THIRD DIVISION
GUEVENT INDUSTRIAL DEVELOPMENT
CORPORATION, Petitioner, - versus - |
G.R. No. 159279 Present: QUISUMBING,
J., Chairperson, CARPIO, CARPIO MORALES, TINGA, and VELASCO, JR., JJ. |
PHILIPPINE LEXUS AMUSEMENT CORPORATION, Respondent. |
Promulgated: July 11, 2006 |
x- - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - -x
DECISION
QUISUMBING, J.:
For
review on certiorari is the Decision[1]
dated July 31, 2002 of the Court of Appeals in CA-G.R. CV No. 54291 which
reversed the Decision[2]
dated August 5, 1996 of the Regional Trial Court, Pasig City, Branch 156. Also assailed is the Resolution[3]
dated
Respondent leased for the period of
United Adjustment Company (UAC),
commissioned by respondent, estimated the value of the damage at P865,149.25 and concluded that the clogged storm drainage and
sewer pipes installed underground along petitioner’s private road caused the
flooding. On the basis of this report,
respondent demanded the payment of the value of the damage from petitioner. When petitioner refused, respondent filed a
complaint for damages with the Regional Trial Court (RTC) of
In its Answer, petitioner averred
that it was the clogged public drainage of
On
On appeal, the Court of Appeals
reversed the trial court. It ruled that
the flooding was not due to a fortuitous event but caused by the clogging of
petitioner’s internal drainage system as reported by UAC. It further ruled that respondent’s failure to
insure the machines did not excuse petitioner from liability. Petitioner sought reconsideration but the
same was denied.
Petitioner now comes before us
raising the following issues:
A.
WHETHER OR NOT THE PETITIONER IS LIABLE TO RESPONDENT
FOR DAMAGES SUSTAINED BY RESPONDENT DUE TO THE CLOGGING OF THE INTERNAL
DRAINAGE SYSTEM IN (sic) PETITIONER IN ITS COMPOUND.
B. WHETHER OR NOT THE PROPER MAINTENANCE OF PETITIONER’S INTERNAL DRAINAGE SYSTEM WAS IMMATERIAL BECAUSE THE CAUSE OF THE DAMAGE SUSTAINED BY RESPONDENT WAS THE DEFECTIVE INTERNAL DRAINAGE SYSTEM OF PETITIONER.
C. WHETHER OR NOT RESPONDENT WAS NEGLIGENT WHEN IT DID NOT PROCURE THE STIPULATED INSURANCE OVER ITS VIDEO MACHINES AGAINST FIRE AND ALLEGED RISKS INCLUDING TYPHOONS, FLOODS, ETC.
D.
WHETHER OR NOT PETITIONER IS LIABLE TO RESPONDENT FOR
DAMAGES IN THIS INSTANT CASE AT BENCH.[4]
For our
initial resolution is the question, what caused the flooding? Then, we will consider whether the petitioner is
liable for damages.
Though the jurisdiction of this Court
in cases brought before it from the Court of Appeals is limited to reviewing or
revising errors of law, findings of facts of the latter may be reviewed in
exceptional cases.[5] Such exception takes place where the findings
of fact of the Court of Appeals are at variance with those of the trial court,[6]
in which case the Court reviews the evidence in order to arrive at the correct
findings based on the records.
After our review of the records, we
are inclined to agree with the Court of Appeals that the cause of flooding was
not a fortuitous event but the clogging of the drainage pipes. We ask then, did petitioner’s private pipes
cause the flooding or was it due to the clogging of the public drainage system?
The Court of Appeals based its ruling
on the assessment report of the respondent-commissioned UAC pointing to the
clogged internal pipes as the cause of the flooding. Yet, the UAC did not explain how it arrived
at its conclusions. Neither are we told
of UAC’s qualifications to determine the conditions of the drainage pipes. At this juncture, worth stressing, UAC was
commissioned by respondent, and UAC is not an independent, impartial nor neutral investigator.
Before the trial court, petitioner showed
that it had maintained and regularly de-clogged its own drainage as evidenced
by its Daily Deployment of Personnel Report.
We note also that there was proof that the public drainage system needed
de-clogging. Petitioner also presented a
barangay certification that the area is always flooded whenever there is heavy
downpour. The Office of the City Mayor
also does not deny that the public drainage system needed rehabilitation. All these lead us to conclude that the poor
condition of the public drainage, and not the private pipes, primarily caused
the flooding. Conformably then, we
cannot hold petitioner negligent, for the record reveals that it had constantly
requested the local government to dredge and de-clog the public sewers.[7]
The maintenance of the public
drainage system could not have been contemplated by the lease contract when it
provided that the lessor shall maintain the premises in good and tenantable
condition. The law on contract does not force
the performance of impossible obligations by the parties,[8]
and the maintenance of the public sewers is something impossible to expect from
the lessor.[9] The petitioner is accountable only for its
pipes, and it should not be held responsible for the maintenance of the public
sewers.
WHEREFORE, the
petition is GRANTED. The Decision dated
Costs against the respondent.
SO ORDERED.
|
LEONARDO A. QUISUMBING Associate Justice |
WE CONCUR:
ANTONIO T. CARPIO Associate Justice |
|
CONCHITA CARPIO MORALES Associate Justice |
DANTE O. TINGA Associate Justice |
PRESBITERO J. VELASCO,
JR. Associate Justice |
A T T E S T A T I O N
I attest that the conclusions in the above Decision
had been reached in consultation before the case was assigned to the writer of
the opinion of the Court’s Division.
|
LEONARDO A. QUISUMBING Associate Justice Chairperson |
C E R T I F I C A T I O N
Pursuant to Section 13, Article VIII of the
Constitution, and the Division Chairperson’s Attestation, I certify that the
conclusions in the above Decision had been reached in consultation before the
case was assigned to the writer of the opinion of the Court’s Division.
|
ARTEMIO V. PANGANIBAN Chief Justice |
[1] Rollo, pp. 40-46. Penned by Associate Justice Hilarion L. Aquino, with Justices Edgardo P. Cruz, and Regalado E. Maambong concurring.
[2]
[3]
[4]
[5] See Pastor v. Philippine
National Bank, G.R. No. 141316,
[6] See Serrano v. Court of Appeals,
G.R. No. 123896,
[7] Exhibits “8, 8-A, 9, 9-C,
10, 11 and 12”, records, pp. 255-264.
[8] Civil Code, Art. 1348. Impossible things or services cannot be the object of contracts.
[9] See Edgardo L. Paras, Civil
code of the