SECOND DIVISION
EXCELLENT QUALITY APPAREL, G.R. No. 175048
INC.,
Petitioner,
Present:
QUISUMBING,
J.,
Chairperson,
-
versus - CARPIO
MORALES
TINGA,
VELASCO,
JR., and
WIN MULTI RICH BUILDERS, INC., BRION, JJ.
represented by its President,
WILSON G. CHUA, Promulgated:
Respondent.
February 10, 2009
x
---------------------------------------------------------------------------------x
D E C I S
I O N
Tinga, J.:
Before us is a Rule 45
petition[1] seeking the reversal of the Decision[2]
and Resolution[3]
of the Court of Appeals in CA-G.R. SP No. 84640. The Court of Appeals had
annulled two orders[4]
of the Regional Trial Court (RTC), Branch 32, of
On 26 March 1996,
petitioner Excellent Quality Apparel, Inc. (petitioner) then represented by Max
L.F. Ying, Vice-President for Productions, and Alfiero R. Orden, Treasurer,
entered into a contract[5]
with Multi-Rich Builders (Multi-Rich) represented by Wilson G. Chua (Chua), its
President and General Manager, for the construction of a garment factory within
the Cavite Philippine Economic Zone Authority (CPEZ).[6]
The duration of the project was for a maximum period of five (5) months or 150
consecutive calendar days. Included in the contract is an arbitration clause
which is as follows:
Article XIX : ARBITRATION
CLAUSE
Should there be any dispute, controversy or difference between the parties arising out of this Contract that may not be resolved by them to their mutual satisfaction, the matter shall be submitted to an Arbitration Committee of three (3) members; one (1) chosen by the OWNER; one (1) chosen by the CONTRACTOR; and the Chairman thereof to be chosen by two (2) members. The decision of the Arbitration Committee shall be final and binding on both the parties hereto. The Arbitration shall be governed by the Arbitration Law (R.A. [No.] 876). The cost of arbitration shall be borned [sic] jointly by both CONTRACTOR and OWNER on 50-50 basis.[7]
The construction of the factory
building was completed on
Respondent
Win Multi-Rich Builders, Inc. (Win) was incorporated with the Securities and
Exchange Commission (SEC) on P8,634,448.20. It also
prayed for the issuance of a writ of attachment claiming that Mr. Ying was
about to abscond and that petitioner was about to close. Win obtained a surety
bond[10] issued
by Visayan Surety & Insurance Corporation. On 10 February 2004, the RTC
issued the Writ of Attachment[11]
against the properties of petitioner.
On
P8,634,448.20, to prevent the Sheriff
from taking possession of its properties.[13] The check was made payable to the Office of
the Clerk of Court of the RTC of Manila as a guarantee for whatever liability
there may be against petitioner.
Petitioner
filed an Omnibus Motion[14]
claiming that it was neither about to close. It also denied owing anything to
Win, as it had already paid all its obligations to it. Lastly, it questioned
the jurisdiction of the trial court from taking cognizance of the case. Petitioner
pointed to the presence of the Arbitration Clause and it asserted that the case
should be referred to the Construction Industry Arbitration Commission (CIAC)
pursuant to Executive Order (E.O.) No. 1008.
In
the hearing held on
oppose the allegations in the Reply.
Win admitted that it was only incorporated on
In
an Order[19]
dated
On
Hence
this petition.
Petitioner
raised the following issues to wit: (1) does Win have a legal personality to
institute the present case; (2) does the RTC have jurisdiction over the case
notwithstanding the presence of the arbitration clause; and (3) was the
issuance of the writ of attachment and the subsequent garnishment proper.
A
suit may only be instituted by the real party in interest. Section 2, Rule 3 of
the Rules of Court defines “parties in interest” in this manner:
A real party in interest is the party who stands to be benefited or injured by the judgment in the suit, or the party entitled to the avails of the suit. Unless otherwise authorized by law or these Rules, every action must be prosecuted or defended in the name of the real party in interest.
Is Win a real party in interest? We answer in the negative.
Win
admitted that the contract was executed between Multi-Rich and petitioner. It
further admitted that Multi-Rich was a sole proprietorship with a business
permit issued by the Office of the Mayor of Manila. A sole proprietorship is
the oldest, simplest, and most prevalent form of business enterprise.[31]
It is an unorganized business owned by one person. The sole proprietor is
personally liable for all the debts and obligations of the business.[32] In the case of Mangila v. Court of Appeals,[33]
we held that:
x x x In fact, there is no law authorizing sole proprietorships to file a suit in court.
A sole proprietorship does not possess a juridical personality separate and distinct from the personality of the owner of the enterprise. The law merely recognizes the existence of a sole proprietorship as a form of business organization conducted for profit by a single individual and requires its proprietor or owner to secure licenses and permits, register its business name, and pay taxes to the national government. The law does not vest a separate legal personality on the sole proprietorship or empower it to file or defend an action in court.
The original petition was
instituted by Win, which is a SEC-registered corporation. It filed a collection
of sum of money suit which involved a construction contract entered into by petitioner
and Multi-Rich, a sole proprietorship. The counsel of Win wanted to change the
name of the plaintiff in the suit to Multi-Rich. The change cannot be
countenanced. The plaintiff in the
collection suit is a corporation. The name cannot be changed to that of a sole
proprietorship. Again, a sole proprietorship is not vested with juridical
personality to file or defend an action.[34]
Petitioner
had continuously contested the legal personality of Win to institute the case.
Win was given ample opportunity to adduce evidence to show that it had legal
personality. It failed to do so. Corpus
Juris Secundum, notes:
x x x where an individual or sole trader organizes a corporation to take over his business and all his assets, and it becomes in effect merely an alter ego of the incorporator, the corporation, either on the grounds of implied assumption of the debts or on the grounds that the business is the same and is merely being conducted under a new guise, is liable for the incorporator's preexisting debts and liabilities. Clearly, where the corporation assumes or accepts the debt of its predecessor in business it is liable and if the transfer of assets is in fraud of creditors it will be liable to the extent of the assets transferred. The corporation is not liable on an implied assumption of debts from the receipt of assets where the incorporator retains sufficient assets to pay the indebtedness, or where none of his assets are transferred to the corporation, or
where, although all the assets of the incorporator have been transferred, there is a change in the persons carrying on the business and the corporation is not merely an alter ego of the person to whose business it succeeded.[35]
In order for a
corporation to be able to file suit and claim the receivables of its
predecessor in business, in this case a sole proprietorship, it must show proof
that the corporation had acquired the assets and liabilities of the sole
proprietorship. Win could have easily presented or attached any document e.g., deed of assignment which will show
whether the assets, liabilities and receivables of Multi-Rich were acquired by
Win. Having been given the opportunity to rebut the allegations made by petitioner,
Win failed to use that opportunity. Thus, we cannot presume that Multi-Rich is
the predecessor-in-business of Win and hold that the latter has standing to
institute the collection suit.
Assuming
arguendo that Win has legal personality, the petition will still be
granted.
Section
4 of E.O. No. 1008[36]
provides for the jurisdiction of the Construction Industry Arbitration
Commission, to wit:
Section 4. Jurisdiction.—The CIAC shall have original and exclusive jurisdiction over disputes arising from, or connected with, contracts entered into by parties involved in construction in the Philippines, whether the disputes arises before or after the completion of the contract, or after the abandonment or breach thereof. These disputes may involve government or private contracts. For the Board to acquire jurisdiction, the parties to a dispute must agree to submit the same to voluntary arbitration.
The jurisdiction of the CIAC may include but is not limited to violation of specifications for materials and workmanship; violation of the terms of agreement; interpretation and/or application of contractual time and delays; amount of damages and penalties; commencement time and delays; maintenance and defects; payment, default of employer or contractor and changes in contract cost.
Excluded from the
coverage of this law are disputes from employer-employee relationships which
shall continue to be covered by the Labor Code of the
There is nothing in the
law which limits the exercise of jurisdiction to complex or difficult cases.
E.O. No. 1008 does not distinguish between claims involving payment of money or
not.[37]
The CIAC acquires jurisdiction over a construction contract by the mere fact
that the parties agreed to submit to voluntary arbitration.[38]
The law does not preclude parties from stipulating a preferred forum or
arbitral body but they may not divest the CIAC of jurisdiction as provided by
law.[39] Arbitration is an alternative method of
dispute resolution which is highly encouraged.[40]
The arbitration clause is a commitment on the part of the parties to submit to
arbitration the disputes covered since
that clause is binding, and they are expected to
abide by it in good faith.[41]
Clearly, the RTC should not have taken cognizance of the collection suit. The
presence of the arbitration clause vested jurisdiction to the CIAC over all
construction disputes between Petitioner and Multi-Rich. The RTC does not have
jurisdiction.[42]
Based
on the foregoing, there is no need to discuss the propriety of the issuance of
the writ of attachment. However, we cannot allow Win to retain the garnished
amount which was turned over by the RTC. The RTC did not have jurisdiction to
issue the questioned writ of attachment and to order the release of the
garnished funds.
WHEREFORE, the petition is GRANTED. The
Decision of the Court of Appeals is hereby MODIFIED.
Civil Case No. 04-108940 is DISMISSED.
Win Multi-Rich Builders, Inc. is ORDERED
to return the garnished amount of EIGHT MILLION SIX HUNDRED THIRTY-FOUR THOUSAND FOUR HUNDRED
FORTY-EIGHT PESOS AND FORTY CENTAVOS (P8,634,448.40),
which was turned over by the Regional
Trial Court, to petitioner with legal interest of 12 percent (12%) per annum upon
finality of this Decision until payment.
SO ORDERED.
DANTE O. TINGA Associate Justice
WE CONCUR:
LEONARDO A. QUISUMBING
Associate Justice
Chairperson
CONCHITA CARPIO MORALES PRESBITERO J.
VELASCO, JR.
Associate Justice Associate Justice
ARTURO D. BRION
Associate Justice
ATTESTATION
I attest that the conclusions in the above
Decision had been reached in consultation before the case was assigned to the
writer of the opinion of the Court’s Division.
LEONARDO A. QUISUMBING
Associate
Justice
Chairperson,
Second Division
CERTIFICATION
Pursuant to Section 13, Article VIII of
the Constitution, and the Division Chairperson’s Attestation, it is hereby
certified that the conclusions in the above Decision had been reached in
consultation before the case was assigned to the writer of the opinion of the
Court’s Division.
REYNATO S. PUNO
Chief Justice
[2]Dated
[3]Dated
[15]Dated
[16]
[17]Dated.
[21]
[23]
[24]
[25]
[31] Henn,
Harry G. Cases and Materials on the Laws of Corporations American Casebook Series, West Publishing Co.
[32] Schneeman, Angela. The Law of Corporations and Other Business Organizations. 4th ed. ThomPson. © 2007, p. 26.
[33]435 Phil. 870, 886 (2002).
[36]Entitled Creating An Arbitration Machinery in
the Construction Industry of the Philippines, approved on
[37] Parlade, Custodio, The Law and Practice of Conciliation and Arbitration of Construction Disputes, ©2001 p. 89.
[39] China
Chang Jiang Energy Corporation v. Rosal Infrastructure Bulders, etc., G.R.
No. 125706, Third Division Resolution
dated
[41] LM Power Engineering Corporation v. Capitol Industrial Construction Groups, Inc., 447 Phil. 705, 716 (2003).
[42]Apart from Sec. 4 of E.O. No. 1008, supra note 11, R.A. No. 9285, otherwise known as the “Alternative Disputes Resolution Act of 2004,” provides:
SEC. 39. Court to Dismiss Case Involving a Construction Dispute.—A Regional Trial Court before which a construction dispute is filed shall, upon becoming aware, not later than the pretrial conference, that the parties had entered into an arbitration agreement, dismiss the case and refer the parties to arbitration to be conducted by the CIAC, unless both parties, assisted by their respective counsel, shall submit to the Regional Trial Court a written agreement exclusively for the Court, rather than the CIAC, to resolve the dispute.