THIRD DIVISION
[G.R. No. 133909. February 15, 2000]
PHILIPPINE
NATIONAL CONSTRUCTION CORPORATION, petitioner, vs. MARS
CONSTRUCTION ENTERPRISES, INC., respondent. brando
D E C I S I O N
PANGANIBAN, J.:
Unilateral rescission of a contract is
subject to judicial determination. Contractual stipulations should be
interpreted together. Ambiguous ones should be construed to conform to the
sense that would result when all the provisions are comprehended jointly.
Moreover, doubts should be settled in favor of the greatest reciprocity of
interests.
The
Case
Before the Court is a Petition for Review
under Rule 45 of the Rules of Court, seeking the reversal of the May 20, 1998
Decision of the Court of Appeals[1] (CA) in CA-GR CV No. 45009, which affirmed the
Regional Trial Court (RTC) of Pasig City (Branch 154). The assailed Decision
disposed as follows:[2]
"WHEREFORE,
[there being] no error in the appealed decision, the same is AFFIRMED in
toto."
The
Facts
In its assailed Decision, the Court of
Appeals relates the facts of this case as follows:[3]
"On July 2,
1982, [Mars Construction Enterprises, Inc., respondent herein] entered into a
subcontract/Agreement with x x x Construction & Development Corporation of
the Philippines (CDCP) [petitioner herein], later reorganized into the present
Philippine National Construction Corporation (PNCC), for the supply of
‘approximately seventy thousand (70,000) cubic meters of aggregates consisting
of: micks
1. washed sand,
2. washed ¾" gravel,
3. washed 1-½" gravel
4. sub-base’.
"On August 7,
1982, [respondent] and CDCP executed Amendment No. 1 increasing the amount of
the third party liability coverage from P50,000.00 to P100,000.00.
On November 5, 1982, [respondent] and CDCP executed Amendment No. 2 amending
the scope of services, as follows:
‘1. Art. I is hereby amended to read:
‘ARTICLE I –
SCOPE OF SERVICES
'The FIRST PARTY
[respondent] shall supply approximately SEVENTY THOUSAND (70,000) cubic meters
of concrete aggregates consisting of the following:
1. [W]ashed sand app. 17,500 cu. m.
2. Washed ¾" gravel app. 17,500 cu. m. Me-sm
3. Washed 1 ½" gravel app. 35,000 cu.
m.
4. Sub-base 2" minus crusher run
xxx xxx xxx.'
(Exhibit ‘C-1’,
Folder of Exhibits)
"Amendment
No. 2 also altered Article IV (5.0) of the original Agreement which provided
that ‘(t)he first party guarantees to commence delivery within forty five (45)
days after signing of the contract and continue delivery until the quantities
enumerated x x x [shall] have been delivered to the jobsite stockpile’ to read
as follows:
‘ARTICLE V –
DELIVERY
'The FIRST PARTY
[respondent] shall deliver a minimum of SIX THOUSAND (6,000) cubic meters of
combined concrete aggregate per month until the entire requirements of the
SECOND PARTY [petitioner] to complete the Philphos Project shall have been
satisfied.’ (Underscoring supplied.)
"Actual
delivery of aggregates started only in March of 1983, or a delay of eight (8)
months of the 45 days stipulated in the Agreement (Agreement, Article IV (5.0);
TSN, September 6, 1985, pp. 9-10). There were also non-deliveries between the
period June 1983 to January 1984 (TSN, supra). Thus [petitioner] was
constrained to obtain the necessary materials from other sources, incurring
additional costs representing the difference between the agreed price of
P140.00 per cubic meter under the Agreement and the pricing of the outside
sources. The difference in cost was reimbursed by [respondent] in accordance
with the default clause under the Agreement that ‘the Second Party [petitioner]
can procure from any other quarry operator x x x (and) should such procurement
cost the Second Party more than the agreed price above, the excess [would] be
for the account of the First Party x x x' (Article VII, no. 7). A total of
P1.578 M was thusly paid by [respondent] (TSN, September 5, 1985, p. 12). S-l-x
"The
controversy arose when [petitioner] refused to accept [respondent’s] delivery
of 17,000.00 cubic meters of washed 1-1/2" gravel, saying that it had no
more need for the same. For this, [respondent] claimed the amount of
P680,000.00 representing lucrum cessans or unrealized profit with
interest at bank rate until fully paid, exemplary damages and attorney’s fees.
[Respondent] also demanded payment of P118,518.68 (Memorandum for Plaintiff,
Record, p. 245) covered by a check tendered by [petitioner] (Exhibit ‘15’)
based on a balance on the purchase of 39,200.62 cubic meters of base course
amounting to P130,000.00 after deducting half of the overpayment of P23,256.80
made by [respondent] (TSN, April 22, 1986, p. 22).
"[Petitioner]
denied that it breached the contract and counter-claimed for the amount of
P85,120 as price differential of the procurement cost over the agreed price,
plus reimbursement of overpayment of P23,256.80 it had made arising from error
in measurement. (Answer, Counterclaim).
"The lower
court rendered judgment, as follows: nigella
‘Wherefore, the
foregoing considered, judgment is hereby rendered in favor of plaintiff and
against the defendant ordering the defendant to pay plaintiff: a.) the amount
of P680,000.00 as lucrum cessans; b.) the amount of P33,387.91 for the
outstanding obligation of PNCC in favor of plaintiff (118,518.68 less price
differential of P85,120.77); c.) attorney’s fees x x x reduced to the
reasonable amount of P50,000.00; and as the costs of litigation.’"
Ruling
of the Court of Appeals
The CA ruled that the Contract and its
amendments impelled petitioner to accept delivery of the washed 1.5-inch gravel
from the respondent. The figures in the "Scope of Services" provision
were interpreted to mean the minimum quantities to be delivered to the
petitioner. The petitioner received a total of 8,162.43 cubic meters of washed
1.5-inch gravel from the respondent and 9,978.06 cubic meters from other
sources. Hence, the petitioner actually utilized only 18,140.49 cubic meters of
aggregates of this specification, which was only about half of the stipulated
35,000 cubic meters. Clearly, it breached the Contract when it refused to
accept delivery of the 17,000 cubic meters of washed 1.5-inch gravel from the
respondent.
Because of this breach, the respondent was
entitled to lucrum cessans, computed by deducting the production cost
from the agreed cost per cubic meter of aggregates
The outstanding obligation of the petitioner
to the respondent was the difference between the subcontractor’s quitclaim
minus the penalty charges for outsourcing aggregates, which respondent incurred
for its failure to deliver. The amount was based on the Quitclaim presented by
petitioner and the undisputed Backcharge Invoice No. 354 presented by
respondent.
Sc-slx
The CA denied the petitioner’s prayer for
damages arising from the delays in delivery, because respondent had already
compensated or paid for such delays. The appellate court rejected petitioner’s
contention that the respondent committed bad faith by entering into a contract
that it was financially incapable of fulfilling, inasmuch as this issue had not
been raised before the trial court.
Hence, this Petition.[4]
Issues
In its Memorandum, the petitioner submits
the following "issues" for the Court’s consideration:[5]
"i. The honorable Court of Appeals x x x
decided that PNCC was compelled to accept the delivery of the 17,000 cubic
meters of washed 1-½" gravel which is not in accord with law and
jurisprudence
"ii. The honorable Court of Appeals x x x
decided to award the amount of P680,000.00 as lucrum cessans which is not in
accord with law and jurisprudence." Sl-xsc
The
Court’s Ruling
The Petition has no merit.
First
Issue: Obligation to Accept Delivery
Petitioner contends that it was not under
any obligation to accept 17,000 cubic meters of washed 1.5-inch gravel, because
the delivery was made after the actual aggregate requirement of the project had
already been fully satisfied, and after respondent had defaulted on its
contractual undertakings.
Interpreting the ContractSl-xm-is
Petitioner adds that the respondent had
already delivered aggregates, the combined volume of which was about 45 percent
over and above that required in Article I, Amendment 2 of the Contract. Hence,
the petitioner refused to accept the "excess" delivery in issue.
This contention is incorrect. The various
stipulations in a contract should be interpreted together. Ambiguous ones
should be so construed as to conform to the sense that would result if all the
provisions are comprehended jointly.[6] The "Scope of Services" provision in
Amendment 2 stipulated the delivery of 70,000 cubic meters of concrete
aggregates consisting of approximately 17,500 cubic meters of washed sand,
approximately 17,500 cubic meters of washed .75-inch gravel, 35,000 cubic
meters of washed 1.5-inch gravel, and "sub-base 2" minus crusher run.
Clearly, at least 35,000 of the 70,000 cubic meters of concrete
aggregates that the respondent was supposed to deliver to the petitioner should
be washed 1.5-inch gravel. The trial court correctly explained: M-issdaa
"x x x
Initially, [respondent’s] scope of services [was] to supply 70,000 cu. m. of
concrete aggregates consisting of washed sand, washed ¾"gravel, washed
1-½" gravel and sub-base (Art. 1 of the Agreement). This was amended per
Amendment No. 2 (Exhibit C) to 70,000 cu. m. of concrete aggregates consisting
of washed sand approximately 17,500 cu. m., washed ¾" gravel approximately
17,500 cu. m., washed 1-½" gravel approximately 35,000 cu. m., and
sub-base 2" minus crusher run. This amendment x x x made the agreement
[ambiguous] because the quantity of sub-base 2" minus crusher run was not
specified. If said aggregate was included[;] however, the total would
definitely be in excess of 70,000 cu. m. x x x [Petitioner] had ordered from
[respondent] more than what was specified in the agreement. This act
[signified] that the maximum limit of 70,000 cu. m. [was] disregarded
[because of] PNCC’s needs. What then would be the significance of the
quantities stated in Amendment No. 2? We interpret that these are the minimum
quantities which must be delivered by [respondent]. Both parties are bound by
these figures. x x x."[7]
Besides, the stipulation would be too
burdensome to the respondent if, as petitioner insists, the breakdown of the
specified aggregates were interpreted as mere estimates of the project
requirements; the respondent would have then been uncertain as to how much it
should deliver. Doubts in contracts should be settled in favor of the greatest
reciprocity of interests.[8] Accordingly, these figures, as held by the CA,
should be deemed the minimum amounts to be procured and delivered. In this way,
both parties would know exactly how much to demand from each other to be able
to comply with their respective obligations.
Provisional Unilateral Resolution
PNCC Project Director H. R. Taylor’s letter
of May 17, 1984 informed the respondent of the final quantities of concrete
aggregates to be delivered, with the advice that no other deliveries would be
accepted. Hence, the petitioner asserts that, after that advice, it was no
longer bound to accept any further deliveries from the respondent. Sd-aad-sc
We disagree. Such advice is not a sufficient
justification for refusing delivery. The only clause on delivery is Stipulation
2 of Amendment 2, which states that "[t]he FIRST PARTY shall deliver a
minimum of SIX THOUSAND (6,000) [c]ubic meters of combined concrete aggregate
per month until the entire requirements of the SECOND PARTY to complete the
Philphos Project shall have been satisfied."[9] The Contract did not authorize the petitioner to
limit, by means of a unilateral advice, the quantity of aggregates that may be
delivered. Although there were several occasions when the petitioner advised
the respondent on the quality and the quantity of concrete aggregates to be
delivered, Mr. Solomon Chu (general manager of respondent) testified that the
giving of advice did not become the practice between them.[10]
By saying that the quantity specified in the
letter was its last order, petitioner unilaterally amended its Contract with
the respondent. The act of treating a contract as cancelled or rescinded on
account of infractions by the other contracting party is always provisional;[11] that is, contestable and subject to judicial
determination.[12] Judicial action is necessary for its rescission in
order to afford the other party an opportunity to be heard[13] and to determine if the rescission was proper.[14] When the herein petitioner resolved or rescinded the
Agreement without previous court action, it proceeded at its own risk. Only the
final judgment of a court will conclusively and finally settle whether such
recourse was correct in law.
Default as Insubstantial BreachScä
Petitioner avers that respondent was already
in default when the former refused the latter's delivery of 17,000 cubic meters
of washed 1.5-inch gravel. Hence, its refusal was justified.
We are not persuaded. The contract
specifically provided that if the respondent failed to deliver the required
aggregates, the petitioner could procure them from other sources so as not to
jeopardize the entire construction project. The records reveal that on several
occasions, petitioner purchased concrete aggregates from other suppliers.[15]
Pursuant to Paragraph 3 of Amendment 2,
petitioner imposed penalties for the incremental cost of procuring materials
from other sources, which respondent willingly paid in the sum of P1,577,000.
Since petitioner was already compensated for respondent's defaults, such
defaults cannot be considered as a substantial breach that justified the
rescission of the Contract and the refusal to accept the questioned delivery.[16]
Furthermore, when the petitioner exercised
its options in case of delay or default on the part of the respondent, the
former waived its right to rescind and was thus estopped from rescinding the
Contract by reason of such short delivery.[17] ScmisÓ
In light of the foregoing, the CA correctly
held that petitioner was under obligation to accept and to pay for the 17,000
cubic meters of washed 1.5-inch gravel delivered by the respondent.[18] As found by the CA, the petitioner procured only a
total of 18,140.49 cubic meters of washed 1.5-inch gravel from the respondent
and from other suppliers (9,978.06 and 8,162.43 cubic meters, respectively).
Thus, the respondent had the prerogative to supply, and the petitioner was
bound to accept, 16,859.51 (or approximately 17,000) cubic meters of 1.5-inch
gravel. Parties to a contract are bound to the fulfillment of what has
expressly been stipulated.[19]
Second
Issue: Factual Question of Lost Profits
Petitioner avers that the profits which
respondent expected to derive from the Agreement were purely speculative, and
that the trial and the appellate courts erroneously believed Mr. Chu’s bare
testimony on said profits. MisÓ sc
We are not persuaded. Whether the respondent
failed to realize profits -- and if so, how much -- and whether the judgment
was supported by the evidence presented by it are factual in nature. Factual
findings of the trial court, especially when affirmed by the Court of Appeals,
as in this case, are binding and conclusive on the Supreme Court. It is not the
function of this Court to reexamine the lower courts’ findings of fact.[20] While there are exceptions to this rule,[21] petitioner has not shown its entitlement to any of
them.
WHEREFORE, the Petition is DENIED and the assailed
Decision AFFIRMED. Costs against petitioner.
SO ORDERED.
Melo, (Chairman), Vitug, Purisima, and Gonzaga-Reyes, JJ., concur. MisÓ spped
[1] First Division composed of J. Portia Aliño-Hormachuelos, ponente; JJ Arturo B. Buena (now a member of the Supreme Court) and Buenaventura J. Guerrero, members.
[2] CA Decision, p. 38.
[3] Ibid., pp. 1-4; rollo, pp. 30-33.
[4] This case was deemed submitted for decision upon receipt by this Court of the Memorandum for Mars Construction Enterprises, Inc. on October 11, 1999. This Memorandum was signed by Atty. Luis V. Diores of Diores Law Offices (rollo, p. 93).
[5] Rollo, p. 75; the Memorandum for the petitioner was signed by Government Corporate Counsel Jun N. Valerio, Deputy Government Corporate Counsel Elpidio J. Vega, Asst. Government Corporate Counsel Efren B. Gonzales and Government Corporate Attorney IV Manuel V. Fernandez (rollo, p. 75).
[6] See Article 1374, Civil Code.
[7] RTC Decision, p. 12; CA rollo, p. 66.
[8] Article 1378, Civil Code.
[9] Exhibit "C-2," RTC records, p. 42.
[10] TSN, December 19, 1985, pp. 6-9.
[11] University of the Philippines v. De los Angeles, 35 SCRA 102, 107, September 29, 1970.
[12] UP v. De los Angeles, supra.
[13] UP v. De los Angeles, supra; Ocejo, Perez & Co. v. International Banking Corp., 37 Phil. 631, 643, February 14, 1918; Republic v. Hospital de San Juan de Dios, 84 Phil. 820, 827, October 31, 1949; Coronel v. Court of Appeals, 263 SCRA 15, 35, October 7, 1996; and Adelfa Properties, Inc. v. Court of Appeals, 240 SCRA 565, 588, January 25, 1988.
[14] Pangilinan v. Court of Appeals, 279 SCRA 590, 597, September 29, 1997.
[15] Exhibit "I-1," Folder of Exhibits.
[16] Power Commercial and Industrial Corporation v. Court of Appeals, 274 SCRA 597, 608, June 20, 1997; Siska Dev’t. Corp. v. Office of the President of the Phil., 231 SCRA 674, 681, April 22, 1994.
[17] Siska Dev’t. Corp. v. Office of the President, supra; Angeles v. Calasanz, 135 SCRA 323, 332, March 18, 1985.
[18] CA Decision, p. 6; rollo, p. 35.
[19] Romero v. Court of Appeals, 250 SCRA 223, 233, November 23, 1995; Pangilinan v. CA, supra, p. 599.
[20] Sps. Lagandaon v. Court of Appeals, GR Nos. 102526-31, May 21, 1998; National Steel Corporation v. Court of Appeals, GR No. 112287, December 12, 1997.
[21] Fuentes v. CA, 268 SCRA 708-709, February 26, 1997.