SECOND DIVISION
[G.R. No. 114323.
July 23, 1998]
OIL AND NATURAL GAS
COMMISSION, petitioner, vs. COURT OF APPEALS and PACIFIC CEMENT COMPANY,
INC. respondents.
D E C I S I O N
MARTINEZ, J.:
This proceeding
involves the enforcement of a foreign judgment rendered by the Civil Judge of
Dehra Dun, India in favor of the petitioner, OIL AND NATURAL GAS COMMISSION and
against the private respondent, PACIFIC CEMENT COMPANY, INCORPORATED.
The petitioner
is a foreign corporation owned and controlled by the Government of India while
the private respondent is a private corporation duly organized and existing
under the laws of the Philippines. The present conflict between the petitioner
and the private respondent has its roots in a contract entered into by and
between both parties on February 26, 1983 whereby the private respondent
undertook to supply the petitioner FOUR THOUSAND THREE HUNDRED (4,300) metric
tons of oil well cement. In consideration therefor, the petitioner bound itself
to pay the private respondent the amount of FOUR HUNDRED SEVENTY-SEVEN THOUSAND
THREE HUNDRED U.S. DOLLARS ($477,300.00) by opening an irrevocable, divisible,
and confirmed letter of credit in favor of the latter. The oil well cement was
loaded on board the ship MV SURUTANA NAVA at the port of Surigao City,
Philippines for delivery at Bombay and Calcutta, India. However, due to a
dispute between the shipowner and the private respondent, the cargo was held up
in Bangkok and did not reach its point of destination. Notwithstanding the fact
that the private respondent had already received payment and despite several
demands made by the petitioner, the private respondent failed to deliver the
oil well cement. Thereafter, negotiations ensued between the parties and they
agreed that the private respondent will replace the entire 4,300 metric tons of
oil well cement with Class “G” cement cost free at the petitioner’s designated
port. However, upon inspection, the Class “G” cement did not conform to the
petitioner’s specifications. The petitioner then informed the private
respondent that it was referring its claim to an arbitrator pursuant to Clause
16 of their contract which stipulates:
“Except where otherwise provided in
the supply order/contract all questions and disputes, relating to the meaning
of the specification designs, drawings and instructions herein before mentioned
and as to quality of workmanship of the items ordered or as to any other
question, claim, right or thing whatsoever, in any way arising out of or
relating to the supply order/contract design, drawing, specification,
instruction or these conditions or otherwise concerning the materials or the
execution or failure to execute the same during stipulated/extended period or
after the completion/abandonment thereof shall be referred to the sole
arbitration of the persons appointed by Member of the Commission at the time of
dispute. It will be no objection to any such appointment that the arbitrator so
appointed is a Commission employer (sic) that he had to deal with the matter to
which the supply or contract relates and that in the course of his duties as
Commission’s employee he had expressed views on all or any of the matter in
dispute or difference.
“The arbitrator to whom the matter
is originally referred being transferred or vacating his office or being unable
to act for any reason the Member of the Commission shall appoint another person
to act as arbitrator in acordance with the terms of the contract/supply order.
Such person shall be entitled to proceed with reference from the stage at which
it was left by his predecessor. Subject as aforesaid the provisions of the
Arbitration Act, 1940, or any Statutary modification or re-enactment there of
and the rules made there under and for the time being in force shall apply to
the arbitration proceedings under this clause.
“The arbitrator may with the
consent of parties enlarge the time, from time to time, to make and publish the
award.
“The venue for arbitration shall be
at Dehra dun.”[1]
On July 23, 1988,
the chosen arbitrator, one Shri N.N. Malhotra, resolved the dispute in
petitioner’s favor setting forth the arbitral award as follows:
“NOW THEREFORE after considering
all facts of the case, the evidence, oral and documentarys adduced by the
claimant and carefully examining the various written statements, submissions,
letters, telexes, etc. sent by the respondent, and the oral arguments addressed
by the counsel for the claimants, I, N.N. Malhotra, Sole Arbitrator, appointed
under clause 16 of the supply order dated 26.2.1983, according to which the
parties, i.e. M/S Oil and Natural Gas Commission and the Pacific Cement Co.,
Inc. can refer the dispute to the sole arbitration under the provision of the
Arbitration Act. 1940, do hereby award and direct as follows:-
“The Respondent will pay the
following to the claimant :-
1. Amount
received by the Respondent
against the letter of credit No. 11/19
dated 28.2.1983 -
- - US $ 477,300.00
2. Re-imbursement
of expenditure incurred
by the claimant on the inspection team’s
visit to
Philippines in August 1985 - - - US$ 3,881.00
3. L.
C. Establishment charges incurred
by the
claimant
- - - US $ 1,252.82
4. Loss
of interest suffered by claimant
from 21.6.83
to 23.7.88 - - - US $ 417,169.95
Total amount of
award - - - US $ 899,603.77
“In addition to the above, the
respondent would also be liable to pay to the claimant the interest at the rate
of 6% on the above amount, with effect from 24.7.1988 upto the actual date of
payment by the Respondent in full settlement of the claim as awarded or the
date of the decree, whichever is earlier.
“I determine the cost at Rs.
70,000/- equivalent to US $5,000 towards the expenses on Arbitration, legal
expenses, stamps duly incurred by the claimant. The cost will be shared by the
parties in equal proportion.
“Pronounced at Dehra Dun to-day,
the 23rd of July 1988.”[2]
To enable the petitioner to execute the above award in its favor, it
filed a Petition before the Court of the Civil Judge in Dehra Dun, India
(hereinafter referred to as the foreign court for brevity), praying that the
decision of the arbitrator be made “the Rule of Court” in India. The foreign
court issued notices to the private respondent for filing objections to the
petition. The private respondent complied and sent its objections dated January
16, 1989. Subsequently, the said court directed the private respondent to pay
the filing fees in order that the latter’s objections could be given
consideration. Instead of paying the required filing fees, the private
respondent sent the following communication addressed to the Civil Judge of
Dehra Dun:
“The Civil Judge
Dehra Dun (U.P.) India
Re: Misc. Case No. 5 of 1989
M/S Pacific Cement Co.,
Inc. vs.
ONGC Case
Sir:
1. We received
your letter dated 28 April 1989 only
last 18 May 1989.
2. Please
inform us how much is the court fee to be paid. Your letter did not mention the
amount to be paid.
3. Kindly give
us 15 days from
receipt of your
letter advising us how much to pay to comply with the same.
Thank you for your kind consideration.
Pacific Cement Co., Inc.
By:
Jose Cortes, Jr.
President"[3]
Without
responding to the above communication, the foreign court refused to admit the
private respondent’s objections for failure to pay the required filing fees,
and thereafter issued an Order on February 7, 1990, to wit:
“ORDER
Since objections filed by defendant
have been rejected through Misc. Suit No. 5 on 7.2.90, therefore, award should
be made “Rule of the Court.
“ORDER
Award dated 23.7.88, Paper No.
3/B-1 is made Rule of the Court. On the basis of conditions of award decree is
passed. Award Paper No. 3/B-1 shall be a part of the decree. The plaintiff
shall also be entitled to get from defendant (US$ 899, 603.77 (US$ Eight Lakhs
ninety nine thousand six hundred and three point seventy seven only) alongwith
9% interest per annum till the last date of realisation.”[4]
Despite notice
sent to the private respondent of the foregoing order and several demands by
the petitioner for compliance therewith, the private respondent refused to pay
the amount adjudged by the foreign court as owing to the petitioner. Accordingly,
the petitioner filed a complaint with Branch 30 of the Regional Trial Court
(RTC) of Surigao City for the enforcement of the aforementioned judgment of the
foreign court. The private respondent moved to dismiss the complaint on the
following grounds: (1) plaintiff’s lack of legal capacity to sue; (2) lack of
cause of action; and (3) plaintiff’s claim or demand has been waived,
abandoned, or otherwise extinguished. The petitioner filed its opposition to
the said motion to dismiss, and the private respondent, its rejoinder thereto.
On January 3, 1992, the RTC issued an order upholding the petitioner’s legal
capacity to sue, albeit dismissing the complaint for lack of a valid cause of
action. The RTC held that the rule prohibiting foreign corporations transacting
business in the Philippines without a license from maintaining a suit in
Philippine courts admits of an exception, that is, when the foreign corporation
is suing on an isolated transaction as in this case.[5] Anent the issue of the sufficiency
of the petitioner’s cause of action, however, the RTC found the referral of the
dispute between the parties to the arbitrator under Clause 16 of their contract
erroneous. According to the RTC,
“[a] perusal of the above-quoted
clause (Clause 16) readily shows that the matter covered by its terms is
limited to “ALL QUESTIONS AND DISPUTES, RELATING TO THE MEANING OF THE
SPECIFICATION, DESIGNS, DRAWINGS AND INSTRUCTIONS HEREIN BEFORE MENTIONED and
as to the QUALITY OF WORKMANSHIP OF THE ITEMS ORDERED or as to any other questions, claim, right or thing whatsoever,
but qualified to ‘IN ANY WAY ARISING OR RELATING TO THE SUPPLY ORDER/CONTRACT,
DESIGN, DRAWING, SPECIFICATION, etc.,’ repeating the enumeration in the opening
sentence of the clause.
“The court is inclined to go along
with the observation of the defendant that the breach, consisting of the
non-delivery of the purchased materials, should have been properly litigated
before a court of law, pursuant to Clause No. 15 of the Contract/Supply Order,
herein quoted, to wit:
‘JURISDICTION
All questions, disputes and
differences, arising under out of or in connection with this supply order,
shall be subject to the EXCLUSIVE JURISDICTION OF THE COURT, within the local
limits of whose jurisdiction and the place from which this supply order is
situated.’”[6]
The RTC characterized the erroneous submission of the dispute to the
arbitrator as a “mistake of law or fact amounting to want of jurisdiction”.
Consequently, the proceedings had before the arbitrator were null and void and
the foreign court had therefore, adopted no legal award which could be the
source of an enforceable right.[7]
The petitioner
then appealed to the respondent Court of Appeals which affirmed the dismissal
of the complaint. In its decision, the appellate court concurred with the RTC’s
ruling that the arbitrator did not have jurisdiction over the dispute between
the parties, thus, the foreign court could not validly adopt the arbitrator’s
award. In addition, the appellate court observed that the full text of the
judgment of the foreign court contains the dispositive portion only and
indicates no findings of fact and law as basis for the award. Hence, the said
judgment cannot be enforced by any Philippine court as it would violate the
constitutional provision that no decision shall be rendered by any court
without expressing therein clearly and distinctly the facts and the law on
which it is based.[8] The appellate court ruled further
that the dismissal of the private respondent’s objections for non-payment of
the required legal fees, without the foreign court first replying to the
private respondent’s query as to the amount of legal fees to be paid,
constituted want of notice or violation of due process. Lastly, it pointed out
that the arbitration proceeding was defective because the arbitrator was
appointed solely by the petitioner, and the fact that the arbitrator was a
former employee of the latter gives rise to a presumed bias on his part in
favor of the petitioner.[9]
A subsequent
motion for reconsideration by the petitioner of the appellate court’s decision
was denied, thus, this petition for review on certiorari citing the
following as grounds in support thereof:
“RESPONDENT COURT OF APPEALS GRAVELY ERRED IN AFFIRMING THE LOWER
COURT’S ORDER OF DISMISSAL SINCE:
A. THE
NON-DELIVERY OF THE CARGO WAS A MATTER PROPERLY COGNIZABLE BY THE PROVISIONS OF
CLAUSE 16 OF THE CONTRACT;
B. THE
JUDGMENT OF THE CIVIL COURT OF DEHRADUN, INDIA WAS AN AFFIRMATION OF THE FACTUAL
AND LEGAL FINDINGS OF THE ARBITRATOR AND THEREFORE ENFORCEABLE IN THIS
JURISDICTION;
C. EVIDENCE
MUST BE RECEIVED TO REPEL THE EFFECT OF A PRESUMPTIVE RIGHT UNDER A FOREIGN
JUDGMENT.”[10]
The threshold
issue is whether or not the arbitrator had jurisdiction over the dispute
between the petitioner and the private respondent under Clause 16 of the
contract. To reiterate, Clause 16 provides as follows:
“Except where otherwise provided in
the supply order/contract all questions and disputes, relating to the meaning
of the specification designs, drawings and instructions herein before mentioned
and as to quality of workmanship of the items ordered or as to any other
question, claim, right or thing whatsoever, in any way arising out of or
relating to the supply order/contract design, drawing, specification,
instruction or these conditions or otherwise concerning the materials or the
execution or failure to execute the same during stipulated/extended period or
after the completion/abandonment thereof shall be referred to the sole
arbitration of the persons appointed by Member of the Commission at the time of
dispute. It will be no objection to any such appointment that the arbitrator so
appointed is a Commission employer (sic) that he had to deal with the matter to
which the supply or contract relates and that in the course of his duties as
Commission’s employee he had expressed views on all or any of the matter in
dispute or difference.”[11]
The dispute
between the parties had its origin in the non-delivery of the 4,300 metric tons
of oil well cement to the petitioner. The primary question that may be posed,
therefore, is whether or not the non-delivery of the said cargo is a proper
subject for arbitration under the above-quoted Clause 16. The petitioner
contends that the same was a matter within the purview of Clause 16,
particularly the phrase, “x x x or as to any other questions, claim, right
or thing whatsoever, in any way arising or relating to the supply
order/contract, design, drawing, specification, instruction x x x”.[12] It is argued that the foregoing
phrase allows considerable latitude so as to include non-delivery of the cargo
which was a “claim, right or thing relating to the supply order/contract”. The
contention is bereft of merit. First of all, the petitioner has misquoted the
said phrase, shrewdly inserting a comma between the words “supply
order/contract” and “design” where none actually exists. An accurate
reproduction of the phrase reads, “x x x or as to any other question, claim,
right or thing whatsoever, in any way arising out of or relating to the supply
order/contract design, drawing, specification, instruction or these conditions
x x x”. The absence of a comma between the words “supply order/contract” and
“design” indicates that the former cannot be taken separately but should be
viewed in conjunction with the words “design, drawing, specification,
instruction or these conditions”. It is thus clear that to fall within the
purview of this phrase, the “claim, right or thing whatsoever” must arise out
of or relate to the design, drawing, specification, or instruction of the
supply order/contract. The petitioner also insists that the non-delivery of the
cargo is not only covered by the foregoing phrase but also by the phrase, “x x
x or otherwise concerning the materials or the execution or failure to
execute the same during the stipulated/extended period or after
completion/abandonment thereof x x x”.
The doctrine of noscitur
a sociis, although a rule in the construction of statutes, is equally
applicable in the ascertainment of the meaning and scope of vague contractual
stipulations, such as the aforementioned phrase. According to the maxim noscitur
a sociis, where a particular word or phrase is ambiguous in itself or is
equally susceptible of various meanings, its correct construction may be made
clear and specific by considering the company of the words in which it is found
or with which it is associated, or stated differently, its obscurity or doubt
may be reviewed by reference to associated words.[13] A close examination of Clause 16
reveals that it covers three matters which may be submitted to arbitration
namely,
(1) all questions and disputes,
relating to the meaning of the specification designs, drawings and instructions
herein before mentioned and as to quality of workmanship of the items ordered;
or
(2) any other question, claim,
right or thing whatsoever, in any way arising out of or relating to the supply
order/contract design, drawing, specification, instruction or these conditions;
or
(3) otherwise concerning the
materials or the execution or failure to execute the same during
stipulated/extended period or after the completion/abandonment thereof.
The first and
second categories unmistakably refer to questions and disputes relating to the
design, drawing, instructions, specifications or quality of the materials of
the supply/order contract. In the third category, the clause, “execution or
failure to execute the same”, may be read as “execution or failure to execute
the supply order/contract”. But in accordance with the doctrine of noscitur
a sociis, this reference to the supply order/contract must be construed in
the light of the preceding words with which it is associated, meaning to say,
as being limited only to the design, drawing, instructions, specifications or
quality of the materials of the supply order/contract. The non-delivery of the
oil well cement is definitely not in the nature of a dispute arising from the
failure to execute the supply order/contract design, drawing, instructions,
specifications or quality of the materials. That Clause 16 should pertain only
to matters involving the technical aspects of the contract is but a logical
inference considering that the underlying purpose of a referral to arbitration
is for such technical matters to be deliberated upon by a person possessed with
the required skill and expertise which may be otherwise absent in the regular
courts.
This Court
agrees with the appellate court in its ruling that the non-delivery of the oil
well cement is a matter properly cognizable by the regular courts as stipulated
by the parties in Clause 15 of their contract:
“All questions, disputes and differences, arising under out of or in
connection with this supply order, shall be subject to the exclusive
jurisdiction of the court, within the local limits of whose jurisdiction
and the place from which this supply order is situated.”[14]
The following fundamental principles in the interpretation of contracts
and other instruments served as our guide in arriving at the foregoing
conclusion:
"ART. 1373. If some
stipulation of any contract should admit of several meanings, it shall be
understood as bearing that import which is most adequate to render it
effectual."[15]
“ART. 1374. The various
stipulations of a contract shall be interpreted together, attributing to the
doubtful ones that sense which may result from all of them taken jointly”.[16]
“Sec. 11. Instrument construed
so as to give effect to all provisions. In the construction of an
instrument, where there are several provisions or particulars, such a
construction is, if possible, to be adopted as will give effect to all.”[17]
Thus, this Court
has held that as in statutes, the provisions of a contract should not be read
in isolation from the rest of the instrument but, on the contrary, interpreted
in the light of the other related provisions.[18] The whole and every part of a
contract must be considered in fixing the meaning of any of its parts and in
order to produce a harmonious whole. Equally applicable is the canon of
construction that in interpreting a statute (or a contract as in this case),
care should be taken that every part thereof be given effect, on the theory
that it was enacted as an integrated measure and not as a hodge-podge of
conflicting provisions. The rule is that a construction that would render a
provision inoperative should be avoided; instead, apparently inconsistent
provisions should be reconciled whenever possible as parts of a coordinated and
harmonious whole.[19]
The petitioner’s
interpretation that Clause 16 is of such latitude as to contemplate even the
non-delivery of the oil well cement would in effect render Clause 15 a mere superfluity. A perusal of Clause 16
shows that the parties did not intend arbitration to be the sole means of
settling disputes. This is manifest from Clause 16 itself which is prefixed
with the proviso, “Except where otherwise provided in the supply order/contract
x x x”, thus indicating that the jurisdiction of the arbitrator is not all
encompassing, and admits of exceptions as may be provided elsewhere in the
supply order/contract. We believe that the correct interpretation to give
effect to both stipulations in the contract is for Clause 16 to be confined to
all claims or disputes arising from or relating to the design, drawing,
instructions, specifications or quality of the materials of the supply
order/contract, and for Clause 15 to cover all other claims or disputes.
The petitioner
then asseverates that granting, for the sake of argument, that the non-delivery
of the oil well cement is not a proper subject for arbitration, the failure of
the replacement cement to conform to the specifications of the contract is a
matter clearly falling within the ambit of Clause 16. In this contention, we
find merit. When the 4,300 metric tons of oil well cement were not delivered to
the petitioner, an agreement was forged between the latter and the private
respondent that Class “G” cement would be delivered to the petitioner as
replacement. Upon inspection, however, the replacement cement was rejected as
it did not conform to the specifications of the contract. Only after this
latter circumstance was the matter brought before the arbitrator. Undoubtedly,
what was referred to arbitration was no longer the mere non-delivery of the
cargo at the first instance but also the failure of the replacement cargo to
conform to the specifications of the contract, a matter clearly within the
coverage of Clause 16.
The private
respondent posits that it was under no legal obligation to make replacement and
that it undertook the latter only “in the spirit of liberality and to foster
good business relationship”.[20] Hence, the undertaking to deliver
the replacement cement and its subsequent failure to conform to specifications
are not anymore subject of the supply order/contract or any of the provisions
thereof. We disagree.
As per Clause 7
of the supply order/contract, the private respondent undertook to deliver the
4,300 metric tons of oil well cement at “BOMBAY (INDIA) 2181 MT and CALCUTTA
2119 MT”.[21] The failure of the private
respondent to deliver the cargo to the designated places remains undisputed.
Likewise, the fact that the petitioner had already paid for the cost of the
cement is not contested by the private respondent. The private respondent
claims, however, that it never benefited from the transaction as it was not
able to recover the cargo that was unloaded at the port of Bangkok.[22] First of all, whether or not the
private respondent was able to recover the cargo is immaterial to its
subsisting duty to make good its promise to deliver the cargo at the stipulated
place of delivery. Secondly, we find it difficult to believe this
representation. In its Memorandum filed before this Court, the private
respondent asserted that the Civil Court of Bangkok had already ruled that the
non-delivery of the cargo was due solely to the fault of the carrier.[23] It is, therefore, but logical to
assume that the necessary consequence of this finding is the eventual recovery
by the private respondent of the cargo or the value thereof. What inspires
credulity is not that the replacement was done in the spirit of liberality but
that it was undertaken precisely because of the private respondent’s
recognition of its duty to do so under the supply order/contract, Clause 16 of
which remains in force and effect until the full execution thereof.
We now go to the
issue of whether or not the judgment of the foreign court is enforceable in
this jurisdiction in view of the private respondent’s allegation that it is
bereft of any statement of facts and law upon which the award in favor of the
petitioner was based. The pertinent portion of the judgment of the foreign
court reads:
“ORDER
Award dated 23.7.88, Paper No.
3/B-1 is made Rule of the Court. On the basis of conditions of award decree is
passed. Award Paper No. 3/B-1 shall be a part of the decree. The plaintiff shall also be entitled to get from
defendant ( US$ 899, 603.77 (US$ Eight Lakhs ninety nine thousand six hundred
and three point seventy seven only) alongwith 9% interest per annum till the
last date of realisation.”[24]
As specified in
the order of the Civil Judge of Dehra Dun, “Award Paper No. 3/B-1 shall be a
part of the decree”. This is a categorical declaration that the foreign court
adopted the findings of facts and law of the arbitrator as contained in the
latter’s Award Paper. Award Paper No. 3/B-1, contains an exhaustive discussion
of the respective claims and defenses of the parties, and the arbitrator’s
evaluation of the same. Inasmuch as the foregoing is deemed to have been
incorporated into the foreign court’s judgment the appellate court was in error
when it described the latter to be a “simplistic decision containing literally,
only the dispositive portion”.[25]
The
constitutional mandate that no decision shall be rendered by any court without
expressing therein clearly and distinctly the facts and the law on which it is
based does not preclude the validity of “memorandum decisions” which adopt by
reference the findings of fact and conclusions of law contained in the
decisions of inferior tribunals. In Francisco v. Permskul,[26] this Court held that the following
memorandum decision of the Regional Trial Court of Makati did not transgress
the requirements of Section 14, Article VIII of the Constitution:
“MEMORANDUM DECISION
After a careful perusal, evaluation
and study of the records of this case, this Court hereby adopts by reference
the findings of fact and conclusions of law contained in the decision of the
Metropolitan Trial Court of Makati, Metro Manila, Branch 63 and finds that
there is no cogent reason to disturb the same.
“WHEREFORE, judgment appealed from
is hereby affirmed in toto.”[27] (Underscoring
supplied.)
This Court had occasion to make a similar pronouncement in the earlier
case of Romero v. Court of Appeals,[28] where the assailed decision of the
Court of Appeals adopted the findings and disposition of the Court of Agrarian
Relations in this wise:
“We have, therefore, carefully
reviewed the evidence and made a re-assessment of the same, and We are
persuaded, nay compelled, to affirm the correctness of the trial court’s
factual findings and the soundness of its conclusion. For judicial
convenience and expediency, therefore, We hereby adopt by way of reference, the
findings of facts and conclusions of the court a quo spread in its
decision, as integral part of this Our decision.”[29] (Underscoring
supplied)
Hence, even in this jurisdiction, incorporation by reference is allowed
if only to avoid the cumbersome reproduction of the decision of the lower
courts, or portions thereof, in the decision of the higher court.[30] This is particularly true when the
decision sought to be incorporated is a lengthy and thorough discussion of the
facts and conclusions arrived at, as in this case, where Award Paper No. 3/B-1
consists of eighteen (18) single spaced pages.
Furthermore, the
recognition to be accorded a foreign judgment is not necessarily affected by
the fact that the procedure in the courts of the country in which such judgment
was rendered differs from that of the courts of the country in which the
judgment is relied on.[31] This Court has held that matters of
remedy and procedure are governed by the lex fori or the internal law of
the forum.[32] Thus, if under the procedural rules
of the Civil Court of Dehra Dun, India, a valid judgment may be rendered by
adopting the arbitrator’s findings, then the same must be accorded respect. In the same vein, if the procedure in the foreign
court mandates that an Order of the Court becomes final and executory upon
failure to pay the necessary docket fees, then the courts in this jurisdiction
cannot invalidate the order of the foreign court simply because our rules
provide otherwise.
The private
respondent claims that its right to due process had been blatantly violated,
first by reason of the fact that the foreign court never answered its queries
as to the amount of docket fees to be paid then refused to admit its objections
for failure to pay the same, and second, because of the presumed bias on the
part of the arbitrator who was a former employee of the petitioner.
Time and again
this Court has held that the essence of due process is to be found in the
reasonable opportunity to be heard and submit any evidence one may have in
support of one’s defense[33] or stated otherwise, what is
repugnant to due process is the denial of opportunity to be heard.[34] Thus, there is no violation of due
process even if no hearing was conducted, where the party was given a chance to
explain his side of the controversy and he waived his right to do so.[35]
In the instant
case, the private respondent does not deny the fact that it was notified by the
foreign court to file its objections to the petition, and subsequently, to pay
legal fees in order for its objections to be given consideration. Instead of
paying the legal fees, however, the private respondent sent a communication to
the foreign court inquiring about the correct amount of fees to be paid. On the
pretext that it was yet awaiting the foreign court’s reply, almost a year
passed without the private respondent paying the legal fees. Thus, on February
2, 1990, the foreign court rejected the objections of the private respondent
and proceeded to adjudicate upon the petitioner’s claims. We cannot subscribe
to the private respondent’s claim that the foreign court violated its right to
due process when it failed to reply to its queries nor when the latter rejected
its objections for a clearly meritorious ground. The private respondent was
afforded sufficient opportunity to be heard. It was not incumbent upon the
foreign court to reply to the private respondent’s written communication. On
the contrary, a genuine concern for its cause should have prompted the private respondent
to ascertain with all due diligence the correct amount of legal fees to be
paid. The private respondent did not act with prudence and diligence thus its
plea that they were not accorded the right to procedural due process cannot
elicit either approval or sympathy from this Court.[36]
The private
respondent bewails the presumed bias on the part of the arbitrator who was a
former employee of the petitioner. This point deserves scant consideration in
view of the following stipulation in the contract:
“x x x. It
will be no objection to any such appointment that the arbitrator so appointed
is a Commission employer (sic) that he had to deal with the matter to which the
supply or contract relates and that in the course of his duties as Commission’s
employee he had expressed views on all or any of the matter in dispute or
difference.”[37] (Underscoring supplied.)
Finally, we
reiterate hereunder our pronouncement in the case of Northwest Orient
Airlines, Inc. v. Court of Appeals[38] that:
“A foreign judgment is presumed to
be valid and binding in the country from which it comes, until the contrary is
shown. It is also proper to presume the regularity of the proceedings and the
giving of due notice therein.
“Under Section 50, Rule 39 of the
Rules of Court, a judgment in an action in personam of a tribunal of a foreign
country having jurisdiction to pronounce the same is presumptive evidence of a
right as between the parties and their successors-in-interest by a subsequent
title. The judgment may, however, be assailed by evidence of want of
jurisdiction, want of notice to the party, collusion, fraud, or clear mistake
of law or fact. Also, under Section 3 of Rule 131, a court, whether of the
Philippines or elsewhere, enjoys the presumption that it was acting in the
lawful exercise of jurisdiction and has regularly performed its official duty.”[39]
Consequently, the party attacking a foreign judgment, the private
respondent herein, had the burden of overcoming the presumption of its validity
which it failed to do in the instant case.
The foreign
judgment being valid, there is nothing else left to be done than to order its
enforcement, despite the fact that the petitioner merely prays for the remand
of the case to the RTC for further proceedings. As this Court has ruled on the
validity and enforceability of the said foreign judgment in this jurisdiction,
further proceedings in the RTC for the reception of evidence to prove otherwise
are no longer necessary.
WHEREFORE, the instant petition is GRANTED, and
the assailed decision of the Court of Appeals sustaining the trial court’s
dismissal of the OIL AND NATURAL GAS COMMISSION’s complaint in Civil Case No.
4006 before Branch 30 of the RTC of Surigao City is REVERSED, and another in
its stead is hereby rendered ORDERING private respondent PACIFIC CEMENT
COMPANY, INC. to pay to petitioner the amounts adjudged in the foreign judgment
subject of said case.
SO ORDERED.
Regalado,
(Chairman), Melo, and
Puno, JJ., concur.
Mendoza, J., no part, having
taken part in the consideration of this case below.
[1]
Supply Order Contract, ANNEX “C” to PETITION in G.R. No. 114323, p. 5; Rollo,
p. 114.
*Note: The contract and the foreign judgments per
awards by the Indian courts follow the British spelling of words for which sic
will no longer be indicated.
[2]
Arbitral Award dated July 23, 1988, ANNEX “D” of the Petition, p. 17; Rollo,
p. 143-144.
[3]
DECISION in CA-G.R. CV NO. 37080 promulgated on October 29, 1993, p. 10;
Rollo, p. 103; RTC Records, pp. 143-144.
[4]
ANNEX “F” of the Petition; Rollo, p. 157.
[5]
ORDER in Civil Case No. 4006, ANNEX “G” of the Petition, p. 1; Rollo,
p. 158.
[6]
Ibid., p. 4; Rollo, p. 161.
[7]
Ibid., p. 5; Rollo, p. 162.
[8]
Article VIII, Section 14 of the 1987 Constitution.
[9]
CA Decision, Supra, pp. 8-12; Rollo, pp. 101-105.
[10]
Petition, Supra, p. 9; Rollo, p. 73.
[11]
See Supply Order Contract.
[12]
Petition, Supra, pp. 11-12; Rollo, pp. 75-76.
[13]
Motoomul, et al. vs. Dela Paz, et al., 187 SCRA 743, 753
[1990]; Luzon Stevedoring Co. vs. Trinidad, 43 Phil. 804 [1922].
[14]
Terms and Conditions of Supply Order, “ANNEX C-1” of the Petition, p. 8;
Rollo, p. 125-126; RTC Records, pp. 17-26.
[15]
Article 1373 of the Civil Code.
[16]
Article 1374 of the Civil Code.
[17]
Rule 130, Section 11 of the Rules of Court.
[18]
De Leon vs. Court of Appeals, 205 SCRA 612, 620 [1992].
[19]
JMM Promotions & Management, Inc. vs. NLRC, 228 SCRA 129, 134
[1993].
[20]
Private Respondent’s Memorandum in G.R. No. 114323, p. 17.
[21]
Supra, Supply Order, p. 2; Rollo, p. 110.
[22]
Supra, Private Respondent’s Memorandum, p. 18.
[23]
Ibid.
[24]
Court of Dehra Dun, Suit No. 677 of 1988, ONGC vs. Pacific
Cement, 7-2-90; Rollo, p. 157.
[25]
CA Decision.
[26]
173 SCRA 324 [1989].
[27]
Ibid., p. 326.
[28]
147 SCRA 183 [1987].
[29]
Ibid., p. 189.
[30]
Francisco v. Permskul, 173 SCRA 324, 333.
[31]
Francisco, Vicente J., The Revised RULES OF COURT in the Philippines,
Volume II, pp. 891-892, 1966 ed. citing 31 Am. Jur. 153-154.
[32]
Northwest Orient Airlines, Inc. vs. Court of Appeals, 241 SCRA
192, 199 [1995].
[33]
Roces vs. Aportadera, 243 SCRA 108 [1995]; Mutuc vs. Court
of Appeals, 190 SCRA 43, 49 [1990]; Richards vs. Asoy, 152 SCRA 45
[1987]; Tajonera vs. Lamaroza, 110 SCRA 438 [1981].
[34]
Korean Airlines Co., Ltd. vs. Court of Appeals, 247 SCRA 599, 603
[1995].
[35]
Roces vs. Aportadera, supra, p. 114; Stayfast Sunset View
Condominium Corporation vs. NLRC, 228 SCRA 466 [1993]; Villareal vs. Court
of Appeals, 219 SCRA 292 [1993].
[36]
B.R. Sebastian Enterprises, Inc. vs. Court of Appeals, 206 SCRA
28 [1992].
[37]
Supply Order, Supra.
[38]
241 SCRA 192, 199 [1995].
[39]
Ibid.