THIRD DIVISION
[G.R. No. 122196. January 15, 1997]
F. F. MAÑACOP CONSTRUCTION CO., INC., petitioner, vs.
COURT OF APPEALS and THE MANILA INTERNATIONAL AIRPORT AUTHORITY, respondents.
D E C I S I O N
FRANCISCO, J.:
The undisputed facts are as follows:
"Sometime in September, 1995, petitioner started with the construction
of a perimeter fence along the MIA road from Asia Overseas, Inc. up to Airscope
Development Corporation for and in consideration of the quoted price of
P307,440.00. Because of the urgency of building the said fence which was to
prevent would be squatters from entering the area, petitioner proceeded with
the fence construction even if the Notice to Proceed was not yet signed by the
general manager[1]
of private respondent[2] but already initialed by its Asst. Project
Manager.[3] After the February, 1986 revolution,
however, the new general manager[4] of private respondent stopped the
construction of the said fence. By that time 95% was finished which was worth
P282,068.00 as computed by petitioner. Petitioner made repeated demands for the
payment of what it has completed but private respondent ignored said demands.
After two years of making demands for payment which, as aforesaid, were simply
ignored by private respondent, petitioner decided to bring the matter to court
and thus incurred attorney's fees in the process.
"In court, the issues were limited to whether or not petitioner had done works for the private respondent and whether or not the same was authorized.
"In order to prove that petitioner rendered services to
private respondent, petitioner presented Engr. Angelito Gonzales who testified
that indeed fence was constructed for private respondent in accordance with
plans therefor (Exh. "C") and pictures had been taken of the fence
(Exhs. "N" to "N-3") and the certification of the supplier
as to the materials used by petitioner in constructing the fence and the price
thereof.
"Private respondent presented no evidence whatever (sic)
despite the chances[5] given to it by the trial court, one of which
evidence would have consisted of a testimony from the COA[6] on what should be the expenses involved in
the construction of said fence.
"After the repeated failure of private respondent to present its evidence, the trial court rendered a decision wherein it is found that for the services rendered by the petitioner it should be paid P238,501.48 based upon a quantum meruit since there is an absence of a written contract between the parties. Said amount is the latest evaluation of the work done which evaluation was made by private respondent itself. Likewise, the trial court ordered private respondent to pay petitioner attorney's fees since there is reason to believe that private respondent acted in bad faith in refusing to comply with the repeated demands of petitioner for payment for two long years.
"On appeal to the respondent court, the private respondent
assigned the error that the trial court should have referred the computation of
what should be paid to petitioner to the COA pursuant to what was done in the
case of Eslao v. Commission on Audit, 195 SCRA 730. The petitioner
refuted this assigned error by pointing out that it is not one of the issues
raised before the trial court.
"In its decision dated September 8, 1995, the Court of Appeals
agreed that petitioner rendered services to private respondent for which it
should be paid but set aside the entire decision of the trial court
directing the latter to refer the computation of what should be paid to
petitioner to the COA as done in the case of Eslao v. Commission on Audit.
"A motion for reconsideration of the aforesaid decision proved
futile."[7]
Petitioner comes to this Court via petition for review
under Rule 45 arguing that the Court of Appeals (CA) erred in taking cognizance
of the issue of referring the matter to the COA to determine the amount due to
petitioner by relying on Eslao v. COA and Royal Trust Co. vs. COA[8], which issue was raised for the first time
on appeal. The Court gave due course to the petition and required the parties
to submit their respective memoranda. Petitioner complied while private respondent
adopted its comment as memorandum.
Well-recognized jurisprudence precludes raising an issue only for
the first time on appeal,[9] as it would be offensive to the basic rules
of fair play and justice to allow private respondent to raise a question not
ventilated before the court a quo.[10] There is no dispute that the issue of
whether the matter should be referred to the COA was not raised in the lower
court. Thus, technically, respondent court should not have taken cognizance of
the same. However, considering that the issue of reference is a matter closely
related to the determination of the question on how much is exactly due to
petitioner, the court may consider the former issue for a just and complete
resolution of the case.[11] Besides, the present case involves the
disposition of public funds and calls for the performance of a constitutional
duty of the COA which should not be defeated by mere technicalities of
procedure.
Proceeding to the merits, it is not disputed that Petitioner is
entitled to payment for the construction it made, which arose from a quasi-contractual
relation created between the former and private respondent. But should
petitioner be paid based on quantum meruit?
The issue was answered in the affirmative in the case of Eslao.
We find no reason to depart from such ruling due to the following reasons:
First, the instant quasi-contract is neither fraudulent nor mala in
se. Second, the project was already covered by a specific appropriation.[12] Third, as in private contracts, the facts
show that an implied obligation to pay would be imposed upon the government.
Fourth, the property or benefit is not ultra vires, i.e. they can be the
proper subject of an express contract and are within the contractual powers of
the public body. Fifth, the case falls within the exemption from the mandatory
procedure of public bidding which is dispensed with on the ground of public
necessity,[13] or when time is of the essence,[14] and considering that the subject project was
contiguous to an on going project[15] performed by petitioner and there is no
proof of any unsatisfactory performance or negative slippage.[16] Sixth, the contractor substantially complied
(95% complete) in good faith with its obligation and no intentional departure from
the specifications were alleged. Seventh, petitioner's claim is clearly
supported by equity. Private respondent is reaping benefits from the scallop
fence and wire placed by petitioner. Eighth, there is no proof of any collusion
among the parties involved. Finally, the payment is limited to the actual cost
chargeable against funds authorized and certified for the purpose. All these
circumstances, taken together, negate fraud and collusion.[17]
Citing the cases of Eslao and Royal Trust, the Solicitor General, on behalf of private respondent argues that the matter should be referred to the COA.
Such argument is without merit. Quantum meruit allows recovery of
the reasonable value regardless of any agreement as to value. It entitles the
party to "as much as he reasonably deserves,"[18] as distinguished from quantum valebant
or to "as much as what is reasonably worth."
Unliquidated claims present a justiciable question ripe for
judicial determination which is beyond the powers of the COA to adjudicate.[19] Recovery based on quantum meruit is
in the nature of such claim because its settlement requires the application of
judgment and discretion and cannot be adjusted by simple arithmetical
processes. In the cases of Eslao and Royal Trust, the Court found
it necessary to refer to the COA the task of determining the total compensation
due to the claimants considering that the matter on the exact amount was not at
issue[20] and the determination thereof involves a
review of the factual findings and evidence in support thereof. On the other
hand, the lower court in this case, had already made a factual finding on the
amount reasonably due to petitioner and scrutinized the evidence to sustain the
claim. Besides, there is nothing in the cited cases which would imply that only
the COA can determine the specific amount due to a contractor guided by the
equitable principle of quantum meruit. As our courts are both courts of
law and equity, they are not powerless to determine a factual matter in
accordance with both standards.
With respect to the award of attorney's fees, the same is
premised on the uncontroverted factual finding of the lower court, as affirmed
by respondent appellate court, that private respondent acted in bad faith in
refusing payment to petitioner. Such factual findings are not only accorded
great weight, but finality as well, since they are supported by substantial
evidence.[21] No reason appears in this case that would
justify departure from the above doctrine.
WHEREFORE, the decision of the Court of Appeals is SET ASIDE
and the decision of the Regional Trial Court dated May 4, 1992 is REINSTATED.
SO ORDERED.
Narvasa, C.J. (Chairman), Davide, Jr., Melo, and Panganiban, JJ., concur.
[1] Luis Tabuena, (Rollo,
p. 70).
[2] Renamed as the Ninoy
Aquino International Airport (NAIA), (Rollo, p. 8).
[3] Elpidio L. Mendoza,
(Rollo, p. 70).
[4] Luis Tabuena was
replaced by Romeo Santos who was in turn replaced by Reli German, (Rollo,
p. 9).
[5] The RTC gave private
respondent at least (4) opportunities to present their evidence but the latter still
failed to avail of such opportunities for undisclosed reasons.
[6] Commission on Audit.
[7] Rollo, pp.
127-129.
[8] G.R. No. 84202,
November 23, 1988 (Resolution of the Court en banc, cited in Eslao vs. COA, 195
SCRA 730 (1991).
[9] Manila Bay Club vs. CA,
[resolution] 249 SCRA 303 (1995); Republic vs. NLRC, 314 Phil. 507 (1995).
[10] See Lopez Realty,
Inc. vs. Fontecha, 247 SCRA 183 (1995); Manila Bay Club vs. CA,
[Decision] 315 Phil. 805 (1995); C. Alcantara & Sons, Inc. vs. NLRC,
229 SCRA 109 (1994); Ravelo vs. CA, 207 SCRA 254 (1992); Anchuelo vs.
IAC, 147 SCRA 434 (1987).
[11] Garrido v.
CA, 236 SCRA 450 (1994).
[12] An amount of
P313,325.28 was appropriated for the reinforcement of the fence. (Rollo,
p. 45).
[13] Section 9, B.P. 132 (Public Works Appropriations Act) provides:
"Negotiated contracts — Pursuant to the general policy
of undertaking projects by contract after public bidding, no project covered by
appropriations in this act shall be prosecuted by negotiated contract except: x
x x ; (b) in case of urgent necessity or emergency or danger to life and
property; x x x : Provided,
that no negative slippage exceeding ten per centum (10%) is incurred by the
contractor in any of his on-going projects: Provided, further, That the
additional work is within his contracting capabilities. x x x " (emphasis
supplied).
[14] Section 4, P.D. 1594 as amended provides:
"Bidding. — Construction projects shall generally be
undertaken by contract after competitive public bidding. Projects may be
undertaken by administration or force account or by negotiated contract only in
exceptional cases where time is of the essence, or where there is lack of
qualified bidders or contractors, or where there is a conclusive evidence that
greater economy and efficiency would be achieve through this arrangement, and
in accordance with provisions of laws and acts on the matter, subject to the
approval of the Minister of Public Works, Transportation and Communications,
the Minister of Public Highways, or the Minister of Energy, as the case may be,
if the project cost is less than P1 million, and the President of the
Philippines, upon recommendation of the Minister, if the project cost is P1
million or more.
[15] Petitioner was under
contract with private respondent and was actually fencing the MIAA Engineering
compound at the time the latter asked the former to perform the project subject
of this case. (Rollo, p. 44).
[16] IB 10.4.2, Implementing Rules and Regulations of P.D. 1594, as amended provides:
"1. Negotiated contract may be entered into only where any of the following conditions exist and the implementing office/agency/corporation is not capable of undertaking the project by administration:
xxx xxx xxx
c. Where the subject project is adjacent or contiguous to an ongoing project and it could be economically prosecuted by the same contractor, in which case, direct negotiation may be undertaken with the said contractor at the same unit prices and contract conditions, less mobilization cost, provided that he has no negative slippage and has demonstrated a satisfactory performance. (italics ours).
xxx xxx xxx."
[17] Rivera v.
Municipality of Malolos, 102 Phil. 285, 291 (1957).
[18] Caughlan v.
International Longshoremen's and Warehousemen's Union, 78 A.L. R. 2d 313;
Jackson v. City of Gastonia, 100 S.E. 2d 241, 243; Lockard v.
City of Salem, 43 S.E. 2d 239 244, 130 W. Va. 287; Mead v. Ringling, 64
N. W. 2d 222, 225; American-Hawaiian Engineering and Construction Co. v.
Butler, 165 Cal. App. 497 cited in 17 Am Jur 2d Contracts, Sec. 583.
[19] See Phil.
Operations, Inc. v. Auditor-General, 94 Phil. 868 (1954).
[20] The issue in the
cited cases is whether the contractors were entitled to any payment.
[21] See Far East Bank v.
CA, G.R. No. 123569, April 1, 1996; Acevedo Optical v. CA, 250 SCRA 409
(1995); Salvador v. CA, supra.; Alforte v. Santos, 313
Phil. 384 (1995); Chua v. CA, 312 Phil. 857 (1995); Tay v. CA,
312 Phil. 1128 (1995); Meneses v. CA, 246 SCRA 162.