THIRD DIVISION
CONTINENTAL CEMENT CORP., Petitioner, - versus - FILIPINAS (PREFAB)
SYSTEMS, INC., Respondent. FILIPINAS (PREFAB)
SYSTEMS, INC., Petitioner, - versus - CONTINENTAL CEMENT CORP., Respondent. |
G.R.
No. 176917
G.R. No. 176919 Present: YNARES-SANTIAGO, J.,
Chairperson, CHICO-NAZARIO, VELASCO, NACHURA, and PERALTA, JJ. Promulgated: August 4,
2009 |
x------------------------------------------------------------------------------------x
DECISION
NACHURA, J.:
Before this Court are two Petitions
for Review on Certiorari assailing the Court of Appeals’ Decision[1]
dated October 20, 2006 and Resolution[2]
dated March 6, 2007 in CA G.R. CV No. 71593.
The antecedents, as summarized by the
Court of Appeals, are as follows:
x x x
[P]laintiff-appellee Continental Cement Corporation (CCC) entered into a
construction agreement with defendant-appellant Filipinas Systems, Inc.
(FILSYSTEMS) for the civil works construction for its Cement Plant Expansion
Project at Bo. Bigte, Norzagaray, Bulacan for and in consideration of P82,300,00.00
(sic). Under the contract, the period for the project’s completion should be
300 days from 22 February 1993 or up to 18 December 1993. However, on 3
September 1993, CCC filed an action for Specific Performance with TRO and/or
Preliminary Mandatory Injunction against FILSYSTEMS to prevent the latter from
pulling out its equipment from the site and stopping the construction of the
project. While the suit was pending, the parties entered into a Compromise
Agreement which was approved by the trial court on 14 October 1993. Among
others, the said agreement provided for new terms and conditions of payment.
Under Item No. 5 thereof, the civil works was to be paid in cash, cement,
crushed aggregates (sic) as well as steel bars. The agreement, particularly
Item No. 6, also admitted that FILSYSTEMS has 109 days [from 6 October 1993 or
actual resumption of work, exclusive of contract time extensions for
accomplished and future changes] to finish the project. And under item no. 7,
the parties further agreed that all future change orders, additional works and
construction bulletins shall be implemented by FILSYSTEMS only after CCC and
its architect sign and the two agree on the price which will be billed
separately. The change orders, additional works and construction bulletins
already accomplished prior to the Compromise Agreement were supposed to be
reconciled and paid immediately.
Thereafter, FILSYSTEMS and CCC filed their separate Motions for Execution based on the aforementioned Compromise Agreement on, (sic) 1 and 14 September 1994, respectively.
Banking on items no. 5 and 7 of the Compromise Agreement, FILSYSTEMS claimed that CCC failed to release the cement and crushed aggregates as per the agreed schedules annexed to the Compromise Agreement and to pay FILSYSTEMS’ subsequent billings also in the form of cement. Aside from this claim, the latter also asked for the fifteen percent (15%) liquidated damages and five percent (5%) attorney’s fees computed from the original price.
On the other hand, CCC advanced that FILSYSTEMS failed to finish the project after one hundred nine (109) days as provided in Item no. 6 of the same compromise agreement. As such, it similarly prays for the fifteen percent (15%) liquidated damages and five percent (5%) attorney’s fees.[3]
After trial, the RTC issued a
Decision,[4]
the dispositive portion of which reads:
WHEREFORE, premises considered, finding that the defendant failed to perform its obligation under the Compromise Agreement dated October 4, 1993, without any justification, the plaintiff’s expansion project on time or within the 109 calendar days, from October 6, 1993 to January 23, 1994, as agreed and without fault on plaintiff’s part, this Court hereby orders said defendant to pay the plaintiff the following:
1. The sum of Twelve Million Three Hundred Forty Five Thousand Pesos (Php 12,345,000.00) in liquidated damages pursuant to the Compromise Agreement;
2. The sum of Fifty Million Three Hundred Thirty Eight Thousand Two Hundred Twenty One Pesos and Sixty One Centavos (Php 50,338,221.61) for the cost of finishing plaintiff’s expansion cement plant, pursuant to Article 1167 of the Civil Code; and
3. Four Million One Hundred Fifteen Thousand Pesos (Php 4,115,000.00) for attorney’s fees, as provided for in the Compromise Agreement.
4. Plus costs.
SO ORDERED.[5]
FILSYSTEMS appealed the Decision to
the Court of Appeals. On October 20,
2006, the CA issued the assailed Decision,[6]
the dispositive portion of which reads:
WHEREFORE, the instant appeal is AFFIRMED with these MODIFICATIONS:
(1) Appellant FILSYSTEMS is hereby ordered to pay appellee CCC the following:
(a) The sum of Six Million One Hundred Seventy-Two Thousand Five Hundred Pesos (PhP6,172,500.00) as liquidated damages; and
(b) The sum of Six Million Six Hundred Thousand Seven Hundred Twenty-Three Pesos and Thirty-Six Centavos (PhP6,600,723.36) as the cost of finishing CCC’s expansion cement plant;
and
(2) Appellee CCC is hereby ordered to pay appellant FILSYSTEMS the following:
(a) The sum of Ten Million Four Hundred Twenty Thousand One Hundred Sixty-One Pesos and Seventeen Centavos (PhP10,420,161.17) as the amount still due the latter based on the parties (sic) reconciliatory talks;
(b) The sum of Seven Hundred Seventy-Seven Thousand Seven Hundred Thirty-Five Pesos (PhP777,735.00) as liquidated damages.
SO ORDERED.[7]
The
CA found CCC to have defaulted in the payment of its obligations. On the other hand, FILSYSTEMS not only
incurred in delay in performing its obligation but, in fact, failed to finish
the project.
The CA held that, under the
Compromise Agreement, CCC was to pay FILSYSTEMS P3.5 million in cement for
change orders, additional works, and construction bulletins, even as the
parties failed to reconcile their accounts.
The CA, likewise, held that, while
FILSYSTEMS agreed that CCC would pay in kind, the payment was not to be made in
advance. Under the Compromise Agreement,
CCC was to deliver the delivery receipts only and not the cement. These delivery receipts were to be given in
advance to allow FILSYSTEMS to withdraw cement from CCC’s plants, but always
against the value equivalent to the completed or accomplished work.
The CA also found that FILSYSTEMS was
in fact lagging behind in its work schedule. It said that CCC’s delay was not a sufficient
excuse for FILSYSTEMS to incur in delay and not finish the project. According to the CA, FILSYSTEMS failed to
explain how the delay in CCC’s payment contributed to its own delay.
On the other hand, the CA upheld FILSYSTEMS’
claim that it was entitled to time extension. However, it said that FILSYSTEMS could not
unilaterally claim the time extension in order to excuse itself or justify the
delay in the project. As such,
FILSYSTEMS is still liable for the delay. Hence, the CA made a tempered
application of the penalty clause of the Construction Contract. It reduced the liquidated damages awarded by
the trial court by half, bringing down FILSYSTEMS’ liability to P6,172,500.00.
The CA also found that FILSYSTEMS had
completed 92.839% of the project, based on the testimony of CCC’s own accounting
manager,[8]
and is, therefore, entitled to P10,420,161.17. This also proves, the CA said, that payments
by CCC to FILSYSTEMS were also delayed. Hence,
the CA held that CCC is liable to pay FILSYSTEMS P777,735.00 as
liquidated damages.
The CA also modified the trial
court’s award of P50,338,221.61 in favor of CCC, which was allegedly the
cost incurred when CCC hired another contractor to finish the project. The CA said that the amount was glaringly
disproportionate to the unfinished part of the project. Considering that the unfinished work is
equivalent only to 7.161% of the project, the amount FILSYSTEMS should pay must
be correspondingly reduced to P6,600,723.36.
CCC then filed the first of the two
petitions at bar.[9] It
assails the part of the CA’s Decision holding that FILSYSTEMS is entitled to P3.5
million in cement. It claims that the
payment of that amount is still subject to final reconciliation of accomplished
change orders, additional works, and construction bulletins.[10]
It also argues that the CA erred in
reducing the award of liquidated damages, stressing that time is of the essence
in the Construction Contract, and that FILSYSTEMS’ delay and total failure to
complete the project is a clear breach of the Compromise Agreement and renders
the essence of time under the Construction Contract moot.[11] Thus, CCC posits that it is entitled to the
full amount of liquidated damages.[12]
CCC likewise disputes the finding that
it incurred in delay in paying FILSYSTEMS. It avers that nowhere in the
Compromise Agreement did it admit that it was in delay; that the Compromise
Agreement stated, in fact, that the balance it is to pay FILSYSTEMS would be due
only after the completion of the project, a condition never fulfilled because
of the latter’s breach.[13]
Then, CCC assails the CA’s finding
that FILSYSTEMS had finished 92.839% of the project, since no evidence was adduced
to this effect before FILSYSTEMS was deemed in delay. Instead, CCC claims that it was able to show
that, because FILSYSTEMS was unable to
finish the project, the former was compelled to contract C.E. Construction to complete
the same.[14]
Lastly, CCC questions the deletion of
the award of attorney’s fees. It argues
that the Compromise Agreement provided that attorney’s fees equivalent to five
percent of the total original contract price, plus change orders/additional
works/construction bulletins, must be paid by the aggrieved party to the guilty
party. Because FILSYSTEMS breached its
obligation under the Compromise Agreement, CCC submits that the trial court
correctly awarded it P4,115,000.00 in attorney’s fees.[15]
Hence, CCC prays that this Court
partially reverse the CA Decision and affirm the trial court’s Decision in toto.[16]
Meanwhile, FILSYSTEMS filed its own
Petition for Review[17]
of the CA Decision.
FILSYSTEMS claims that the CA
erroneously considered all infractions committed by CCC prior to the signing of
the Compromise Agreement to have been set aside by the said agreement. It points to the CA’s failure to appreciate
that the former was authorized to suspend work in the event CCC defaulted in
the payment of submitted progress billings;[18]
thus, FILSYSTEMS was not in delay. On
the contrary, it was CCC that was in delay in the payment of FILSYSTEMS’
approved progress billings, prompting the latter to invoke its right to stop
work in accordance with Article V of the Construction Agreement. According to FILSYSTEMS, CCC’s delay totaled
77 days; but the CA refused to grant FILSYSTEMS the equivalent time extension,
because the infraction occurred before the Compromise Agreement.[19]
Next, FILSYSTEMS posits that the CA
misconstrued the Construction Agreement to be on a “turn key” basis, which
means that the contractor would initially finance the completion of the
project. FILSYSTEMS argues that the agreement was the regular type of
construction agreement, where the owner was obligated to pay the contractor
periodically based on the percentage of completion of work.[20] FILSYSTEMS
emphasized that its refusal to continue working was due to CCC’s failure to
promptly pay the former’s submitted/approved progress billings.[21]
Thus,
FILSYSTEMS prays for modification of the CA Decision and the deletion of all
monetary awards in favor of CCC.[22]
The resolution of these cases calls
for a re-examination of facts. While
generally, the Court is not a trier of facts, a recognized
exception thereto is a situation where the findings of fact of the Court of
Appeals and the trial court are conflicting.[23]
Indeed, the most fundamental
rule in the interpretation of contracts is that, if the terms are clear and
leave no doubt as to the intention of the contracting parties, the literal
meaning of the contract provisions shall control. However, where some ambiguity exists, in
order to determine the intention of the parties, their contemporaneous and
subsequent acts should be considered.[24]
Thus, to resolve the question of
default by the parties, we must re-examine the terms of the Construction Contract
and the Compromise Agreement.
We
sustain the finding of the CA holding CCC to have incurred in default in its payments
to FILSYSTEMS.
Records show that CCC admitted it was
in default. FILSYSTEMS had already
completed 44% of the work at the time the parties entered into a Compromise
Agreement. This means that, by the terms
of the Construction Contract, FILSYSTEMS should have been paid P36,212,000.00.
However, CCC admitted having paid only P27,006,028.04. Hence, it still owed FILSYSTEMS P9,205,971.96.
CCC also admitted that it owed FILSYSTEMS P3.5 million in cement for accomplished
change orders/additional works/construction bulletins.
Conversely, CCC’s contention that
FILSYSTEMS was in default is bereft of merit.
The right of FILSYSTEMS to stop work is
recognized by CCC, as the Construction Contract provides:
ARTICLE V
PAYMENTS
Upon signing of this Contract, the OWNER shall pay the CONTRACTOR a downpayment of twenty six and four over one hundred percent (26.4%) of the Contract Price. The downpayment shall be liquidated by the CONTRACTOR from his monthly progress billings.
Ten percent (10%) of each monthly progress payment shall be retained by the OWNER until fifty (50%) (sic) completion of the contract work. No additional retention shall be made.
The OWNER shall make payment to the CONTRACTOR on account of this Contract thirty (30) days after submission of each progress billing in consideration of the work accomplished by the CONTRACTOR less ten percent (10%) retention and Expanded Withholding Tax (One percent of the gross amount of accomplishment).
As required by Philippine Law, the Contractor’s Expanded Withholding Tax withheld from each payment to the CONTRACTOR shall be transmitted by the OWNER to the Bureau of Internal Revenue in favor of the CONTRACTOR’S TIN Account No. 391-412.
No payments shall be made unless payment requests are on the prescribed form and bear the approval of the Construction Manager of the OWNER and concurred in by the ARCHITECT.
Should the OWNER be delayed in the payment of the monthly billings beyond five (5) days after it is due, the work schedule or timetable shall be extended accordingly. If payment due is delayed for sixty (60) days, then the CONTRACTOR has the right to stop the work.[25]
In addition, in the Compromise
Agreement, the parties recognized that the 109 days left in the original time frame
was “exclusive of contract time extensions for accomplished and future change
orders, additional works and construction bulletins and whatever additional
contract time extensions provided in this Agreement and/or already earned or
allowed under the original Construction Contract, dated January 23, 1993.”[26]
Paragraph 6.b. of the Compromise
Agreement is also instructive:
6.b. Defendant, on a best efforts basis and without prejudice to paragraph 6 above, shall finish the construction zones referred to in the Construction Contract dated January 23, 1993 which shall be identified by the plaintiff as priority construction zones, taking into consideration plaintiff’s schedule of arrival of machineries and installation thereof on said zones.[27]
The Compromise Agreement must be
interpreted as a whole. Its provisions must be construed collectively, and the
meaning imputed to them must give effect to all. As this Court has previously pronounced:
The intention of the contracting parties should be ascertained by looking at the words used to project their intention, that is, all the words, not just a particular word or two or more words standing alone. The various stipulations of a contract shall be interpreted together, attributing to the doubtful ones that sense which may result from all of them taken jointly. The parts and clauses must be interpreted in relation to one another to give effect to the whole. The legal effect of a contract is to be determined from the whole read together.[28]
Thus, FILSYSTEMS must be accorded the
time extensions it is entitled to under the Compromise Agreement. As the CA correctly held, it would go against
the grain of equity and fair play to insist that FILSYSTEMS was limited to the non-extendible
period of 109 days to complete the project, as erroneously found by the trial
court.[29]
Further,
since CCC is in default, FILSYSTEMS is entitled to liquidated damages, pursuant
to Paragraph 9 of the Compromise Agreement, which states:
9. Should any party fail to comply
with its obligation(s) as stipulated in this Compromise Agreement and/or
violate any provisions of the Construction Contract not otherwise amended,
repealed and/or modified as aforestated, the aggrieved party shall be entitled
to move for the issuance by this Honorable Court of a writ of execution to
enforce the provisions of this Compromise Agreement and/or the Compromise
Judgment to be rendered by the court based on this Compromise Agreement. In
this connection, the guilty party hereby undertakes to pay the aggrieved party
additional liquidated damages in the amount equivalent to fifteen percent (15%)
of the total original contract price of P82,300,000.00 and attorney’s
fees equivalent to five percent (5%) of the total original contract price plus
change orders/additional works/construction bulletins.[30]
However,
we find that the CA erred in its computation of the liquidated damages CCC should
pay FILSYSTEMS. In its Decision, the CA
computed the liquidated damages as follows:
The original cost of the project is Php82,300,000.00 while the additional works, as conceded by CCC’ (sic) 31 August 1994 letter, is approximately 12% of the original project cost. Thus, the total project cost is PhP92,176,000.00. Considering that CCC was entitled to retain 10% of the first half of the construction cost, it was entitled to retain PhP4,608,800.00. Against the PhP10,420,161.17 CCC concededly owed FILSYSTEMS, the latter was underpaid by Php5,811,361.17 or by 6.3% of the total project cost. As such, CCC must be made to 6.3% of the full liquidated damages under the Compromise Agreement at PhP12,345,000.00. Hence, CCC is liable to pay FILSYSTEMS liquidated damages in the amount of PhP777,735.00.[31]
This
computation has no basis. The Compromise Agreement clearly stated that any
liquidated damages due will be “fifteen percent (15%) of the total original
contract price of P82,300,000.00” regardless of any additional costs
incurred by the parties. Thus, FILSYSTEMS is entitled to P12,345,000.00.
We
likewise sustain the CA’s decision holding CCC liable for P3.5 million in
accomplished change orders and additional works.
Paragraph 7 of the Compromise
Agreement reads in part:
x
x x x It is understood that should the parties fail to reconcile the
accomplished change orders, additional works and construction bulletins within
the 15-day period, just the same, plaintiff (CCC) shall immediately pay
defendant the approximate amount of P3.5 Million in cement, subject to
final reconciliation not later than thirty (30) days from signing of this
Agreement. x x x x
It is erroneous for CCC to claim that
it is to pay the P3.5 million only after reconciliation. As the CA aptly held:
With this, CCC cannot simply dismiss
the said P3.5 Million as being a mere “assigned value” for it is very
clear that if the parties fail to reconcile the accomplished additional works
within fifteen (15) days from the signing of the Compromise Agreement, CCC must
still pay the said amount, which is the determined value of the change orders admitted
in paragraphs 1 (a) and 7 of the Compromise Agreement. Thus, it is incorrect
for CCC to expect that it must first be billed and approved by CCC and CC
Castro International before it can be required to pay for this procedure
applies to the subsequent additional works done after the signing of the Compromise
Agreement.[32]
CCC itself recognized that it was
liable to pay this amount to FILSYSTEMS in paragraph 1 (a) of the Compromise
Agreement when it acknowledged the latter’s accomplished change
orders/additional works and construction bulletins in the approximate amount of
P3.5 million.
Had
it been the parties’ intention to make the payment subject to reconciliation,
it would have been unnecessary to put the above-quoted portion in paragraph 7
of the Compromise Agreement. The intent,
to our mind, is simple, i.e., that
even if there is no reconciliation within 15 days, CCC will still pay – “just
the same” – FILSYSTEMS P3.5 million in cement “subject to final
reconciliation”. The reconciliation will
come after the payment and not before.
FILSYSTEMS next argues that the CA
erred in interpreting the Construction Contract as a “turn key” agreement[33]
and not a regular type of construction agreement, where the owner is obligated
to pay the contractor periodically based on percentage of completion, which, in
this case, would be within 30 days from submission of each billing progress.[34]
The CA based its conclusion on
Article 1 (Scope of Work) of the contract, which reads in part:
That the CONTRACTOR, for and in consideration of the payment to be made by the CONTRACTOR of the sum of money hereinafter stated, shall construct/perform and erect on a turnkey basis the following scope of work: x x x x[35]
This denomination of the nature of
the project notwithstanding, there is a specific provision in the agreement to
the effect that the owner shall pay the contractor “on account of this contract
thirty (30) days after submission of each progress billing in consideration of
the work accomplished by the contractor less ten percent (10%) retention and
Expanded Withholding Tax.”[36] Further, that same article in the contract
provides that delay by CCC in the payment of the monthly billings beyond five
days after they are due entitles FILSYSTEMS to an extension of the work
schedule. If the delay in payment
extends to 60 days, FILSYSTEMS may then exercise the right to stop the work.[37] This was precisely what FILSYSTEMS did. Thus,
it cannot be said to have violated the terms of the contract.
Still, FILSYSTEMS cannot fully escape
liability. It is a fact – and FILSYSTEMS
does not deny this – that it failed to finish the project, in contravention of
its obligation under the Construction Contract and the Compromise Agreement.
The CA held that FILSYSTEMS failed to
prove that the delay it incurred was attributable to CCC’s failure to deliver
the P3.5 million payment in cement.[38] It also held that FILSYSTEMS could not
unilaterally declare or claim the time extensions in order to excuse itself or
justify the delay in the project.[39]
We agree with the CA.
FILSYSTEMS has not shown that it was CCC’s
delay that caused the former to fail to complete the project. On the contrary, it appears that despite CCC’s
delays, FILSYSTEMS was able to accomplish 92.83% of the work. This proves that the completion of the project
was not entirely dependent on CCC’s payment – or prompt payment – of its obligation.
FILSYSTEMS’ failure to finish the project is, therefore, unjustified. Accordingly, it must be held liable for the
cost of completing the project. Article
1167 of the Civil Code provides:
Art. 1167. If a person obliged to do something fails to do it, the same shall be executed at his cost.
This same rule shall be observed if he does it in contravention of the tenor of the obligation. Furthermore, it may be decreed that what has been poorly done be undone.
We
do not believe, however, that FILSYSTEMS should be made to pay the entire cost
CCC paid to CE Construction, which finished the project.
It has been shown that at the time
FILSYSTEMS stopped work, the project was 92.83% finished, although such work was
accomplished beyond the initial deadline of 23 January 1993. But, as already
discussed above, FILSYSTEMS was entitled to time extensions equivalent to the
delay in the payment of its progress billings. Hence, FILSYSTEMS must be held liable only for
the remaining 7.17% of the project. To make
it answer for more would unjustly enrich CCC, which has already benefited from
the former’s work.
Finally,
the issue of attorney’s fees. We sustain the CA’s deletion of the trial court’s
award thereof, because both parties failed to comply with their obligations as
stipulated in the Compromise Agreement.[40]
In sum, we hold that CCC defaulted in
the payment of its obligation to FILSYSTEMS under the Compromise Agreement. On
the other hand, FILSYSTEMS was not in default; however, considering that it failed
to perform the obligation incumbent upon it under the Compromise Agreement, it
must be held liable for the cost of completion of the unfinished portion of the
project.
WHEREFORE, the
foregoing premises considered, the Petition in G.R. No. 176917 is DENIED for lack of merit, while the
Petition in G.R. No. 176919 is PARTIALLY
GRANTED. Accordingly, the Court of
Appeals’ Decision dated October 20, 2006 in CA G.R. CV No. 71593 is hereby PARTIALLY MODIFIED to read:
WHEREFORE, the instant appeal is AFFIRMED with MODIFICATIONS:
(1) Appellant FILSYSTEMS is hereby ordered to pay appellee CCC the sum of six Million Six hundred Thousand Seven Hundred Twenty-Three Pesos and Thirty-Six Centavos (PhP6,600,723.36) as the cost of finishing CCC’s expansion cement plant, plus legal interest at the rate of 6% per annum from the time of the filing of CCC’s Motion for Execution of the Compromise Agreement before the trial court and, thereafter, at the rate of 12% from the finality of this Decision until the same is fully paid;
and
(2) Appellee CCC is hereby ordered to pay appellant FILSYSTEMS the following:
(a) The sum of Ten Million Four Hundred Twenty Thousand One Hundred Sixty-One Pesos and Seventeen Centavos (PhP10,420,161.17) as the amount still due the latter based on the parties’ reconciliatory talks, plus legal interest at the rate of 6% per annum from the time of the filing of FILSYSTEMS’ Motion for Execution of the Compromise Agreement before the trial court and, thereafter, at the rate of 12% from the finality of this Decision until the same is fully paid;
(b) The sum of Twelve Million Three Hundred Forty-Five Thousand Pesos (PhP12,345,000.00) as liquidated damages, plus legal interest at the rate of 6% per annum from the time of the filing of FILSYSTEMS’ Motion for Execution of the Compromise Agreement, before the trial court and, thereafter, at the rate of 12% from the finality of this Decision until the same is fully paid.
SO ORDERED.
ANTONIO EDUARDO B. NACHURA
Associate
Justice
WE CONCUR:
CONSUELO YNARES-SANTIAGO
Associate
Justice
Chairperson
MINITA V. CHICO-NAZARIO Associate
Justice |
PRESBITERO J. VELASCO, JR. Associate
Justice |
DIOSDADO M. PERALTA
Associate
Justice
A T T E S T A T I O N
I attest that the conclusions in the above Decision were
reached in consultation before the case was assigned to the writer of the
opinion of the Court’s Division.
CONSUELO
YNARES-SANTIAGO
Associate
Justice
Chairperson,
Third Division
C E R T I F I C A T I O N
Pursuant to Section 13, Article VIII of the Constitution
and the Division Chairperson's Attestation, I certify that the conclusions in
the above Decision were reached in consultation before the case was assigned to
the writer of the opinion of the Court’s Division.
REYNATO
S. PUNO
Chief
Justice
[1] Penned by Justice Rosmari D. Carandang, with Justices Renato C. Dacudao and Estela M. Perlas-Bernabe, concurring, Rollo (G.R. No. 176917), pp. 8-31.
[2] Penned by Justice Rosmari D. Carandang, with Justices Renato C. Dacudao and Estela M. Perlas-Bernabe, concurring, id. at 32-33.
[3]
[4] Penned by Judge Fatima Gonzales-Asdala, rollo (G.R. No. 176919), pp. 129-142.
[5]
[6] Rollo (G.R. No. 176917), pp. 57-80.
[7]
[8]
[9] G.R. No. 176917.
[10] Rollo (G.R. No. 176917), p. 45.
[11]
[12]
[13]
[14]
[15]
[16]
[17] G.R. No. 176919.
[18] Rollo (G.R. No. 176919), p. 25.
[19]
[20]
[21]
[22]
[23]
[24]Agro Conglomerates, Inc. v. Court of Appeals, 401 Phil. 645, 656 (2000) citing Manila Surety & Fidelity Co., Inc. vs. Court of Appeals, G.R. No 55466, December 3, 1990, 191 SCRA 805, 812; citing Mercantile Ins. Co., Inc. vs. Felipe Ysmael, Jr. & Co. Inc., G.R. No. 43862, January 13, 1989, 169 SCRA 66, 74; GSIS vs. Court of Appeals, 229 Phil. 320 (1986); Sy vs. Court of Appeals, 216 Phil. 110 (1984).
[25] Rollo (G.R. No. 176917), p. 108. (emphasis supplied)
[26]
[27]
[28] Villamaria, Jr. v. Court of Appeals, G.R. No. 165881, April 19, 2006, 487 SCRA 571, 593. (citations omitted)
[29] Rollo (G.R. No. 176917), p. 22.
[30]
[31]
[32]
[33] A turnkey
(or turn-key) is defined as
pertaining to, or resulting from, an arrangement under which a private
contractor designs and constructs a project, building, etc., for sale when
completely ready for occupancy or operation.<http://dictionary.reference.com/browse/turn
key> (visited July 24, 2009).
[34] Rollo (G.R. No. 176919), p. 31.
[35] Rollo (G.R. No. 176917), p. 105.
[36] Rollo (G.R. No. 176917), paragraph 3, Article V, Construction Contract, p. 108
[37]
[38]
[39]
[40]