Republic of the
Supreme Court
SPECIAL THIRD DIVISION
ELPIDIO S. UY, doing
business under the name and style of
Petitioner, - versus - PUBLIC ESTATES AUTHORITY , Respondent. |
G.R.
Nos. 147925-26
Present: VELASCO, JR.,**
NACHURA,
Chairperson, BRION,***and PERALTA, JJ. Promulgated: July 7,
2010 |
x---------------------------------------------------------------------------------x
RESOLUTION
NACHURA, J.:
Before us are (i) the Motion for
Partial Reconsideration filed by petitioner Elpidio S. Uy (Uy), doing business
under the name and style of Edison Development & Construction (EDC), and
(ii) the Motion for Reconsideration filed by respondent Public Estates
Authority (PEA) of our June 8, 2009 Decision, the fallo of which reads:
WHEREFORE, the
petition is PARTIALLY GRANTED. The assailed Joint Decision and Joint
Resolution of the Court of Appeals in CA-G.R. SP Nos. 59308 and 59849
are AFFIRMED with MODIFICATIONS. Respondent Public Estates Authority is
ordered to pay Elpidio S. Uy, doing business under the name and style Edison
Development and Construction, P55,680,492.38 for equipment rentals on
standby; P2,275,721.00 for the cost of idle manpower; and P6,050,165.05 for the construction of
the nursery shade net area; plus interest at 6% per annum to be computed
from the date of the filing of the complaint until finality of this Decision
and 12% per annum thereafter until full payment. Respondent PEA is further ordered to pay
petitioner Uy 10% of the total award as attorney’s fees.
SO ORDERED.[1]
Uy seeks partial reconsideration of
our Decision. He argues that:
I
x x x THE HONORABLE COURT ERRED IN THE COMPUTATION OF THE DAMAGES DUE THE PETITIONER FOR THE STANDBY EQUIPMENT COST.
II
x x x PETITIONER SHOULD BE REIMBURSED FOR COSTS INCURRED FOR ADDITIONAL HAULING DISTANCE OF TOPSOIL ALSO BECAUSE THE EVIDENCE ON RECORD CONFIRMS THE EXISTENCE OF RESPONDENT PEA’S WRITTEN CONSENT, AND THE FACT THAT IT IS INDESPENSABLE TO COMPLETING THE PROJECT. WITHOUT SUCH ASSURANCE OF REIMBURSEMENT, PETITIONER WOULD NOT HAVE TAKEN SUCH PRUDENT ACTION.
III
x x x PETITIONER SHOULD BE ALLOWED TO RECOVER THE COSTS HE INCURRED FOR THE MOBILIZATION OF WATER TRUCKS ALSO BECAUSE RESPONDENT BREACHED ITS OBLIGATIONS UNDER THE CONTRACT.
IV
WITH REGARD TO THE COURT OF APPEALS’ ILLEGAL INJUNCTION PREVENTING PETITIONER FROM RECOVERING HIS CLAIMS AGAINST RESPONDENT PEA IN CIAC CASE NO. 03-2001, THIS SHOULD HAVE BEEN LIFTED SINCE IT INVOLVES CLAIMS SEPARATE AND DISTINCT FROM THE CASE A QUO.[2]
PEA,
on the other hand, assails the Decision on the following grounds:
I.
THE FACTUAL FINDINGS AND CONCLUSIONS OF THE CONSTRUCTION INDUSTRY ARBITRATION COMMISSION (CIAC) INSOFAR AS THE ARBITRAL AWARD TO PETITIONER IS CONCERNED, WHICH THE COURT OF APPEALS AND THE FIRST DIVISION OF THIS HONORABLE COURT AFFIRMED, HAS LONG BECOME FINAL AND EXECUTORY.
II.
THE CIAC ARBITRAL AWARD HAD ALREADY BEEN IMPLEMENTED UNDER WRIT OF EXECUTION DATED 19 SEPTEMBER 2000, WRIT OF EXECUTION DATED 31 AUGUST 2001 AND SUPPLEMENTAL WRIT OF EXECUTION DATED 10 APRIL 2002.[3]
We will deal first with Uy’s motion.
Uy objects to the factor rate used in
the computation of the award for standby equipment costs. He points out that the actual number of
equipment deployed and which remained on standby, occasioned by the delay in
delivery of work areas, has not been considered in the computation. The Association of Carriers and Equipment
Lessors (ACEL) rate or the factor rate used was only the total average rate, without
regard to the actual number of equipment deployed. He, therefore, insists that an increase in the
award is in order.
We find Uy’s argument on this point meritorious;
and this Court is swayed to modify the formula used
in the computation of the award.
The Certification,[4]
dated December 6, 1996, shows that EDC mobilized the following equipment for
the Heritage Park Project, viz.:
Description |
Number |
Road Grader |
2 |
Pay Loader |
2 |
Dump Trucks |
10 |
Tractor with attachments |
2 |
Backhoe |
2 |
Delivery Trucks |
3 |
Rolo-tiller |
0 |
Concrete Mixer |
4 |
Bar Cutter |
2 |
Welding Machine |
2 |
Roller |
1 |
Bulldozer |
1 |
Concrete Cutter |
2 |
Plate Compactor |
2 |
Compressor/Jack Hammer |
3 |
Genset – 5KVA |
1 |
Electric drill/ Holesaw |
4 |
These equipment remained in
the project site on the days that EDC was waiting for the turnover of
additional work areas.[5] Thus, we agree with Uy that the actual number
of equipment mobilized should be included in computing the award for standby
equipment cost. The award must, therefore,
be modified using the following formula:
Actual period of delay (18.2 months) x average rate per ACEL x
number of equipment
However, we cannot simply accept in full Uy’s
claim that he is entitled to P71,009,557.95 as standby equipment cost. The records show that not all of the equipment were
operational; several were under repair.[6] Accordingly, we
find it necessary to remand the records of the case to the Construction
Industry Arbitration Commission (CIAC), which decided the case in the first
instance, for the proper computation of the award of standby equipment cost
based on the foregoing formula.
On
the claim for costs for additional hauling distance of topsoil and for
mobilization of water truck, we maintain our ruling that a written approval of
PEA’s general manager was indispensable before the claim for additional cost
can be granted. In this case, the additional
costs were incurred without the written approval of PEA. The denial of Uy’s claims was, therefore,
appropriate.
We
cannot sustain this claim that is premised mainly on the principle of unjust
enrichment. We stress that the principle
of unjust enrichment cannot be validly invoked by a party who, through his own
act or omission, took the risk of being denied payment for additional costs by
not giving the other party prior notice of such costs and/or by not securing
their written consent thereto, as required by law and their contract.[7]
Similarly,
we find no cogent reason to lift the injunction issued in
CIAC Case No. 03-2001. We are not
persuaded by Uy’s argument that the claims under CIAC Case No. 03-2001
are different from his claims in CIAC Case No. 02-2000. As we explained in our Decision, there is
only one cause of action running through Uy’s undertakings – the violation of his
alleged right under the Landscaping and Construction Agreement. Therefore, the landscaping agreement is
indispensable in the prosecution of his claims in both CIAC Cases No. 02-2000
and No. 03-2001. We reiterate that a
party, either by varying the form or action or by bringing forward in a second
case additional parties or arguments, cannot escape the effects of res judicata when the facts remain the
same, at least where such new parties or matter could have been impleaded or
pleaded in the prior action.
In fine,
except for the claim for standby equipment costs, this Court finds no cogent
reason to depart from our June 8, 2009 Decision.
We now go to PEA’s motion.
PEA insists that our Decision in this
case transgresses the principle of res
judicata. It asserts that the propriety of Uy’s monetary claims against PEA
had already been considered and passed upon by this Court in G.R. Nos.
147933-34.
The argument is specious.
In G.R. Nos. 147933-34, this Court
was very explicit in its declaration that its Decision was independent of, and
without prejudice to, the appeal filed by Uy, viz.:
However,
in order not to prejudice the deliberations of the Court’s Second Division in
G.R. Nos. 147925-26, it should be stated that the findings made in this case,
especially as regards the correctness of the findings of the CIAC, are limited
to the arbitral awards granted to respondent Elpidio S. Uy and to the denial of
the counterclaims of petitioner Public Estates Authority. Our decision in this case does not affect the
other claims of respondent Uy which were not granted by the CIAC in its
questioned decision, the merits of which were not submitted to us for
determination in the instant petition.[8]
Indubitably, this Court’s Decision in G.R. Nos. 147933-34 will
not bar the grant of additional award to Uy.
WHEREFORE, Uy’s Motion for Partial
Reconsideration is PARTLY GRANTED. PEA’s Motion for Reconsideration, on the
other hand, is DENIED with
FINALITY. The assailed Decision dated June 8, 2009 is AFFIRMED with MODIFICATION as to the award of
standby equipment cost. The case is hereby REMANDED to the Construction
Industry Arbitration Commission solely for the purpose of computing the exact
amount of standby equipment cost pursuant to the formula herein specified. The CIAC is DIRECTED to compute the award and effect payment thereof within
thirty (30) days from receipt of the records of this case.
No further pleadings will be entertained.
SO ORDERED.
ANTONIO EDUARDO B. NACHURA
Associate
Justice
WE CONCUR:
RENATO C. CORONA
Chief Justice
PRESBITERO J. VELASCO, JR. Associate Justice |
ARTURO D. BRION Associate Justice |
DIOSDADO M. PERALTA
Associate
Justice
A T T E S T A T I O N
I attest that the conclusions in the above Resolution had
been reached in consultation before the case was assigned to the writer of the
opinion of the Court’s Division.
ANTONIO EDUARDO B. NACHURA
Chairperson,
Special Third Division
C E R T I F I C A T I O N
Pursuant to Section 13, Article VIII of the Constitution
and the Division Chairperson's Attestation, I certify that the conclusions in
the above Resolution had been reached in consultation before the case was
assigned to the writer of the opinion of the Court’s Division.
RENATO
C. CORONA
Chief Justice
* Designated member vice Associate Justice Minita V. Chico-Nazario (ret.) per Special Order No. 631 dated April 29, 2009.
** Designated member vice Associate Justice Conchita Carpio Morales per Special Order No. 649 dated May 25, 2009.
*** Designated member vice Associate Justice Consuelo Ynares-Santiago (ret.) per Raffle dated October 21, 2009.
[1] Rollo, p. 995.
[2]
[3]
[4] Exhibit “J”; Folder No. 2, CIAC Case No. 02-2002.
[5] See Exhibits “F,” “H-1” to “H-29,” “I”; id.
[6] See Exhibit C-1,” id.
[7] Powton Conglomerate, Inc. v. Agcolicol, 448 Phil. 643 (2003).
[8] Public Estates Authority v. Uy, 423 Phil. 407, 419 (2001).