am. Jur. 2d § 79.