Republic of the Philippines
Supreme Court
Manila
THIRD DIVISION
REPUBLIC
OF THE PHILIPPINES, G.R. No.
158253
represented
by the DEPARTMENT
OF
PUBLIC WORKS AND HIGHWAYS,
COMMISSION
ON AUDIT and THE
NATIONAL
TREASURER,
Petitioner,
Present:
YNARES-SANTIAGO, J.,
(Chairperson)
- versus - AUSTRIA-MARTINEZ,
CALLEJO,
SR.,*
CHICO-NAZARIO,
and
NACHURA,
JJ.
CARLITO
LACAP, doing business
under the
name and style CARWIN
CONSTRUCTION
AND
CONSTRUCTION
SUPPLY, Promulgated:
Respondent. March 2,
2007
x-
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - x
D E C I S I O N
AUSTRIA-MARTINEZ,
J.:
Before the Court is a Petition for Review
on Certiorari under Rule 45 of the
Revised Rules of Court assailing the Decision[1]
dated April 28, 2003 of the Court of Appeals (CA) in CA-G.R. CV No. 56345 which
affirmed with modification the Decision[2] of
the Regional Trial Court, Branch 41, San Fernando, Pampanga (RTC) in Civil Case
No. 10538, granting the complaint for Specific Performance and Damages filed by
Carlito Lacap (respondent) against the Republic of the Philippines
(petitioner).
The factual background of the case is
as follows:
The District Engineer of Pampanga issued and duly published an “Invitation To Bid” dated January 27, 1992. Respondent, doing business under the name and
style Carwin Construction and Construction Supply (Carwin Construction), was pre-qualified together with two other
contractors. Since respondent submitted the lowest bid, he was awarded the
contract for the concreting of Sitio 5 Bahay Pare.[3] On
November 4, 1992, a Contract Agreement was executed by respondent and
petitioner.[4] On
September 25, 1992, District Engineer Rafael S. Ponio
issued a Notice to Proceed with the concreting of Sitio 5 Bahay Pare.[5] Accordingly,
respondent undertook the works, made advances for the purchase of the materials
and payment for labor costs.[6]
On October 29, 1992, personnel of the
Office of the District Engineer of San Fernando, Pampanga conducted a final
inspection of the project and found it 100% completed in accordance with the
approved plans and specifications. Accordingly, the Office of the District
Engineer issued Certificates of Final Inspection and Final Acceptance.[7]
Thereafter, respondent sought to
collect payment for the completed project.[8] The
DPWH prepared the Disbursement Voucher in favor of petitioner.[9]
However, the DPWH withheld payment from respondent after the District Auditor
of the Commission on Audit (COA) disapproved the final release of funds on the
ground that the contractor’s license of respondent had expired at the time of the
execution of the contract. The District Engineer sought the opinion of the DPWH
Legal Department on whether the contracts of Carwin Construction for various
Mount Pinatubo rehabilitation projects were valid and effective although its
contractor’s license had already expired when the projects were contracted.[10]
In a Letter-Reply dated September 1,
1993, Cesar D. Mejia, Director III of the DPWH Legal Department opined that since
Republic Act No. 4566 (R.A. No. 4566), otherwise known as the Contractor’s
License Law, does not provide that a contract entered into after the license
has expired is void and there is no law which expressly prohibits or declares
void such contract, the contract is enforceable and payment may be paid,
without prejudice to any appropriate administrative liability action that may
be imposed on the contractor and the government officials or employees
concerned.[11]
In a Letter dated July 4, 1994, the
District Engineer requested clarification from the DPWH Legal Department on
whether Carwin Construction should be paid for works accomplished despite an
expired contractor’s license at the time the contracts were executed.[12]
In a First Indorsement dated July 20,
1994, Cesar D. Mejia, Director III of the Legal Department, recommended that
payment should be made to Carwin Construction, reiterating his earlier legal
opinion.[13] Despite
such recommendation for payment, no payment was made to respondent.
Thus, on July 3, 1995, respondent
filed the complaint for Specific Performance and Damages against petitioner before
the RTC.[14]
On September 14, 1995, petitioner,
through the Office of the Solicitor General (OSG), filed a Motion to Dismiss
the complaint on the grounds that the complaint states no cause of action and
that the RTC had no jurisdiction over the nature of the action since respondent
did not appeal to the COA the decision of the District Auditor to disapprove
the claim.[15]
Following the submission of
respondent’s Opposition to Motion to Dismiss,[16]
the RTC issued an Order dated March 11, 1996 denying the Motion to Dismiss.[17]
The OSG filed a Motion for Reconsideration[18]
but it was likewise denied by the RTC in its Order dated May 23, 1996.[19]
On August 5, 1996, the OSG filed its
Answer invoking the defenses of non-exhaustion of administrative remedies and the
doctrine of non-suability of the State.[20]
Following trial, the RTC rendered on
February 19, 1997 its Decision, the dispositive portion of which reads as
follows:
WHEREFORE,
in view of all the foregoing consideration, judgment is hereby rendered in
favor of the plaintiff and against the defendant, ordering the latter, thru its
District Engineer at Sindalan, San Fernando, Pampanga, to pay the following:
a)
P457,000.00 – representing the
contract for the concreting project of Sitio 5 road,
Bahay Pare, Candaba, Pampanga
plus interest at 12% from demand until fully paid; and
b)
The costs of suit.
SO
ORDERED.[21]
The RTC held that petitioner must be
required to pay the contract price since it has accepted the completed project and
enjoyed the benefits thereof; to hold otherwise would be to overrun the long
standing and consistent pronouncement against enriching oneself at the expense
of another.[22]
Dissatisfied, petitioner filed an
appeal with the CA.[23] On April 28, 2003, the CA rendered its
Decision sustaining the Decision of the RTC.
It held that since the case involves the application of the principle of
estoppel against the government which is a purely legal question, then the
principle of exhaustion of administrative remedies does not apply; that by its
actions the government is estopped from questioning the validity and binding
effect of the Contract Agreement with the respondent; that denial of payment to
respondent on purely technical grounds after successful completion of the
project is not countenanced either by justice or equity.
The CA rendered herein the assailed
Decision dated April 28, 2003, the dispositive
portion of which reads:
WHEREFORE, the decision of the lower court is hereby AFFIRMED with modification in that the interest shall be six percent (6%) per annum computed from June 21, 1995.
SO ORDERED.[24]
Hence, the present petition on the following
ground:
THE COURT OF APPEALS
ERRED IN NOT FINDING THAT RESPONDENT HAS NO CAUSE OF ACTION AGAINST PETITIONER,
CONSIDERING THAT:
(a)
RESPONDENT FAILED TO EXHAUST
ADMINISTRATIVE REMEDIES; AND
(b)
IT IS THE COMMISSION ON AUDIT WHICH
HAS THE PRIMARY JURISDICTION TO RESOLVE RESPONDENT’S MONEY CLAIM AGAINST THE
GOVERNMENT.[25]
Petitioner contends that respondent’s
recourse to judicial action was premature since the proper remedy was to appeal
the District Auditor’s disapproval of payment to the COA, pursuant to Section
48, Presidential Decree No. 1445 (P.D. No. 1445), otherwise known as the
Government Auditing Code of the Philippines; that the COA has primary
jurisdiction to resolve respondent’s money claim against
the government under Section
2(1),[26]
Article IX of the 1987 Constitution and Section 26[27]
of P.D. No. 1445; that non-observance of the doctrine of exhaustion of
administrative remedies and the principle of primary jurisdiction results in a
lack of cause of action.
Respondent, on the other hand, in his
Memorandum[28] limited
his discussion to Civil Code provisions relating to human relations. He submits
that equity demands that he be paid for the work performed; otherwise, the
mandate of the Civil Code provisions relating to human relations would be
rendered nugatory if the State itself is allowed to ignore and circumvent the
standard of behavior it sets for its inhabitants.
The present petition is bereft of
merit.
The general rule is that
before a party may seek the intervention of the court, he should first avail of
all the means afforded him by administrative processes.[29]
The issues which
administrative agencies are authorized to decide should not be summarily taken
from them and submitted to a court without first giving such administrative
agency the opportunity to dispose of the same after due deliberation.[30]
Corollary to the doctrine of
exhaustion of administrative remedies is the doctrine of primary jurisdiction;
that is, courts cannot or will not determine a controversy involving a question
which is within the jurisdiction of the administrative tribunal prior to the
resolution of that question by the administrative tribunal, where the question
demands the exercise of sound administrative discretion requiring the special
knowledge, experience and services of the administrative tribunal to determine
technical and intricate matters of fact.[31]
Nonetheless, the doctrine of
exhaustion of administrative remedies and the corollary doctrine of primary
jurisdiction, which are based on sound public policy and practical
considerations, are not inflexible rules.
There are many accepted exceptions, such as: (a) where there is estoppel
on the part of the party invoking the doctrine; (b) where the challenged
administrative act is patently illegal, amounting to lack of jurisdiction; (c) where there is unreasonable delay or
official inaction that will irretrievably prejudice the complainant; (d) where
the amount involved is relatively small so as to make the rule impractical and
oppressive; (e) where the question
involved is purely legal and will ultimately have to be decided by the courts
of justice;[32] (f) where judicial
intervention is urgent; (g) when its application may cause great and
irreparable damage; (h) where the controverted acts violate due process; (i)
when the issue of non-exhaustion of administrative remedies has been rendered
moot;[33]
(j) when there is no other plain, speedy and adequate remedy; (k) when strong
public interest is involved; and, (l) in quo
warranto proceedings.[34] Exceptions (c) and (e) are applicable
to the present case.
Notwithstanding the legal opinions of
the DPWH Legal Department rendered in 1993 and 1994 that payment to a
contractor with an expired contractor’s license is proper, respondent remained
unpaid for the completed work despite repeated demands. Clearly, there was unreasonable delay and
official inaction to the great prejudice of respondent.
Furthermore, whether a contractor
with an expired license at the time of the execution of its contract is
entitled to be paid for completed projects, clearly is a pure question of
law. It does not involve an examination
of the probative value of the evidence presented by the parties. There is a
question of law when the doubt or difference arises as to what the law is on a
certain state of facts, and not as to the truth or the falsehood of alleged
facts.[35] Said question at best could be resolved only tentatively
by the administrative authorities. The final decision on the matter rests not
with them but with the courts of justice. Exhaustion of administrative remedies
does not apply, because nothing of an administrative nature is to be or can be
done.[36]
The issue does not require technical knowledge and experience but one that would
involve the interpretation and application of law.
Thus, while it is undisputed that the
District Auditor of the COA disapproved respondent’s claim against the Government,
and, under Section 48[37]
of P.D. No. 1445, the administrative remedy available to respondent is an
appeal of the denial of his claim by the District Auditor to the COA itself, the
Court holds that, in view of exceptions (c) and (e) narrated above, the
complaint for specific performance and damages was not prematurely filed and within
the jurisdiction of the RTC to resolve, despite the failure to exhaust
administrative remedies. As the Court aptly
stated in Rocamora v. RTC-Cebu (Branch
VIII):[38]
The
plaintiffs were not supposed to hold their breath and wait until the Commission
on Audit and the Ministry of Public Highways had acted on the claims for
compensation for the lands appropriated by the government. The road had been completed; the Pope had
come and gone; but the plaintiffs had yet to be paid for the properties taken
from them. Given this official
indifference, which apparently would continue indefinitely, the private
respondents had to act to assert and protect their interests.[39]
On the question of
whether a contractor with an expired license is entitled to be paid for
completed projects, Section
35 of R.A. No. 4566 explicitly provides:
SEC. 35. Penalties. Any contractor
who, for a price, commission, fee or wage, submits or attempts to submit a bid
to construct, or contracts to or undertakes to construct, or assumes charge in a
supervisory capacity of a construction work within the purview of this Act,
without first securing a license to engage in the business of contracting in
this country; or who shall present or file the license certificate of another,
give false evidence of any kind to the Board, or any member thereof in
obtaining a certificate or license, impersonate another, or use an expired or revoked certificate or
license, shall be deemed guilty of misdemeanor, and shall, upon conviction,
be sentenced to pay a fine of not less than five hundred pesos but not more
than five thousand pesos. (Emphasis supplied)
The “plain meaning rule” or verba
legis in statutory construction is that if the statute is clear, plain and
free from ambiguity, it must be given its literal meaning and applied without
interpretation.[40]
This rule derived from the maxim Index animi sermo est (speech is the index of intention) rests on
the valid presumption that the words employed by the legislature in a statute
correctly express its intention or will and preclude the court from construing
it differently. The legislature is presumed to know the meaning of the
words, to have used words advisedly, and to have expressed its intent by use of
such words as are found in the statute.[41]
Verba legis non est recedendum, or from the words of a statute there
should be no departure.[42]
The wordings of R.A. No. 4566 are
clear. It does not declare, expressly or
impliedly, as void contracts entered into by a contractor whose license had
already expired. Nonetheless, such contractor is liable for payment of the fine
prescribed therein. Thus, respondent
should be paid for the projects he completed.
Such payment, however, is without prejudice to the payment of the fine
prescribed under the law.
Besides, Article 22 of the Civil Code
which embodies the maxim Nemo ex alterius incommode
debet lecupletari (no man ought to be made rich out of another’s injury)
states:
Art.
22. Every person who through an act of
performance by another, or any other means, acquires or comes into possession
of something at the expense of the latter without just or legal ground, shall
return the same to him.
This article is part of the chapter
of the Civil Code on Human Relations, the provisions of which were formulated
as “basic principles to be observed for the rightful relationship between human
beings and for the stability of the social order, x x
x designed to indicate certain norms that spring from
the fountain of good conscience, x x x guides human conduct [that] should run as golden threads
through society to the end that law may approach its supreme ideal which is the
sway and dominance of justice.”[43] The
rules thereon apply equally well to the Government.[44] Since
respondent had rendered services to the full satisfaction and acceptance by
petitioner, then the former should be compensated for them. To allow petitioner to acquire the finished
project at no cost would undoubtedly constitute unjust enrichment
for the petitioner to the prejudice of respondent. Such unjust enrichment is
not allowed by law.
WHEREFORE, the present
petition is DENIED for lack of merit.
The assailed Decision of the Court of Appeals dated April 28, 2003 in CA-G.R. CV No.
56345 is AFFIRMED. No
pronouncement as to costs.
SO ORDERED.
MA. ALICIA AUSTRIA-MARTINEZ
Associate
Justice
WE CONCUR:
CONSUELO
YNARES-SANTIAGO
Associate Justice
Chairperson
(On Leave)
ROMEO J. CALLEJO, SR. MINITA V. CHICO-NAZARIO
Associate Justice Associate Justice
ANTONIO EDUARDO B. NACHURA
Associate Justice
ATTESTATION
I attest that the conclusions in the
above Decision had been reached in consultation before the case was assigned to
the writer of the opinion of the Court’s Division.
CONSUELO
YNARES-SANTIAGO
Associate Justice
Chairperson, Third Division
C
E R T I F I C A T I O N
Pursuant to Section 13, Article VIII
of the Constitution, and the Division Chairperson’s attestation, it is hereby
certified that the conclusions in the above Decision had been reached in
consultation before the case was assigned to the writer of the opinion of the
Court’s Division.
REYNATO S. PUNO
Chief Justice
* On Leave.
[1] Penned by Associate Justice Rosmari D. Carandang and concurred in by Associate Justices Conrado M. Vasquez, Jr. and Mercedes Gozo-Dadole, CA rollo, p. 167.
[2] Original Records, p. 120.
[3] Id. at 7.
[4] Id. at 8.
[5] Id. at 12.
[6] CA rollo, p. 268.
[7] Original Records, p. 12-A.
[8] Id. at 13.
[9] Id. at 14.
[10] Id. at 15.
[11] Ibid.
[12] Id. at 16.
[13] Id.
[14] Id. at 1.
[15] Id. at 37.
[16] Id. at 48.
[17] Id. at 50.
[18] Id. at 58.
[19] Id. at 67.
[20] Id. at 78.
[21] Id. at 125.
[22] Id. at 124-125.
[23] CA rollo, p. 17.
[24] Id. at 273.
[25] Id. at 33.
[26] SEC. 2
(1) The Commission on Audit shall have the power, authority, and duty to
examine, audit and settle all accounts pertaining to the revenue and receipts
of, and expenditures or uses of funds and property, owned or held in trust by,
or pertaining to, the Government, or any of its subdivisions, agencies, or
instrumentalities, including government-owned or controlled corporations with
original charters, and on a post-audit basis: (a) constitutional bodies,
commission and offices that have been granted fiscal autonomy under this Constitution;
(b) autonomous state colleges and universities; (c) other government-owned or
controlled corporations and their subsidiaries; and (d) such non-governmental
entities receiving subsidy or equity, directly or indirectly, from or through
the Government, which are required by law or the granting institution to submit
to such audit as a condition of subsidy or equity. However, where the internal control system of
the audited agencies is inadequate, the Commission may adopt such measures,
including temporary or special pre-audit, as are necessary and appropriate to
correct the deficiencies. It shall keep
the general accounts of the Government and for such period as may be provided
by law, preserve the vouchers and other supporting papers pertaining thereto.
[27] Section 26. General jurisdiction. – The authority and powers of the Commission shall extend to and comprehend all matters relating to auditing procedures, systems and controls, the keeping of the general accounts of the Government, the preservation of vouchers pertaining thereto for a period of ten years, the examination and inspection of the books, records, and papers relating to those accounts; and the audit and settlement of the accounts of all persons respecting funds or property received or held by them in an accountable capacity, as well as the examination, audit, and settlement of all debts and claims of any sort due from or owing the Government or any of its subdivisions, agencies and instrumentalities. The said jurisdiction extends to all government-owned or controlled corporations, including their subsidiaries, and other self-governing boards, commissions, or agencies of the Government, and as herein prescribed, including non-governmental entities subsidized by the government, those funded by donation through the government, those required to pay levies of government share, and those which the government has put up a counterpart fund or those partly funded by the government.
[28] Rollo, p. 152.
[29] ACWS, Ltd. v. Dumlao, 440 Phil. 787, 801-802 (2002); Zabat v. Court of Appeals, 393 Phil. 195, 206
(2000).
[30] ACWS case, id. at 802.
[31] Paloma v. Mora, G.R. No. 157783, September 23, 2005, 470 SCRA 711, 725; Fabia v. Court of Appeals, 437 Phil. 389, 403 (2002).
[32] Rocamora v. Regional Trial Court-Cebu (Branch VIII), No. L-65037, November 23, 1988, 167 SCRA 615, 623.
[33] Carale v. Abarintos, 336 Phil. 126, 137 (1997).
[34] Castro v. Sec. Gloria, 415 Phil. 645, 651-652 (2001).
[35] Castro v. Sec. Gloria case, id. at 652.
[36] Espina v. Court of Appeals, 356 Phil. 15, 21 (1998); Prudential Bank v. Gapultos, G.R. Nos. 41835 & 49293, January 19, 1990, 181 SCRA 159, 168.
[37] Section
48. Appeal
from the decision of auditors. – Any person aggrieved by the decision of an
auditor of any government agency in the settlement of account or claim may
within six months from receipt of a copy of the decision appeal in writing to
the Commission.
[38] Supra note 32.
[39] Id. at 624-625.
[40] Commissioner of Internal Revenue v. Central Luzon Drug Corporation, G.R. No. 159647, April 15, 2005, 456 SCRA 414, 443; National Federation of Labor v. National Labor Relations Commission, 383 Phil. 910, 918 (2000); Ruben E. Agpalo, Statutory Construction, 2003 Ed., p. 124.
[41] Southern Cross Cement Corporation v. Philippine Cement Manufacturers Corporation, G.R. No. 158540, July 8, 2004, 434 SCRA 65, 93; Republic v. Court of Appeals, 359 Phil. 530, 602 (2000).
[42] Enjay,
Inc. v. National Labor
Relations Commission, 315 Phil. 648, 656 (1995); Globe-Mackay Cable and Radio Corporation v. National Labor Relations Commission, G.R. No. 82511,
March 3, 1992, 206 SCRA 701, 711.
[43] Advanced Foundation Construction Systems Corporation v. New World Properties and Ventures, Inc., G.R. Nos. 143154 & 143177, June 21, 2006, 491 SCRA 557, 578; Security Bank & Trust Co. v. Court of Appeals, 319 Phil. 312, 317 (1995), citing Report of the Code Commission, p. 39, cited in Padilla, Ambrosio, Civil Code Annotated, Vol. 1, 1975.
[44] Palma Development Corp. v. Municipality of Malangas, Zamboanga Del Sur, 459 Phil. 1042, 1050 (2003); Republic v. Court of Appeals, No. L-31303-04, May 31, 1978, 83 SCRA 453, 480.