Republic of the
Supreme Court
FIRST DIVISION
ADRIAN WILSON INTERNATIONAL ASSOCIATES, INC., |
|
G.R.
No. 162608 |
Petitioner, |
|
Present: |
|
|
|
|
|
|
|
|
VELASCO,
JR., |
- versus - |
|
LEONARDO-DE
CASTRO, |
|
|
|
|
|
PEREZ,
JJ. |
|
|
|
TMX PHILIPPINES, INC., |
|
Promulgated: |
Respondent. |
|
July
26, 2010 |
x - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - x
D E C I S I O N
A claimant is entitled to be compensated reasonably and commensurately
for what he or she has lost as a result of another’s act or omission, and the
amount of damages to be awarded shall be equivalent to what have been pleaded
and adequately proven. Should the
claimant fail to prove with exactitude the extent of injury he or she sustained,
the court will still allow redress if it finds that the claimant has suffered
due to another’s fault.
In this petition for review on certiorari,
petitioner Adrian Wilson International Associates, Inc. (AWIA) assails the Decision[1]
of the Court of Appeals (CA) dated August 14, 2003 in CA-G.R. CV No. 49272
which affirmed with modification the Decision[2]
of the Regional Trial Court (RTC) of Makati City, Branch 150 by further
ordering AWIA to pay to respondent TMX Philippines, Inc. (TMX) the amount of P1,546,084.00
representing the reimbursement of salaries of TMX’s employees. AWIA now pleads that we reinstate the RTC Decision
or reduce the amount of actual damages representing the reimbursement of the
salaries of the TMX employees.
Factual
Antecedents
TMX engaged the services of AWIA for
the construction of its watch assembly plant located in the EPZA[3]-run
Mactan Export Processing Zone in
Specifically, one
of AWIA’s duties was construction administration, i.e., to guard TMX
from defects and deficiencies during the construction phase by determining the
progress and quality of the work of the general contractor, P.G. Dakay
Construction Company (P.G. Dakay). This
is to ensure that this contractor works in accordance with the directed
specifications.
Construction began in 1979 and was
completed in 1980. After five years, however,
TMX noticed numerous cracks and beam deflections (vertical shifting)[6]
along the roof girders and beams in columns B, C, F, and G of the twin modules. TMX, opining that the problem may have been
due to design errors, informed AWIA of the situation.
In its report dated
correct and that
the building was not in danger of collapsing.
AWIA attributed
the existing cracks along column line G to the marginal strength of the
concrete that was poured during a heavy rainfall on
TMX also sought the
opinion of two architectural consultancy firms, the Fletcher-Thompson, Inc. (Fletcher-Thompson)
and C.N. Ramientos and Associates. Both
concluded that the cracks and displacements of the roof’s structural system
were due to AWIA’s errors in the design calculations and in the factoring of
live and dead load and concrete strengths.[9]
Similar to the suggestion
of AWIA, Fletcher-Thompson recommended the installation of lally columns. Thus, as preventive and corrective measure, TMX
shored up the beams and girders with 118 steel lally columns in all the
buildings’ modules.
The major
construction work was done in December 1985, during which TMX was forced to
stop its operations from P3,931,583.00,[10]
i.e.,
P2,385,499.00 for shoring expenses,[11]
and P1,546,084.00, representing wages of its employees for the period
Laying the blame on AWIA for the roof
defects, TMX sought reimbursement of everything it had spent for the corrective
work by suing AWIA for damages before the RTC of Makati. The case was docketed as Civil Case No. 16587
and raffled to Branch 150.[13]
In its Answer,
AWIA insisted on the correctness of its design and that the same was approved
by TMX. It stressed that it faithfully
complied with its obligation of administering the construction contract and was
not responsible for whatever mistakes the contractor made. According to AWIA, TMX has its own staff who
supervised the construction and to whom AWIA’s inspectors submitted their
reports. Conversely, AWIA blamed TMX for
the cracks, alleging that the latter’s supervising staff ignored the
Ruling of the Regional Trial Court
After weighing
the evidence submitted by the parties, the trial court noted that TMX apparently
was satisfied with AWIA’s services because after the completion of the Mactan
assembly plant in 1980, TMX rehired AWIA four years later for the design of two
more separate extensions of the building.
All of AWIA’s documents, designs, drawings, plans and specifications of
the building were subject to TMX and its parent company’s approval, which both
relayed their comments and instructions to AWIA. During the construction phase, TMX had its
own engineering team which actively participated in the project. The trial court concluded that AWIA complied
faithfully with its obligations in all phases indicated in the Agreement.[16]
The court a
quo found that only 11 shoring columns on the roof girders were necessary
to remedy the cracks and deflections in lines B and G, and thus reduced the
shoring expenses AWIA incurred on a pro-rate basis. It was also noted that the defects were not
solely attributable to AWIA, because TMX ignored Engr. Lacanilao’s
This Court finds that there was no necessity at
all for plaintiff TMX to have installed 118 shoring columns all over its
building. Except for the bare allegation
of TMX president Rogelio Lim that this was done upon the recommendation of
Engr. Ramientos and its U.S.-based consultant Fletcher-Thompson, plaintiff has
not shown that it was necessary to put up more than one hundred columns at all
beam intersections with sophisticated designs using expensive materials. Admittedly, cracks and deflections appeared
in some beams and roof girders after five (5) years from the building’s
completion. The subject building or any
part thereof has not collapsed nor has ever fallen down. As a matter of fact, it was plaintiff’s own
consultant Fletcher-Thompson in its Beam Deflection Check (Exhibits “5” to
“5-J”) who recommended the installation of eleven (11) shoring columns on the
roof girders which had failures (T.S.N., July 3, 1990, pp. 27-34). Even plaintiff’s complaint mentions cracks
and deflections only on column lines B and G.
To allow plaintiff reimbursement for putting up 118 columns all over the
building would unduly favor plaintiff TMX.
Only eleven (11) columns would have been necessary to correct the
crackings and deflections in column lines B and G. Any excess of that would be considered as a
renovation or added improvement of which the defendant should not be made to
shoulder.
Thus, the defendant should reimburse TMX only for
eleven (11) shoring columns as its just and equitable share in the expenses
incurred by plaintiff. Taking the ratio
of 11 and 118 columns and applying the same to the total amount of P2,385,499.00,
the expenses for installing 11 columns would be P222,377.00.
As regards the claim for reimbursement of P1,546,084.00
representing the salaries and wages that plaintiff allegedly paid its employees
during the work stoppage from
As testified by defendant’s witness, Engineer
Labrador, it was agreed that the 11 shoring columns will be put up late
December since admittedly the last two (2) weeks of December up to the first
week of January was plaintiff’s scheduled production shutdown as its employees
usually go on vacation during those days.
Moreover, it is observed that plaintiff failed to present during the
hearing of this case the pertinent payroll documents to substantiate its
claim. What it produced were only
computer printouts of the salaries allegedly paid to its employees for the
period in question.
x x x x[17]
The dispositive portion of the trial court’s Decision
reads:
WHEREFORE, the Court
hereby renders judgment as follows:
1. Defendant is ordered to pay plaintiff TMX the amount of P222,377.00
as compensatory damages;
2. Defendant is ordered to pay P80,000.00 to plaintiff TMX as
attorney’s fees and litigation expenses;
3. The complaint of plaintiff EPZA against
defendant is DISMISSED.
4.
The
counterclaim of defendant is DISMISSED.
SO ORDERED.[18]
Both parties
appealed to the CA but AWIA later withdrew its appeal leaving TMX to contest
the judgment of the trial court.
Ruling of the Court of Appeals
The CA agreed with the RTC that AWIA is responsible for the payment of only
11 shoring columns. However, the CA
differed as to the RTC’s finding that AWIA completely abided by its
obligations. To the CA, AWIA failed to
promptly and adequately notify its principal of the quality and progress of the
work, including the defects and deficiencies in the construction and a
determination of how these will be rectified by the contractor. It said:
To excuse AWIA from any liability for the
contractor’s failure to carry out the work in accordance with the contract
documents, it is required, under their Agreement, to “have kept the OWNER
currently and adequately informed in
writing of the progress and quality of the work.” In the case at bar, We hold that the written
report given by AWIA to TMX of the incident could not be the proper notice
contemplated in the Agreement. Notably,
the report merely contains statements and account of events that transpired
during such pouring operations. It did
not contain any warning or recommendation as to put TMX on notice that
something has to be done. Nor did it
inform TMX that said incident threatened the strength of concrete or structural
integrity of the roof. For this, AWIA is
liable. x x x[19]
The CA further modified the RTC’s
Decision by ordering AWIA to reimburse TMX the amount of P1,546,084.00 representing
the salaries TMX had paid to its employees during the involuntary work stoppage. The appellate court found the check vouchers
and financial schedule of payments as sufficient proofs.
Issues
Hence, AWIA filed this Petition for Review
on Certiorari,[20]
raising the following issues: a) whether AWIA properly discharged its duty as
construction administrator and b) whether there is a valid basis for the
reimbursement of the salaries paid to the employees of TMX.
Petitioner’s Arguments
AWIA’s arguments
are summed up as follows:
a)
It complied with its obligation to keep TMX adequately
informed about the progress and quality of the work of the contractor. Engr. Lacanilao, AWIA’s site representative,
even delayed the pouring of the concrete and rejected the concrete that had
been mixed for more than 45 minutes during the
b)
Assuming that AWIA failed to keep TMX adequately informed
of the ill-effects of the
Moreover, AWIA contends that TMX
failed to prove its claim of payment of alleged salaries during the shutdown
period because the pieces of evidence it presented are mere summaries of
salaries paid and vouchers for checks deposited in a bank for the alleged
salaries. There are no proofs that TMX
employees actually received their salaries during said shutdown period. And even if it could be held responsible for
reimbursing the employees’ salaries, AWIA claims that it should not be held
liable for the TMX employees’ salaries during the entire period of
installation. Had only 11 columns been installed,
the period of shutdown due to remedial work would have been shorter. AWIA thus asks for a reduction of the award,
computed at a formula used by the trial court as basis for awarding TMX the
cost of installing only 11 columns.
Hence, the salary should be computed at 11/118 of P1,546,084.00,
or P144,210.37.
Respondent’s
Arguments
On the other hand, TMX maintains
that:
a)
AWIA can no longer challenge the finding of the RTC and
the CA of its liability. The fact that
the trial court ordered the payment of the costs of the 11 columns is an
implicit recognition that AWIA was responsible for the roof damage. AWIA did not appeal this judgment and thus
this decision had become final and executory.
At most, AWIA can only challenge the CA Decision insofar as the
additional award of reimbursement of the employees’ salaries is concerned.
b)
The CA was correct in its finding that AWIA breached the
Agreement. The report of Engr. Lacanilao had misled TMX
into believing that no problem existed and that nothing was to be rectified
when it was AWIA’s duty under the Agreement to notify and promptly alert TMX of
remedial measures that must be taken when there are defects in the work of the
contractor.
c)
The breach warrants a full reimbursement of salaries TMX
claims. AWIA cannot use as defense the
adequacy of Engr. Lacanilao’s report when this contradicts its own answer to
the complaint, stating therein that the cause of the roof failure was the
“marginal strength of the concrete during a rainfall.” The construction and repair of certain
portions of the roof system forced TMX to undergo work stoppage and pay its
employees wages during the repair period, the ultimate cause of which was AWIA’s
failure to warn TMX of the possible consequences of the
TMX also contends that it was
baseless and speculative for AWIA to assume that the time necessary to install
11 columns would not require a period of two weeks, considering that the
construction work for installing permanent shoring columns was disruptive. Certain factors, such as pre-installation
activities (e.g. careful individual packing of hundreds of TMX’s
sensitive equipment and materials necessary for watch-making and the
painstaking excavation of areas where the new columns were to be attached,
which may take long depending on the difficulty and the location), and faster
pace of work as time progresses, should be taken into account. Nonetheless, for TMX, AWIA’s proposed
computation of 11/118 multiplied by the amount of salaries claimed was
erroneous, because AWIA assumed that all the 118 columns had been installed
from P1,546,084.00,
or P288,253.00.
Our Ruling
AWIA failed in its duty to guard TMX against the contractor’s work
deficiencies
AWIA
persistently faults TMX for its alleged neglect of Engr. Lacanilao’s
report. But according to the parties’ Agreement,
the duty of alerting TMX of the problems in the construction of the building behooves
entirely on AWIA. The following
provisions in the
CONSTRUCTION PHASE – ADMINISTRATION OF THE
CONSTRUCTION CONTRACT
x
x x x
1.1.14. The CONSULTANT, shall make periodic and
regular visits to the site to determine the progress and quality of the Work
and to determine if the Work is proceeding in accordance with the Contract
Documents. On the basis of his on-site
observations as a CONSULTANT, he shall guard the owner against, and shall promptly notify the OWNER in writing
of, defects and deficiencies in the Work of the Contractor and non-compliance
with the Contract Documents. The
CONSULTANT shall be required to make such on-site inspections as may be
reasonably determined by the OWNER to be necessary. Provided that the CONSULTANT shall have kept
the OWNER currently and adequately informed in writing of the progress and
quality of the work, the CONSULTANT shall not be responsible for construction
means, methods, techniques, sequences or procedures, or for safety precautions
in connection with the Work, and he shall not be responsible for the
Contractor’s failure to carry out the Work in accordance with the Contract
Documents.
1.1.15 Based on such observations at the site and on
the Contractor’s Applications for Payment, the CONSULTANT shall determine the
amount owing to the Contractor and shall issue Certificates for Payment in such
amounts. The issuance of a Certificate
for Payment shall constitute a representation by the CONSULTANT to the OWNER,
based on the CONSULTANT’s observations at the site as provided in Subparagraph
1.1.14 and on the data comprising the Application for Payment, that the Work
has progressed to the point indicated; that to the best of the CONSULTANT’s
knowledge, information and belief, the quality of the Work is in accordance
with the Contract Documents (subject to an evaluation of the Work for
conformance with the Contract Documents upon Substantial Completion to the
results of any subsequent tests required by the Contract Documents, to minor
deviations from the Contract Documents correctable prior to completion, and to
any specific qualifications stated in the Certificate for Payment); and that
the Contractor is entitled to payment in the amount certified. By issuing a Certificate for Payment, the
CONSULTANT shall not be deemed to represent that he has made any examination to
ascertain how and for what purpose the Contractor has used the moneys paid on
account of the Contract Sum.
1.1.16 The CONSULTANT shall be, in the first
instance, the interpreter of the requirements of the Contract Documents and the
impartial judge of the performance thereunder by the Contractor. The CONSULTANT shall make decisions on all
claims of the Contractor relating to the execution and progress of the Work and
all other matters or questions related thereto.
1.1.17 The CONSULTANT shall have authority to reject
Work which does not conform to the Contract Documents. Whenever, in his reasonable opinion, he
considers it necessary or advisable to insure the proper implementation of the
intent of the Contract Documents, he will have authority, with the OWNER’s
approval, to require special inspection or testing of any Work in accordance
with the provisions of the Contract Documents whether or not such Work be then
fabricated, installed or completed.
x
x x x
1.1.20
The CONSULTANT shall conduct
inspections to determine the Dates of Substantial Completion and final completion,
shall receive and review written guarantees and related documents assembled by
the Contractor, and shall issue a final Certificate for Payment. The CONSULTANT shall use its best efforts to
enforce warranties and guarantees furnished by the Contractor or by suppliers
of materials or equipment to the extent of assisting OWNER in any arbitration
or court action if necessary.
1.1.21 The CONSULTANT
shall not be responsible for the acts or omissions of the Contractor, or any
Subcontractors, or any of the Contractor’s or Subcontractor’s agents or
employees, or any other persons performing any of the Work but will promptly
inform OWNER thereof in writing and determine how such acts or omissions will
be rectified by the Contractor prior to issuing a final Certificate of Payment.
x
x x x[21]
As can be
inferred from the contract, TMX could solely and absolutely rely on the
assessments and recommendations of AWIA.
Under the aforementioned provisions, AWIA was tasked to guard TMX
against construction problems and to ensure the quality of P.G. Dakay’s
performance. It also had the authority
to approve or reject the contractor’s work, and it could issue certificates of
payments for the progress billings of the contractor only if it found the
latter’s job as covered by each of the billings satisfactory. Thus, it is irrelevant whether TMX has its
own engineering staff to evaluate the reports about the construction work. Taking together Sections 1.1.14 and 1.1.21, AWIA
is not liable for the contractor’s construction errors on the following
conditions: a) that it promptly and adequately informs TMX of whatever defects
and deficiencies in the construction are and b) that it determines how these
problems could be repaired. AWIA should
not release a final certification of payment in favor of the contractor unless
these had been done.
The
TO MR. ROGELIO Q. LIM
FROM GAVINO S. LACANILAO
DATE
TMXP 2, General Manager TMXP
2, Project Inspector
SUBJECT HEAVY RAINS DURING THE POURING
Last night at 22:45 hours while we were
continuously pouring (Monolythic Concreting) on lines F and G of Bays 11 to 16
Section C of Main Building a signal for heavy rains coming was noted, so all
the personnel involved in the pouring covered the newly poured concrete with
polyethylene (Plastic) sheets to protect from the rain. When the rain started the newly poured
concrete were protected.
During the heavy rain the pouring was temporarily
suspended. Since I was the only one who
has a rain coat, I inspected the whole top area and found out that rain water
accumulated which was approximately thirteen (13) inches deep, because the
water line was just below one (1) inch of my rubber boots.
So I removed all the temporary plugs of the C.I.
downspouts to prevent accumulated rain water from destruction, and that was the
only time that the water dispersed little by little.
When the rain stopped, Engineers Ramon Aseniero
and E. Gahi told me that they will continue the pouring. I advised that they must first remove the
water on top of both the plastic sheets and the newly poured concrete so that
the concrete to be poured will not be diluted.
While men working between bays 15 and 16 were busy
applying air pressure on the surface of the fresh concrete with water and the
forms to be poured, I suddenly saw the contents in the bucket of one of the
overhead cranes was about to be poured out on the newly poured concrete. So I ran and told Engr. E. Gahi why he is
already pouring the concrete in the bucket while the rain water is still
there? And Engr. Gahi told me that he
was just following the order of Mr. John Y. Lim who just arrived and without
assessing the situation and asking my decision being the inspector of the
project.
So I approached Mr. Lim and asked him why he gave
the order of pouring the concrete? He
told me right away and pointing at the stopped poured concrete is already
sitting. So I told him that if he
continue [sic] pouring the concrete, I will go out of the construction site or
I will not certify the said area. That
was the time our argument stopped.
The following are my reasons why I delay the
pouring:
*The poured concrete before the rain was with
standing water.
*All the forms to be concreted were covered with
water.
Note: If they will pour concrete on the above
reasons, the mixed concrete will be diluted too much with water that it will
lessen the strength of the roofing slab.
*They were pouring the concrete without first
applying grout to act as binder on the surface of the washed concrete.
*They [sic] concrete they were trying to pour was
already more than 45 minutes in the mixer, because the rain stopped at
Specification manual page 02800-6 Section 1.04.04 truck mixing second to the
last paragraph says:
“Concrete not in place within 45 minutes from the
time the ingredients were charged into the mixing drum or that has developed
initial sitting should not be used.
No exemption. So I rejected the two (2) batches.”
Respectfully,
(Signed) G.S. LACANILAO
TMXP 2, Project Inspector
The subject
report is merely a narration of what Engr. Lacanilao had done and the
justifications why he delayed the pouring of concrete and why he rejected two
batches of concrete mix. Engr. Lacanilao
explained that P.G. Dakay’s representative did not proceed with the pouring of
the substandard concrete mix, after he was informed that he (Engr. Lacanilao) would
not certify the area. TMX then was led
to believe that this incident was no cause for alarm since apparently, Engr.
Lacanilao had prevented a possible problem.
The report did not in any way warn TMX that the quality of the roof may
be in jeopardy and that it had to be rectified.
AWIA even approved all of P.G. Dakay’s progress billings and issued a
final certification of payment, an assurance that it found no problems at all
with the construction work. Ironically
though, when the cracks and deflections in certain sections of the roof had
appeared, AWIA cited the marginal strength of the concrete as a result of the
AWIA’s failure
to adequately inform TMX of the possible implications of the contractor’s
mistake in the concrete pouring was a crucial factor that had cost the former
to spend for the repairs.
AWIA breached its responsibility to inform TMX of the contractor’s
mistake. TMX may demand for damages duly proven as a natural consequence of the
roof failures it has suffered. If the
amount it claims cannot be proven with certainty, temperate damages may be
awarded instead.
In contracts and
quasi-contracts, the damages for which the obligor who acted in good faith is
liable shall be those that are the ‘natural and probable consequences of the
breach of the obligation’.[23]
Both the trial
court and the CA held AWIA liable for the cost of 11 shoring columns. AWIA no longer challenged this ruling when it
withdrew its appeal to the appellate court, rendering the judgment final and
executory.[24] We also found that AWIA had breached its duty
of contract administration. Had the
effects on the marginal strength of the concrete been promptly disclosed to
TMX, the cracks and deflections could have been rectified by the contractor
before it was issued its final certification of payment and the owner could
have been spared from further expenses. There
is a causal connection between AWIA’s negligence and the expenses incurred by TMX. The latter was compelled to shutdown the
plant during the workdays in December to repair the roof. In the process, it incurred expenses for the
repairs, including the salaries of its workers who were put on forced leave,
for which it can ask for reimbursement as actual damages.
Actual damages puts the claimant in the position in which he
had been before he was injured.
The award thereof must be based on the evidence presented, not on the
personal knowledge of the court; and certainly not on flimsy, remote,
speculative and nonsubstantial proof.[25] Under the Civil Code, one is entitled to an adequate compensation only for such pecuniary loss
suffered by him as he has duly proved.[26]
After an exhaustive perusal of the records
pertaining to the claim of the salaries covering December 1-18, 1985 allegedly paid to TMX employees, we find that TMX’s pieces
of evidence do not substantiate such plea for the full reimbursement of the
salaries. To prove that salaries have
been paid, TMX has the burden to show that payments have actually been made to
its employees. However, the documents it
submitted were composed only of a master list of daily and monthly paid
employees, summarized and itemized lists and computations of payroll costs
during the covered period of shoring installation, salary structures, and
vouchers prepared by the accounting department.
These pieces of evidence, as well as the bare assertion of the TMX
President, do not show a reasonable degree of certainty of actual payment to
and actual receipt by its workers but only reflect the list of
disbursements. No other witnesses who
could corroborate the actual payment of the salaries of the employees during
the shutdown period were presented.
Vouchers are not receipts. A
receipt is a written and signed acknowledgment that money has been received or
goods have been delivered, while a voucher is documentary record of a
business transaction.[27] Hence, the RTC correctly preferred the payroll documents (which contain the
signatures of employees), implying that these are the primary/best evidence of
payment, or “that which [afford] the greatest certainty of the fact in
question”.[28]
While TMX failed to prove the exact amount of the salaries it had paid,
we however acknowledge that TMX had to pay its employees during the shutdown
and had suffered pecuniary loss for the structural problem. Moreover, we concede to AWIA’s stance that
the installation of only 11 shoring columns, instead of 118, would
significantly reduce the number of days allotted for the repairs. As a matter of equity, therefore, a relief to
TMX in the form of temperate damages[29] is warranted. We find the amount of P500,000.00
reasonable and sufficient under the circumstances.
WHEREFORE, the instant petition is PARTIALLY GRANTED. The Decision of the Court of Appeals in CA-G.R.
CV No. 49272 is AFFIRMED with the MODIFICATION that the award of
P1,546,084.00 as part of actual damages is deleted, and in lieu thereof,
temperate damages amounting to P500,000.00 are awarded. Costs against AWIA.
SO ORDERED.
MARIANO
C.
Associate
Justice
WE
CONCUR:
RENATO C. CORONA
Chief Justice
Chairperson
PRESBITERO J. VELASCO, JR. Associate
Justice |
TERESITA J. LEONARDO-DE
CASTRO Associate
Justice |
JOSE
Associate Justice
C E R T I F I C A T I O N
Pursuant
to Section 13, Article VIII of the Constitution, it is hereby certified that
the conclusions in the above Decision had been reached in consultation before
the case was assigned to the writer of the opinion of the Court’s Division.
RENATO
C. CORONA
Chief Justice
[1] Rollo, pp. 7-25; penned by Associate Justice Ruben T. Reyes and concurred in by Associate Justices Jose L. Sabio, Jr. and Hakim S. Abdulwahid.
[2]
[3] EPZA stands for Export Processing Zone Authority.
[4] Two of the buildings, called ‘twin modules,’ are of the same design for watch assembly and office spaces, while the other one is differently designed to be used as a warehouse.
[5] Rollo, pp. 84-100.
[6]
[7]
[8] Records, pp. 499-500.
[9] RTC Exhibits, pp. 44-47 and Records, pp. 181-182. Fletcher-Thompson, Inc. enumerated the following errors:
A. Superimposed dead load used in the calculations was less than that actually imposed on the structure.
B. Load distribution from roof beams to roof girders was erroneously assumed to be a uniform loading in lieu of a correct concentrated load distribution.
C. Load redistribution caused by stiffness variations in the structural system was not accounted for.
D. Allowable stresses were calculated assuming the concrete would attain a compressive strength of 5,000 psi in 28 days whereas the project specifications call for a strength attainment of 4,000 psi in 28 days.
E. A live load of 20 psi, as used in the calculations, is not consistent with the drainage system. This live load assumption would be valid only if the roof drainage system would limit rainwater accumulations to 3.85 inches. x x x
On the other hand, Engr. Capistrano Ramientos of C.N. Ramientos and Associates enumerated the following errors:
1. A. Wilson’s structural engineers failed to factor in all live and deadloads in their computations/designs which A. Wilson’s own architects, mechanical and electrical engineers had designed into the three buildings. This resulted in A. Wilson’s structural designs/computations being engineered for load of 95 lbs/square foot, which is 23.70% lower than the correct/actual load of 117.50 per lb/square foot.
2. A. Wilson made a mistake in assuming the loads to be distributed uniformly throughout the length of girders when, in fact, the loads were actually a combination of concentrated and distributed loads in the girders. This resulted in A. Wilson’s underestimating the girder’s bending moment by 14.38% or fully 95,546 lbs-foot.
3. A. Wilson forgot to take into account the effect of rib-shortening due to post-tensioning of beams and girders. This resulted in A. Wilson mistakenly believing that no additional loads/stress had to be considered in its design, when actually there was an incremental load/stress resulting from rib-shortening of no less than an additional 47,828 lbs load/stress on each Beam-Girder intersection of the ridge girders (lines B and G).
The combined effect of errors 1 to 3 above resulted in A. Wilson underestimating the actual total load in each of the ridge girders (lines B and G) of the 3 buildings by 97.6%. This resulted in A. Wilson mistakenly designing girders for a maximum bending moment or load of only 664,044 foot-pounds when the actual bending moment or load is 1,312,360 foot pounds, 97.6% more (or almost 100% or double) A. Wilson’s computation.
A. Wilson failed to considered [sic] that
5,000 psi concrete strength is not normally achievable in Cebu using
x x x x
[10] Exhibit “H”, folder of exhibits, p. 88.
[11] Folder of exhibits, pp. 89-391.
[12]
[13] EPZA was a co-plaintiff in the case, but for lack of cause of action, the court eventually dismissed its complaint against AWIA.
[14] Rollo, pp. 129-130.
[15] Records, pp. 504-515.
[16] The December 29, 1978 Agreement specified the duties of AWIA during the Schematic Design Phase, the Design Development Phase, the Construction Documents Phase, the Bidding or Negotiation Phase, and the Construction Phase-Administration of the Construction Contract.
[17] Rollo, p. 127.
[18]
[19]
[20] TMX likewise elevated the case before us,
docketed as G.R. No. 159580, but we denied its petition on
[21] Rollo, pp. 87-89.
[22] Records, pp. 504-515.
[23] Civil Code, Article 2201. In contracts and quasi-contracts, the damages for which the obligor who acted in good faith is liable shall be those that are the natural and probable consequences of the breach of the obligation, and which the parties have foreseen or could have reasonably foreseen at the time the obligation was constituted.
[24] Development Bank of the
[25] Spouses Ong v. Court of Appeals, 361 Phil. 338, 353 (1999).
[26] Civil Code, Art. 2199. Except as provided by law or by stipulation, one is entitled to an adequate compensation only for such pecuniary loss suffered by him as he has duly proved. Such compensation is referred to as actual or compensatory damages.
[27] Towne and City Development Corporation v. Court of Appeals, 478 Phil. 466, 475 (2004).
[28] Philippine National Bank v. Court of Appeals, 326 Phil. 326, 337 (1996).
[29] Civil
Code, Article 2224. Temperate or
moderate damages, which are more than nominal but less than compensatory
damages, may be recovered when the court finds that some pecuniary loss has
been suffered but its amount cannot, from the nature of the case, be provided
with certainty.